1) I updated the TPC-PXL sector overlap picture to reflect
   the true TPC arrangement, as per Xin's correction. I
   put the new picture in the meeting's Drupal page.
2) Flemming drafted a MS-Project schedule diagram for software
   and associated Milestones. I will at this in detail over
   the weekend.   
3) Flemming is preparing some drawings of the detector complex
   for the non-initiated folks, like me.
4) Jonathan is looking into tracking efficiency/ghosting with the
   prototype only. He has problems with every option he tries
   for the moment (some of them just resolved). There is going
   to be more discussion in this list about this stuff. It
   has been a while since we used this production chains and
   things got rusted.
5) I have asked for CMM time during the Collab. meeting since
   we are going to be there anyway.
6) I 've contacted Auguste about the slow simulator.
7) Jerome contacted me about updates. We are on in next week's
   S&C Wed meeting and also during the Friday morning plenary
   session at the Collab. meeting.

 