Shutdown schedule

FY04

Project Start Date: Fri 1/2/04
Project Finish Date: Mon 10/25/04

STAR FY04 v3 Shutdown


ID
Name
DurationStart_DateFinish_DateResource_NamesPredecessorsSuccessors
1
STAR Detector Operations
211.35 daysMon 1/5/04Mon 10/25/04   
2
Physics Run FY04
96 daysMon 1/5/04Sat 5/15/04  5FF
3
Start Shutdown Activities
116.35 daysSat 5/15/04Mon 10/25/04   
4
Move Detector into AB
14.6 daysSat 5/15/04Thu 6/3/04   
5
Purge TPC Gas
1 daySat 5/15/04Sat 5/15/04 2FF6SS
6
Subsystem Testing
6 daysSat 5/15/04Fri 5/21/04 5SS7
7
Retract PMD Detector
0.1 daysMon 5/24/04Mon 5/24/04Mech.Tech.68
8
Remove East BBC Detector
0.25 daysMon 5/24/04Mon 5/24/04Mech.Tech.79
9
Retract East Pole Tip
0.5 daysMon 5/24/04Mon 5/24/04Mech.Tech.[2]810FF
10
Install Scaffold
0.25 daysMon 5/24/04Mon 5/24/04Carpenter[2]9FF12,11
11
Remove Shield Wall
2.5 daysMon 5/24/04Thu 5/27/04Riggers[3]1026,23,16SS,18,135
12
Remove West Pole Tip Utilities
0.25 daysMon 5/24/04Tue 5/25/04Mech.Tech.1013
13
Remove West BBC Detector
0.25 daysTue 5/25/04Tue 5/25/04Mech.Tech.1214
14
Retract West Pole Tip
0.5 daysTue 5/25/04Tue 5/25/04Mech.Tech.[2]1315FF
15
Install Scaffold
0.13 daysTue 5/25/04Tue 5/25/04Carpenter[2]14FF 
16
Disconnect Electrical Power
0.5 daysMon 5/24/04Tue 5/25/04Electrician[2]11SS18,17
17
Disconnect Magnet Power
0.5 daysTue 5/25/04Tue 5/25/04Elect.Tech.[2]1618
18
Remove Buss Bridge
0.25 daysThu 5/27/04Thu 5/27/04Mech.Tech.[2]16,17,1119,21
19
Disconnect Platform MCWS
0.5 daysThu 5/27/04Fri 5/28/04Mech.Tech.1820
20
Disconnect Subsystems Utilities
1 dayFri 5/28/04Mon 5/31/04Mech.Tech.1926
21
Remove Platform Bridge
0.25 daysThu 5/27/04Thu 5/27/04Mech.Tech.[2]1826,22
22
Remove South Platform Stairs
0.25 daysThu 5/27/04Fri 5/28/04Mech.Tech.[2]2126,24
23
Disconnect RHIC Vacuum Pipe
0.5 daysThu 5/27/04Thu 5/27/04Mech.Tech.11 
24
Remove Seismic Anchors
0.25 daysFri 5/28/04Fri 5/28/04Mech.Tech.[2]2225
25
Disconnect Magnet LCW
0.25 daysFri 5/28/04Fri 5/28/04Mech.Tech.[2]2426
26
Roll Detector into AB
1 dayMon 5/31/04Tue 6/1/04Mech.Tech.[2]11,21,22,25,2027
27
Blow-out Magnet Coils
0.5 daysTue 6/1/04Tue 6/1/04Mech.Tech.[2]2628
28
Connect South Platform Stairs
0.5 daysTue 6/1/04Wed 6/2/04Mech.Tech.[2]2729
29
Connect Platform Bridge
0.5 daysWed 6/2/04Wed 6/2/04Mech.Tech.[2]2831,30
30
Connect Seismic Anchors
0.5 daysWed 6/2/04Thu 6/3/04Mech.Tech.29 
31
Install Buss Bridge
0.5 daysWed 6/2/04Thu 6/3/04Mech.Tech.[2]2932
32
Connect Electrical Power
0.5 daysThu 6/3/04Thu 6/3/04Electrician[2]3133SS
33
Connect Subsystems Utilities
0.5 daysThu 6/3/04Thu 6/3/04Mech.Tech.32SS34SS
34
Connect Platform MCWS
0.5 daysThu 6/3/04Thu 6/3/04Mech.Tech.33SS35
35
Detector In AB
0 daysThu 6/3/04Thu 6/3/04 3437,117,121
36
Remove East & West FTPC
13.75 daysThu 6/3/04Wed 6/23/04   
37
Remove E/W IFC Air Manifolds
0.25 daysThu 6/3/04Thu 6/3/04Mech.Tech.3538
