  • Reminder of the BES / Run 14 production timeline You do not have access to view this node
    • Start of production on April 9th
    • Calibration done by April 2nd (+1 week flex)
    • HFT Geometry to be sorted out
  • You do not have access to view this node
  • Ticket system
    • Please, attend tickets and close
    • Provide HIGHER priority to tickets than personal Emails, redirect Emails to a ticket queue