EMC Meeting 2 February 2009

Attached are plots showing some ADC spectrums for the nominal timing run for the BPRS/BSMD.  I show BSMDE, BSMDP and BBPRS.  Note that the x axis for the BSMD is not the same as for the BPRS.

 

For reference these are the relevant runs for the timing scans:

 

Run Number TCD Delay
8330079 -150
8330088 -100
8330089 -50
8330090 0
8330094 50
8330097 100
8330100 150