38
Remove East & West Scaffold
0.5 daysThu 6/3/04Fri 6/4/04Carpenter[2]3739
39
Install West Platform & Rails
1 dayFri 6/4/04Mon 6/7/04Carpenter[2]3840,41
40
Remove West FTPC
0.5 daysMon 6/7/04Mon 6/7/04Mech.Tech.3945
41
Rig Installation Frame into AB
0.5 daysMon 6/7/04Mon 6/7/04Riggers[3]3942SS
42
Install East Installation Frame
0.5 daysMon 6/7/04Mon 6/7/04Mech.Tech.[2]41SS43
43
Install East Rails
1 dayMon 6/7/04Tue 6/8/04Mech.Tech.[2]4244
44
Remove East FTPC
0.5 daysTue 6/8/04Wed 6/9/04Mech.Tech.[2]4345
45
East & West FTPC's Removed
0 daysWed 6/9/04Wed 6/9/04 40,4446,48
46
Maintenance on FTPC's
10 daysWed 6/9/04Wed 6/23/04Electronic Tech45 
47
Remove Cone
11.5 daysWed 6/9/04Thu 6/24/04   
48
Disconnect Utilities
4 daysWed 6/9/04Tue 6/15/04Mech.Tech.4549
49
Remove Cone from IFC
0.5 daysTue 6/15/04Tue 6/15/04Mech.Tech.4876,126
50
Remove East Installation Frame
1 dayTue 6/22/04Wed 6/23/04Mech.Tech.[2]76,12651FF
51
Remove Installation Frame from AB
0.5 daysWed 6/23/04Wed 6/23/04Riggers[3]50FF52
52
Remove Installation Frame West
1 dayWed 6/23/04Thu 6/24/04Carpenter[2]5153
53
Cone Removed
0 daysThu 6/24/04Thu 6/24/04 5257
54
Install East BEMC Modules
47.5 daysMon 6/14/04Wed 8/18/04   
55
(30) Modules Delivered
4 daysMon 6/14/04Fri 6/18/04Riggers[3]57FF-5 days56FF
56
(30) Modules Staged in AB
4 daysMon 6/14/04Fri 6/18/04Mech.Tech.[2]55FF 
57
Install East & West Scaffold
0.5 daysThu 6/24/04Fri 6/25/04Carpenter[2]5358,55FF-5 days
58
Remove East Side Cables & Tray
3 daysFri 6/25/04Wed 6/30/04Mech.Tech.[2]5759
59
Erect Installation Fixture S.E. Upper
0.5 daysWed 6/30/04Wed 6/30/04Mech.Tech.[2]5860
60
Remove S.E. TPC Support Arm
0.25 daysWed 6/30/04Thu 7/1/04Mech.Tech.[2]5961
61
Install Modules 106-103
4 daysThu 7/1/04Wed 7/7/04Mech.Tech.[2]6062
62
Erect Installation Fixture S.E. Lower
0.5 daysWed 7/7/04Wed 7/7/04Mech.Tech.[2]6163
63
Install Modules 102-89
14 daysWed 7/7/04Tue 7/27/04Mech.Tech.[2]6264
64
Install S.E. TPC Support Arm
0.5 daysTue 7/27/04Wed 7/28/04Mech.Tech.[2]6365
65
Erect Installation Fixture N.E. Lower
0.5 daysWed 7/28/04Wed 7/28/04Mech.Tech.[2]6466
66
Install Modules 77-88
12 daysWed 7/28/04Fri 8/13/04Mech.Tech.[2]6567
67
Remove Installation Fixture
0.25 daysFri 8/13/04Fri 8/13/04Mech.Tech.[2]6668
68
Install East Side Cables & Tray
3 daysFri 8/13/04Wed 8/18/04Mech.Tech.[2]6769
69
East BEMC Installation Complete
0 daysWed 8/18/04Wed 8/18/04 6882,72
70
Install BEMC PMT Boxes
35 daysWed 7/14/04Wed 9/1/04   
71
Install 208 VAC Power
15 daysWed 7/14/04Wed 8/4/04Electrician[2]72SF-10 days 
72
Install PMT Boxes
10 daysWed 8/18/04Wed 9/1/04Mech.Tech.[2]6973FF,71SF-10 days
73
Install Electronics
20 daysWed 8/4/04Wed 9/1/04Electronic Tech72FF74
74
PMT Box Installation Complete
0 daysWed 9/1/04Wed 9/1/04 73144
75
Install SSD
20.5 daysTue 6/15/04Wed 7/14/04   
76
Rig Cone to Cleanroom Roof
