calibration delivery timescale1 for Run11
AV | T0/TWIST | SC&GL | Alignment | dE/dx | |
---|---|---|---|---|---|
p+p, 500 GeV, RFF |
list of good runs exist (~95%) |
done using LowLumi RFF data |
2 weeks for 3 dataset |
use Y2000 alignment parameters |
1 week |
Au+Au, 19 GeV, RFF | list of good runs exist | 1 week | |||
Au+Au, 200 GeV, RFF | list of good runs exist | 1 week | |||
Au+Au, 200 GeV, FF |
~1 week (using FF LowLumi data) |
1week | |||
Au+Au, 27 GeV, FF | list of good runs exist | 1 week |
TWIST & T0 should be done before SC
SC&GL ~1 week or less for dataset
dE/dx ~week for each dataset
Anode voltages - list of good runs exist (repairable runs can be added on the time scale of 1-1.5 week)
Hit errors - not adressed, may want to revisit for Run11