EPD Commissioning 2023
Updated on Wed, 2023-05-03 08:21. Originally created by lisa on 2023-05-03 07:49.
While much of the commissioning activity has already begun and much is well-documented, this will be a "high-level" page to keep track of EPD commissioning for 2023.
There are several changes this year:
To do:
There are several changes this year:
- On the West side, all channels will be read out for every event via the DEP system, but the QTs will only be read out at low event rates
- We now have four EQ crates instead of three (this is related to the above, but no need to explain).
- Some of the QT32Bs have been replaced by QT32Ds.
To do:
- By 5 May 2023: The West EPD has been installed and uninstalled and reinstalled and uninstalled due to water leaks at the same location..... it needs to be reinstalled. - Tristan/Prashanth
- By 5 May 2023: Seven Patterns Test. This has been done in February with imperfect results. Needs to be re-done. Discussion on email list - Maria with advice from elders
- Before beam: Based on previous test: - Tristan/Yevheniia
- replace/repair MDR connections or diffRx boards
- re-map dead QT channels
- Before beam: When things settle down on the trigger side, have trigger group check DSM board mapping - Eleanor (Mike)
- Before beam: VPED scan - Maria
- Before beam: Online monitoring plots - rearranging due to 4 crate? - ??
- First collisions: Timing scan - Mike & Maria
- First collisions: Bias scan - Mike & Maria
»