0.5 daysTue 6/15/04Wed 6/16/04Mech.Tech.4977,50
77
Install SSD on Cone
20 daysWed 6/16/04Wed 7/14/04Mech.Tech.7678SS,80
78
Install LV Crate & Cables
5 daysWed 6/16/04Wed 6/23/04Electronic Tech77SS79
79
Install RDO Boxes
5 daysWed 6/23/04Wed 6/30/04Electronic Tech78 
80
SSD Installed on Cone
0 daysWed 7/14/04Wed 7/14/04 7785
81
Install Cone
20.5 daysWed 8/18/04Thu 9/16/04   
82
Rig Installation Frame into AB
0.5 daysWed 8/18/04Thu 8/19/04Riggers[3]6983SS
83
Install East Installation Frame
0.5 daysWed 8/18/04Thu 8/19/04Mech.Tech.[2]82SS84
84
Install Tables & Rails
0.5 daysThu 8/19/04Thu 8/19/04Mech.Tech.8385
85
Rig Cone to Rails
0.5 daysThu 8/19/04Fri 8/20/04Mech.Tech.[2]84,8086
86
Survey SSD to SVT
2 daysFri 8/20/04Tue 8/24/04Surveyors[2]8587
87
Complete SSD Installation
2 daysTue 8/24/04Thu 8/26/04Mech.Tech.8688
88
Test Utility Connections
1 dayThu 8/26/04Fri 8/27/04Electronic Tech8789FF
89
Clean TPC IFC
1 dayThu 8/26/04Fri 8/27/04Mech.Tech.88FF90
90
Install Cone in Detector
0.5 daysFri 8/27/04Fri 8/27/04Mech.Tech.8991
91
Test IFC High Voltage
0.5 daysFri 8/27/04Mon 8/30/04Electronic Tech9092
92
Survey TPC to Magnet
2 daysMon 8/30/04Wed 9/1/04Surveyors[2]9193
93
Survey SVT to TPC
2 daysWed 9/1/04Fri 9/3/04Surveyors[2]9294
94
Install East Partitions
0.5 daysFri 9/3/04Fri 9/3/04Mech.Tech.93110
95
Connect Water Lines
0.5 daysMon 9/6/04Tue 9/7/04Mech.Tech.11096
96
Connect RDO Cables
1 dayTue 9/7/04Wed 9/8/04Electronic Tech9597
97
Remove East Rails from IFC
0.5 daysWed 9/8/04Wed 9/8/04Mech.Tech.[2]9698
98
Remove East Installation Frame
0.5 daysWed 9/8/04Thu 9/9/04Mech.Tech.[2]9799FF
99
Remove Installation Frame from AB
0.25 daysThu 9/9/04Thu 9/9/04Riggers[3]98FF100
100
East Side Complete
0 daysThu 9/9/04Thu 9/9/04 99107,101
101
Install West Partitions
0.5 daysThu 9/9/04Thu 9/9/04Mech.Tech.100112
102
Connect Water Lines
0.5 daysMon 9/13/04Mon 9/13/04Mech.Tech.114103
103
Connect RDO Cables
1 dayMon 9/13/04Tue 9/14/04Electronic Tech102104
104
Remove West Rails from IFC
0.5 daysTue 9/14/04Wed 9/15/04Mech.Tech.103105
105
Remove Installation Frame West
1 dayWed 9/15/04Thu 9/16/04Carpenter[2]104106
106
West Side Complete
0 daysThu 9/16/04Thu 9/16/04 105107
107
Cone Installation Complete
0 daysThu 9/16/04Thu 9/16/04 100,106144
108
Install FTPC East & West in AB
12.5 daysWed 8/25/04Mon 9/13/04   
109
Run & Test N. Platform
5 daysWed 8/25/04Wed 9/1/04Electronic Tech110SF-2 days 
110
Install East FTPC in Detector
1 dayFri 9/3/04Mon 9/6/04Mech.Tech.[2]94115,109SF-2 days,95
111
Run & Test N. Platform
5 daysWed 9/1/04Wed 9/8/04Electronic Tech114SF-2 days 
112
Remove West Scaffold
0.25 daysThu 9/9/04Fri 9/10/04Carpenter[2]101113
113
Install West Platform & Rails
0.25 daysFri 9/10/04Fri 9/10/04Carpenter[2]112114
114
Install West FTPC in Detector
1 dayFri 9/10/04Mon 9/13/04Mech.Tech.[2]113115,111SF-2 days,102
