EPD Commissioning - Step-by-step
Updated on Wed, 2020-07-08 22:21. Originally created by lisa on 2019-12-09 09:16.
Useful links:
- RHIC monitoring: cadweb.bnl.gov/dashs/Operations/BroadcastWeb/BroadcastMain.dash
- STAR DAQ monitoring: online.star.bnl.gov/daq/export/daq/
- EPD monitor/control GUI: dashboard1.star.bnl.gov/daq/EPD_UI/
- EPD online histograms: online.star.bnl.gov/epd/
Commissioning
Before DAQ is up:
- Install the EPD - Installation workplan
- I-V Scan (just to ensure things aren't crazy) - see EPD manual
After mounting, and when DAQ is up but no beam
- "Seven Patterns" test - instructions
- Vped adjustment - instructions
With cosmics or first collisions:
- Pre-post check - instructions
- EPD-BBC correlations - instructions
With first collisions:
- Timing scan - instructions
- Bias scan - instructions
»