Management Meeting

2018-08-17 12:00
America/New York
Friday, 17 August 2018
Meeting starts Noon BNL Time - BlueJeans Conference ID : 160455989, at 16:00 (GMT), duration : 00:00
 
1. summer shut-down schedule and upgrade progress:
    DOE site-visit in 18/09 and iTPC review 11/10  
    on schedule and next week iTPC sector installation starts

2. issues with run14 production and preparation for HP2018 in October 
    lots of changes among the years, and this year, has fixed a few bugs. 
    next is to test embedding with P18 version 

3. Isobar production and ABC 

   calibration mostly ready,
   concerns about two things: dE/dx and mixing for blinding 
   ABC: discussion with PWGC 

4. upcoming meetings and preparations? 

   ALICE-STAR Indian Meeting (NISER) September 17-21, 2018
   Regional Meeting 10/30, Analysis Meeting 12/11, 
   Collaboration Meeting, March-April 2019
   Collaboration, August-September 2019 
   preQM2019 at SDU (Qingdao campus) [QM in Wuhan in November]

5. order of name authors; Latex of text 

6. newsletter? 

   summer Sunday, FMS de-assembly, spokespersons, 
   shut-down, iTPC installation