115
FTPC Installed in AB
0 daysMon 9/13/04Mon 9/13/04 114,110 
116
PMD Maintenance
40 daysThu 6/3/04Thu 7/29/04   
117
Subsystem Maintenance
30 daysThu 6/3/04Thu 7/15/04 35118
118
Detector Commisioning
10 daysThu 7/15/04Thu 7/29/04 117119
119
PMD Maintenance Complete
0 daysThu 7/29/04Thu 7/29/04 118 
120
EEMC Maintenance
90 daysThu 6/3/04Thu 10/7/04   
121
Maintenance
50 daysThu 6/3/04Thu 8/12/04 35122SS
122
MAPMT Installation
80 daysThu 6/3/04Thu 9/23/04Mech.Tech.[2]121SS123
123
Subsystem Testing
10 daysThu 9/23/04Thu 10/7/04 122124
124
EEMC Maintenance Complete
0 daysThu 10/7/04Thu 10/7/04 123 
125
TPC Maintenance
50 daysTue 6/15/04Tue 8/24/04   
126
Repair IFC Strip Short
5 daysTue 6/15/04Tue 6/22/04Mech.Tech.49127,50,131SS
127
Modify Resistor Chain
5 daysTue 6/22/04Tue 6/29/04Mech.Tech.126128
128
FEE & RDO Maintenance
40 daysTue 6/29/04Tue 8/24/04Electronic Tech127129
129
TPC Maintenance Complete
0 daysTue 8/24/04Tue 8/24/04 128 
130
TOF Maintenance
15 daysTue 6/15/04Tue 7/6/04   
131
Tray Maintenance
10 daysTue 6/15/04Tue 6/29/04 126SS132
132
Detector Testing
5 daysTue 6/29/04Tue 7/6/04 131133
133
TOFp Maintenance Complete
0 daysTue 7/6/04Tue 7/6/04 132 
134
FPD Installation
20 daysThu 5/27/04Thu 6/24/04   
135
Install West Detectors
10 daysThu 5/27/04Thu 6/10/04Mech.Tech.11136
136
Install N. E. Stand for 20-cm Travel
5 daysThu 6/10/04Thu 6/17/04Mech.Tech.[2]135137
137
Detector Commisioning
5 daysThu 6/17/04Thu 6/24/04 136138
138
FPD Installation Complete
0 daysThu 6/24/04Thu 6/24/04 137140
139
BBC Maintenance
15 daysThu 6/24/04Thu 7/15/04   
140
Subsystem Maintenance
10 daysThu 6/24/04Thu 7/8/04 138141
141
Detector Commisioning
5 daysThu 7/8/04Thu 7/15/04 140142
142
BBC Maintenance Complete
0 daysThu 7/15/04Thu 7/15/04 141 
143
Move Detector into WAH
27 daysThu 9/16/04Mon 10/25/04   
144
Disconnect Electrical Power
0.5 daysThu 9/16/04Thu 9/16/04Electrician[2]107,74147,145SS,146SS
145
Disconnect Platform MCWS
0.5 daysThu 9/16/04Thu 9/16/04Mech.Tech.144SS 
146
Disconnect TPC Utilities
0.5 daysThu 9/16/04Thu 9/16/04Mech.Tech.144SS 
147
Remove Buss Bridge
0.5 daysThu 9/16/04Fri 9/17/04Mech.Tech.[2]144148
148
Remove Platform Bridge
0.5 daysFri 9/17/04Fri 9/17/04Mech.Tech.[2]147149
149
Remove South Platform Stairs
1 dayFri 9/17/04Mon 9/20/04Mech.Tech.[2]148150
150
Disconnect Seismic Anchors
0.5 daysMon 9/20/04Tue 9/21/04Mech.Tech.[2]149151SS
151
Lower Detector to Rails
0.5 daysMon 9/20/04Tue 9/21/04Mech.Tech.[2]150SS152
152
Roll Detector into WAH
1.5 daysTue 9/21/04Wed 9/22/04Mech.Tech.[2]151153,154
153
Connect Magnet LCW
1 dayWed 9/22/04Thu 9/23/04Mech.Tech.[2]152 
154
Raise/Level Detector @ IR
0.5 daysWed 9/22/04Thu 9/23/04Mech.Tech.[2]152155FF,163
155
Connect Seismic Anchors
0.5 daysWed 9/22/04Thu 9/23/04Mech.Tech.[2]154FF159,156
156
Install Buss Bridge
