- surrow's home page
- Posts
- 2024
- May (1)
- 2018
- 2017
- 2016
- 2015
- 2014
- October (3)
- September (1)
- August (1)
- July (1)
- June (3)
- May (4)
- April (6)
- March (4)
- February (5)
- January (2)
- 2013
- December (2)
- November (1)
- October (1)
- September (4)
- August (6)
- July (11)
- June (8)
- May (5)
- April (5)
- March (11)
- February (4)
- 2012
- December (3)
- November (3)
- October (3)
- September (3)
- August (3)
- July (10)
- June (9)
- May (5)
- April (4)
- March (4)
- February (7)
- January (4)
- 2011
- 2010
- December (2)
- November (4)
- August (2)
- July (3)
- June (6)
- May (4)
- April (4)
- March (8)
- February (6)
- January (4)
- 2009
- My blog
- Post new blog entry
- All blogs
HV ramp / Power-cycle
Procedure in case of persistend DAQ probems with FGT: Power-cycle FGT crate
--> Consult expert before doing this!
a) Physics --> Standby (Wait until HV is at standby)
b) Standby --> Off (Wait until HV is at off)
c) Turn crate off and then on
d) Off --> Standby
e) Standby --> Physics
Groups: