Run 10 Calibration Status (2010-08-11)

Production of the 7 and 11 GeV data sets are held due to the correction of the TPC anode voltages.

TPC: Twist calibration for the 200GeV FF data has been completed. (Zubayer Ahammed)

       www.star.bnl.gov/protected/bulkcorr/za/twist/FF/twist_Aug5th.ppt

TOF: 39GeV BTof Calibration completed (Rafael Derradi)

      www.star.bnl.gov/HyperNews-star/get/startof/2364.html

BEMC: status and pedestals table are complete for AuAu200GeV dataset. (Alice Ohlson and Elena Bruna)

          -Volunteer needed to produce 7 and 11 GeV status and pedestal tables.