0.5 daysThu 9/23/04Thu 9/23/04Mech.Tech.[2]155157,160
157
Connect Electrical Power
1 dayThu 9/23/04Fri 9/24/04Electrician[2]156158
158
Connect Magnet Power
1 dayFri 9/24/04Mon 9/27/04Elect.Tech.[2]157 
159
Connect All Subsystem Utilities
2 daysThu 9/23/04Mon 9/27/04Mech.Tech.[2]155168,166
160
Connect Platform MCWS
0.5 daysThu 9/23/04Fri 9/24/04Mech.Tech.156168,161
161
Connect South Platform Stairs
1 dayFri 9/24/04Mon 9/27/04Mech.Tech.[2]160162
162
Connect Platform Bridge
0.5 daysMon 9/27/04Mon 9/27/04Mech.Tech.[2]161167
163
Connect Vacuum Pipe & Supports
0.5 daysThu 9/23/04Thu 9/23/04Mech.Tech.[2]154164
164
Vacuum Pipe Bake-out
5 daysThu 9/23/04Thu 9/30/04Mech.Tech.[2]163165
165
Survey Beam Pipe & Magnet
4 daysThu 9/30/04Wed 10/6/04Surveyors[2]164 
166
Detector Safety Certification
2 daysMon 9/27/04Wed 9/29/04 159 
167
Install Shield Wall
3 daysMon 9/27/04Thu 9/30/04Riggers[3]162171
168
Subsystems testing in WAH
20 daysMon 9/27/04Mon 10/25/04 160,159169SS+5 days
169
Install Pole Tips
2 daysMon 10/4/04Wed 10/6/04Mech.Tech.[2]168SS+5 days170
170
Install BBC Detectors
1 dayWed 10/6/04Thu 10/7/04Mech.Tech.[2]169171
171
Shutdown Activities Complete
0 daysThu 10/7/04Thu 10/7/04 167,170 

FY06

STAR FY06 Shutdown Schedule


Project Start Date: 6/26/06
Project Finish Date: 10/27/06

 

STAR FY06 v5 Shutdown

IDWBS
Name
DurationStart_DateFinish_DateResource_NamesPredecessorsSuccessors
11
STAR Detector FY06 Shutdown
87 days6/26/0610/27/06   
21.1
Disconnect Detector Utilities
10.75 days6/26/067/12/06   
31.1.1
Begin Shutdown Activities
0 days6/26/066/26/06  4SS,114SS
41.1.2
Purge TPC Gas
1 day6/26/066/26/06 3SS 
51.1.3
Remove West BBC Detector
0.25 days7/5/067/5/06Mech.Tech.1146,103
61.1.4
Disconnect West Pole Tip Utilities
0.5 days7/5/067/5/06Mech.Tech.[2]57
71.1.5
Retract West Pole Tip
0.5 days7/5/067/6/06Mech.Tech.[2]68FF
81.1.6
Install Scaffold
0.25 days7/6/067/6/06Carpenter[2]7FF9
91.1.7
Remove East BBC Detector
0.25 days7/6/067/6/06Mech.Tech.810,103
101.1.8
Disconnect East Pole Tip Utilities
0.25 days7/6/067/6/06Elect.Tech.[2]911
111.1.9
Retract East Pole Tip
0.5 days7/6/067/7/06Mech.Tech.[2]1012FF,15,13
121.1.10
Install Scaffold
0.25 days7/7/067/7/06Carpenter[2]11FF19
131.1.11
Disconnect Electrical Power
0.5 days7/7/067/7/06Electrician[2]1115,14,17
141.1.12
Disconnect Magnet Power
0.5 days7/7/067/10/06Elect.Tech.[2]1315
151.1.13
Remove Buss Bridge
0.25 days7/10/067/10/06Mech.Tech.[2]13,14,1116
161.1.14
Disconnect Platform MCWS
0.5 days7/10/067/10/06Mech.Tech.[2]1518
171.1.15
Disconnect Subsystems Utilities
2 days7/7/067/11/06Mech.Tech.13 
181.1.16
Remove South Platform Stairs
0.25 days7/11/067/11/06Mech.Tech.[2]1621
191.1.17
Remove pVPD Detectors
0.25 days7/7/067/7/06Mech.Tech.[2]1220
201.1.18
Disconnect RHIC Vacuum Pipe
3 days7/7/067/12/06Mech.Tech.[2]1924
211.1.19
Remove Seismic Anchors
