Running Magellan Cloud at NERSC, Run 11

Running Magellan Cloud at NERSC


Fig 1. General scheme of allocation of resources and connections between machines

Fig 2. Specific implementation of the propagation of STAR DB snapshots, external DB monitoring is abandoned

 

Task In Charge To Do Blocks ERT
Increase /mnt to 100GB  Iwona Check if possible and reconfigure Eucalyptus   Done
Establish # and target to scp data from  Iwona Test scp from /global/scrtach to VM against possible carver nodes supporting /global/scratch. Move Eucalyptus to the set of public IPs registered in DNS.  2011/01/14
Integration of transfer of DAQ file using FastOffline workflow  Jerome Current scheme restore 100 files max every 6 hours. Need transfer from BNL->Cloud+delete files etc ... None 2011/02/08