DOE site visit, revisied info

...


Species Total #of events (M) %tage events completed Estimate time to delivery (months) %tage time to completion
Run 16   9126.46 89.15 0.81 92.45%
  Au+Au 200GeV 6543.26 96.43 0.31  
  d+Au 200GeV 1181.10 36.34 0.41  
  d+Au 62GeV 357.91 99.22 0.08  
  d+Au 39GeV 642.12 99.83  
  d+Au 20GeV 402.08 99.73  
Run 15   10997.37 95.61 0.22 95.94%
  p+p 200GeV 6329.66 96.81 0.10  
  p+Au 200GeV 3647.70 93.29 0.10  
  p+Al 200GeV 1015.11 96.44 0.02  
  Fixed Target 2015 4.76 100.00 0.00  
Run 14   6718.09 84.66 0.39 90.85%
  Au+Au 200GeV 5045.59 96.79 0.22  
  He3+Au 200GeV 1260.30 31.29 0.18  
  Au+Au 14.6GeV 412.20 99.38 0.00  



...

Updated table as per 2017/09/01.
Estimated production (all to 100%) end: 1.4 months.

One possible addition: trying to request a large allocation at NERSC/Cori and demonstrate we can sustain data production at scale and high efficiencies. Initial target 1/2 of the RACF farm size in CPU power. Now discussing an allocation x2 RACF production farm size equivalent to show we can finish a production wave in a few days.