0.25 days7/11/067/11/06Mech.Tech.[2]1822
221.1.20
Disconnect Magnet Water
0.25 days7/11/067/11/06Mech.Tech.[2]2123
231.1.21
Blow-out Magnet Coils
1 day7/11/067/12/06Mech.Tech.[2]2224
241.1.22
Detector Utilities Disconnected
0 days7/12/067/12/06 23,2026,57
251.2
Hydraulic System Testing
6.5 days7/12/067/21/06   
261.2.1
Run & Test Hydraulics
5 days7/12/067/19/06Mech.Tech.2427FF
271.2.2
Position Detector on Beamline
0.5 days7/19/067/19/06Mech.Tech.26FF28SS
281.2.3
Survey Detector on Beamline
2 days7/19/067/21/06Surveyors[2]27SS29
291.2.4
Hydraulics Tests Complete
0 days7/21/067/21/06 2831,67,132,85
301.3
Remove Hilman Rollers
5 days7/31/068/4/06   
311.3.1
Remove Roller Assemblies
5 days7/31/068/4/06Mech.Tech.[2]29,12332FF
321.3.2
Remove Roller Assemblies
2 days8/3/068/4/06Riggers[3]31FF33FF
331.3.3
Crate & Ship Roller Assemblies
1 day8/4/068/4/06Riggers[2],Carpenter[2]32FF34FF
341.3.4
Roller Assembly Removal Complete
0 days8/4/068/4/06 33FF 
351.4
Remove West FPD++ Detector
23.5 days7/5/068/7/06   
361.4.1
Disconnect Cabling
5 days7/5/067/11/06Mech.Tech.11437SS
371.4.2
Remove Existing Cells
13 days7/5/067/21/06Mech.Tech.36SS38
381.4.3
Remove Cabling
5 days7/31/068/4/06Mech.Tech.37,12339
391.4.4
Remove Enclosures & Shield Block
0.5 days8/7/068/7/06Riggers[3]38125,40
401.4.5
FPD++ Removal Complete
0 days8/7/068/7/06 3995
411.5
East FTPC Maintenance
15 days8/7/068/25/06   
421.5.1
Remove East IFC Air Manifolds
0.5 days8/7/068/7/06Mech.Tech.67,12343
431.5.2
Remove East Scaffold
0.5 days8/7/068/7/06Carpenter[2]4244
441.5.3
Rig East FTPC Platform
0.5 days8/8/068/8/06Riggers[3]4345SS
451.5.4
Install East FTPC Platform
0.5 days8/8/068/8/06Carpenter[2]44SS46
461.5.5
Install East FTPC Rails
0.5 days8/8/068/8/06Mech.Tech.[2]4547
471.5.6
Remove East FTPC
1 day8/9/068/9/06Mech.Tech.[2]4648,74
481.5.7
Replace East FTPC FEE
5 days8/10/068/16/06Electronic Tech4749
491.5.8
Install FTPC on Rails & Test
5 days8/17/068/23/06 4850FF
501.5.9
Install East FTPC
0.5 days8/24/068/24/06Mech.Tech.[2]49FF,7551
511.5.10
Remove East FTPC Rails
0.5 days8/24/068/24/06Mech.Tech.[2]5052
521.5.11
Rig East FTPC Platform
0.5 days8/25/068/25/06Riggers[3]5153SS
531.5.12
Remove East FTPC Platform
0.5 days8/25/068/25/06Carpenter[2]52SS54
541.5.13
Install East Scaffold
0.5 days8/25/068/25/06Carpenter[2]5355
551.5.14
FTPC Maintenance Complete
0 days8/25/068/25/06 5486,70
561.6
SSD Maintenance
27.25 days7/12/068/18/06   
571.6.1
Compressor Maintenance
5 days7/12/067/19/06 24 
581.6.2
RDO maintenance
5 days7/31/068/4/06Carpenter[2]67SS59
591.6.3
Crate Maintenance
10 days8/7/068/18/06Riggers[3]58,12360
601.6.4
SSD Maintenance Complete
0 days8/18/068/18/06 59 
611.7
BEMC Maintenance
40 days7/31/069/25/06   
621.7.1
Remove & Repair Crates
20 days7/31/068/25/06Electronic Tech12363
631.7.2
Install PMT Box Remote Power
