ID | Task Name | Duration | Start | Finish | Resource Names | |
---|---|---|---|---|---|---|
1 | ||||||
2 | TPC checks | 7 days | Fri 2/9/07 | Mon 2/19/07 | ||
3 | Laser drift+T0 | 7 days | Fri 2/9/07 | Mon 2/19/07 | Yuri[50%] | |
4 | SSD shift + East/West TPC tracks | 3 days | Fri 2/9/07 | Tue 2/13/07 | Spiros[25%] | |
5 | SVT aligment | 7 days? | Tue 2/20/07 | Wed 2/28/07 | ||
6 | SVT+SSD (cone) for each wafer | 1 wk | Tue 2/20/07 | Mon 2/26/07 | Ivan,Richard | |
7 | Shell/Sector for each magnetic field settings | 1 day? | Tue 2/27/07 | Tue 2/27/07 | ||
8 | Ladder by Ladder | 1 day? | Wed 2/28/07 | Wed 2/28/07 | ||
9 | Using TPC+SSD, Determining the SVT Drift velocity | 7 days | Fri 2/9/07 | Mon 2/19/07 | Ivan | |
10 | Drift velocity | 12 days | Fri 2/9/07 | Mon 2/26/07 | ||
11 | High stat sample processing preview | 7 days | Fri 2/9/07 | Mon 2/19/07 | Vladimir | |
12 | Final evaluation | 5 days | Tue 2/20/07 | Mon 2/26/07 | Vladimir | |
13 | ||||||
14 | Online QA (offline QA) | 7 days | Fri 2/9/07 | Mon 2/19/07 | Ivan,Helen | |
15 | ||||||
16 | Hit error calculation final pass | 1 wk | Fri 2/9/07 | Thu 2/15/07 | Victor | |
17 | Self-Alignement | 3 wks | Fri 2/16/07 | Thu 3/8/07 | Victor | |
18 | Code in place for library - aligement related | 1 wk | Fri 2/9/07 | Thu 2/15/07 | Yuri[10%],Victor[10%] | |
19 | ||||||
20 | Tasks without immediate dependencies | 60 days | Fri 2/9/07 | Thu 5/3/07 | ||
21 | Cluster (SVT+SSD) and efficiency studies | 1.5 mons | Fri 2/9/07 | Thu 3/22/07 | Artemios,Jonathan | |
22 | Slow/Fast simulators reshape | 3 mons | Fri 2/9/07 | Thu 5/3/07 | Jonathan,Polish students x2,Stephen | |
23 | ||||||
24 | ||||||
25 | Cu+Cu re-production | 87.5 days | Fri 3/9/07 | Tue 7/10/07 | ||
26 | Cu+Cu 62 GeV production | 3 wks | Fri 3/9/07 | Thu 3/29/07 | ||
27 | Cu+Cu 200 GeV production | 72.5 days | Fri 3/30/07 | Tue 7/10/07 | ||
28 | cuProdcutionMinBias (30 M) | 8.5 wks | Fri 3/30/07 | Tue 5/29/07 | ||
29 | cuProductionHighTower (17 M) | 6 wks | Tue 5/29/07 | Tue 7/10/07 |