20 days8/28/069/25/06Electronic Tech[2]6264FF
641.7.3
PMT Box Maintenance
20 days8/28/069/25/06Elect.Tech.63FF65
651.7.4
BEMC Maintenance Complete
0 days9/25/069/25/06 64145
661.8
SVT RDO Box Relocation
39 days7/31/069/22/06   
671.8.1
Remove RDO Boxes
5 days7/31/068/4/06Electronic Tech29,12368,42,58SS
681.8.2
Repair RDO Boxes
20 days8/7/069/1/06Electronic Tech6769
691.8.3
Install West RDO Boxes
2 days9/12/069/13/06Electronic Tech68,8772,81,70
701.8.4
Install Remote East RDO Boxes
5 days9/14/069/20/06Mech.Tech.69,5571
711.8.5
Rout East RDO Cables
2 days9/21/069/22/06Electronic Tech[2]7072
721.8.6
SVT RDO Box Relocation Complete
0 days9/22/069/22/06 71,69139,145
731.9
HFT Prototype Installation
10 days8/10/068/23/06   
741.9.1
Install East HFT Prototype
10 days8/10/068/23/06Mech.Tech.[2]4775
751.9.2
HFT Prototype Installed
0 days8/23/068/23/06 7450
761.10
PMD Maintenance
40 days7/31/069/25/06   
771.10.1
Replace Supermodules
30 days7/31/069/11/06 12378
781.10.2
Detector Maintenance
10 days9/12/069/25/06 7779
791.10.3
PMD Maintenance Complete
0 days9/25/069/25/06 78145
801.11
EEMC Maintenance
15 days9/14/0610/4/06   
811.11.1
PMT/MAPMT Box Maintenance
12 days9/14/069/29/06Mech.Tech.[2]69,11282SS
821.11.2
Subsystem Testing
15 days9/14/0610/4/06 81SS83
831.11.3
EEMC Maintenance Complete
0 days10/4/0610/4/06 82145,115
841.12
TPC Maintenance
35.75 days7/21/069/11/06   
851.12.1
Remove East/West Bad FEE/RDO
5 days7/21/067/28/06Electronic Tech[2]2988
861.12.2
Install East FEE/RDO
5 days8/28/069/1/06Electronic Tech[2]5589,87
871.12.3
Install West FEE/RDO
5 days9/5/069/11/06Electronic Tech[2]8689,69
881.12.4
Maintenance on Gas Room UPS
1 day7/28/067/31/06 8589
891.12.5
TPC Maintenance Complete
0 days9/11/069/11/06 88,87,86139,145,107
901.13
TOF Maintenance
5 days10/5/0610/11/06   
911.13.1
Remove Old Tray
2 days10/5/0610/6/06Mech.Tech. 92
921.13.2
Install New Trays
3 days10/9/0610/11/06Mech.Tech.9193
931.13.3
TOF Installation Complete
0 days10/11/0610/11/06 92115
941.14
FMS Installation
43 days8/7/0610/6/06   
951.14.1
Install FMS Carriages
5 days8/7/068/14/06Mech.Tech.[2]4096
961.14.2
Install FMS Cells
30 days8/14/069/26/06Mech.Tech.[2]9598FF,97SS
971.14.3
Install AC Power
5 days8/14/068/21/06Electrician[2]96SS100
981.14.4
Install FMS Enclosures
5 days9/19/069/26/06Mech.Tech.[2]96FF99
991.14.5
Install FMS Cabling
8 days9/26/0610/6/06Mech.Tech.[2]98101
1001.14.6
Install Electronics Racks
10 days8/21/069/5/06Electronic Tech[2]97101
1011.14.7
FMS Installation Complete
0 days10/6/0610/6/06 99,100145
1021.15
BBC Maintenance
25 days7/6/068/10/06   
1031.15.1
Subsystem Maintenance
20 days7/6/068/3/06 5,9104
1041.15.2
Detector Commisioning
5 days8/3/068/10/06 103105
1051.15.3
BBC Maintenance Complete
0 days8/10/068/10/06 104 
1061.16
Trigger Maintenance
10 days9/12/069/25/06   
1071.16.1
Trigger Maintenance
10 days9/12/069/25/06 89108
1081.16.2
Trigger Maintenance Complete
0 days9/25/069/25/06 107145
1091.17
Pole Tip Hose Replacement
5 days7/31/068/4/06   
1101.17.1
Remove Old Hose
2 days7/31/068/1/06Mech.Tech.[2]123111
1111.17.2
Install New Braided Hose
3 days8/2/068/4/06Mech.Tech.[2]110112
1121.17.3
Hose Replacement Complete
0 days8/4/068/4/06 11181
1131.18
Magnet Power Supply Maintenance & Test
87 days6/26/0610/27/06   
1141.18.1
Power Supply Maintenance & Test
5 days6/26/066/30/06Electronic Tech[2]3SS5,36
1151.18.2
Remove East/West Scaffold
0.5 days10/12/0610/12/06Carpenter[2]83,93116SS
1161.18.3
Install East Pole Tip
1 day10/12/0610/12/06Mech.Tech.[2]115SS117
1171.18.4
Install West Pole Tip
1 day10/13/0610/13/06Mech.Tech.[2]116118,143FF
1181.18.5
Power Supply Maintenance & Test
10 days10/16/0610/27/06Electronic Tech[2]117119
1191.18.6
Power Supply Maintenance Complete
0 days10/27/0610/27/06 118146
1201.19
C-AD Maintenance
49 days7/24/069/29/06   
1211.19.1
SGIS Modifications
10 days9/18/069/29/06Elect.Tech.[2] 130,144
1221.19.2
PS Sound Barrier Wall
10 days7/31/068/11/06 123 
1231.19.3
AC Substation Maintenance
5 days7/24/067/28/06  62,110,124,128,77,42,59,31,67,38,132,122
1241.19.4
Control Room Modification
10 days7/31/068/11/06 123126
1251.19.5
Install West Tunnel Shielding
5 days8/7/068/14/06Riggers[3]39 
1261.19.6
DAQ Room A/C Upgrade
10 days8/14/068/25/06 124127
1271.19.7
Fire Sprinkler Preaction Upgrade
10 days8/28/069/11/06 126130
1281.19.8
MCW Flow Balance
10 days7/31/068/11/06Mech.Tech.[2]123129
1291.19.9
Seal Tower Basin
5 days8/14/068/18/06Mech.Tech.[2]128 
1301.19.10
C-A Maintenance Complete
0 days9/29/069/29/06 127,121 
1311.20
Connect Detector Utilities
64 days7/31/0610/27/06   
1321.20.1
Connect Magnet LCW
1 day7/31/067/31/06Mech.Tech.[2]29,123133
1331.20.2
Install Buss Bridge
0.5 days8/1/068/1/06Mech.Tech.[2]132134,137
1341.20.3
Connect Electrical Power
1 day8/1/068/2/06Electrician[2]133135,136
1351.20.4
Connect Magnet Power
1 day8/2/068/3/06Elect.Tech.[2]134 
1361.20.5
Connect All Subsystem Utilities
1 day8/2/068/3/06Mech.Tech.[2]134 
1371.20.6
Connect Platform MCWS
0.5 days8/1/068/1/06Mech.Tech.133138
1381.20.7
Connect South Platform Stairs
1 day8/2/068/2/06Mech.Tech.[2]137 
1391.20.8
Connect Vacuum Pipe & Supports
3 days9/25/069/27/06Mech.Tech.[2]72,89140SS
1401.20.9
Vacuum Pipe Bake-out
10 days9/25/0610/6/06Mech.Tech.[2]139SS141
1411.20.10
Install START Detectors
0.5 days10/9/0610/9/06Mech.Tech.140142
1421.20.11
Survey Beam Pipe
2 days10/9/0610/11/06Surveyors[2]141143
1431.20.12
Install BBC Detectors
1 day10/13/0610/13/06Mech.Tech.[2]142,117FF 
1441.20.13
Detector Safety Certification
5 days10/2/0610/6/06 121145
1451.20.14
Subsystems testing in WAH
5 days10/9/0610/13/06 144,65,108,101,72,79,83,89146
1461.20.15
Shutdown Activities Complete
0 days10/27/0610/27/06 145,119