Software and Computing Meeting
2014-12-17 12:00
2014-12-17 13:00
America/New York
Wednesday, 17 December 2014
1-189, SRN, at 17:00 (GMT), duration : 01:00
1-189, SRN, at 17:00 (GMT), duration : 01:00
Time | Talk | Presenter |
---|---|---|
12:00 | Au-Au 15/200 GeV TPC SC and GL Calibration Update ( 00:20 ) 1 file | Matthew Posik (Temple) |
12:20 | Calibration updates ( 00:15 ) 0 files | Gene V. Buren (BNL) |
12:35 | Sti/HFT status ( 00:20 ) 2 files | Jason Webb (BNL) |
12:55 | AOB ( 00:05 ) 0 files | All (All) |
Dilepton Trigger Run 14 (Bill's slides from 05/03/2014)
Updated on Wed, 2014-12-17 10:19. Originally created by wlodek on 2014-12-17 10:19.exclusivity cut
Updated on Wed, 2014-12-17 10:28. Originally created by adamczyk on 2014-12-17 10:06.Reference
Speaker : Leszek Adamczyk (AGH-UST)
Talk time : 10:50, Duration : 00:05
Calibration status update for Run 14 AuAu datasets
Updated on Wed, 2014-12-17 00:52. Originally created by genevb on 2014-12-17 00:24.- 14.6 GeV AuAu
- ~4 million events, sampling every production run with the st_hltgood file stream, were »
SSD Geometry
Updated on Wed, 2014-12-17 10:44. Originally created by margetis on 2014-12-16 21:56.iTPC insertion tool
2014-12-17 12:30
America/New York
Wednesday, 17 December 2014
2-78 at BNL, at 17:30 (GMT), duration : 00:00
2-78 at BNL, at 17:30 (GMT), duration : 00:00
Insertion tooling has been completed and arrived at BNL 5/12/2017
A few pictures

First attempts to unload

second and successful attempt


tooling out of car

-----------------------------------------------------------------
old meeting: notes 12/17/2014
First review of concepts of iTPC insertion tooling
Agenda:
1) Discussion about the design of the iTPC sector insertion tool for STAR - R.Sharma - 25 mins
2) Analysis of the sector insertion tool and comparing the final deflection numbers with clearances - R.Sharma - 25 mins
3) Clean room environment requirements - R. Brown - 25 mins
4) Scaffolding requirements - R. Brown - 25 mins
5) Schedule - R. Brown - 10 mins
6) Break - 10 mins
7) Reviewer Questions, Comments and Closeup - 60 mins
Meeting minutes will be taken by Flemming. We will start at 12:30pm EST and we will be done by 3:30pm EST. Please try to go over the presentation file in advance. I appreciate everyone making time for this review.
Presentation by Rahul & Ralph
Notes from meeting (FV)
A few pictures

First attempts to unload

second and successful attempt


tooling out of car

-----------------------------------------------------------------
old meeting: notes 12/17/2014
First review of concepts of iTPC insertion tooling
Agenda:
1) Discussion about the design of the iTPC sector insertion tool for STAR - R.Sharma - 25 mins
2) Analysis of the sector insertion tool and comparing the final deflection numbers with clearances - R.Sharma - 25 mins
3) Clean room environment requirements - R. Brown - 25 mins
4) Scaffolding requirements - R. Brown - 25 mins
5) Schedule - R. Brown - 10 mins
6) Break - 10 mins
7) Reviewer Questions, Comments and Closeup - 60 mins
Meeting minutes will be taken by Flemming. We will start at 12:30pm EST and we will be done by 3:30pm EST. Please try to go over the presentation file in advance. I appreciate everyone making time for this review.
Presentation by Rahul & Ralph
Notes from meeting (FV)
Away-side jet correlations 1216 2014
Updated on Wed, 2015-01-21 15:25. Originally created by kjiang on 2014-12-16 14:42.
Trigger for run 15
Updated on Tue, 2014-12-16 12:57. Originally created by igora on 2014-12-16 12:57.Reference
Speaker : Igor Alekseev ( ITEP )
Talk time : 10:30, Duration : 00:20
A revised version of trigger presentation.
Run-11 Transverse Jets: Slides for PWGC Preview
Updated on Tue, 2014-12-16 10:52. Originally created by drach09 on 2014-12-16 10:33.Run 9 200GeV Dijet Cross Section: Integrated Luminosity Systematic
Updated on Wed, 2015-02-11 14:18. Originally created by pagebs on 2014-12-15 23:13. Hopefully the last discussion on how to quantify the systematic error associated with the extraction of the integrated luminosity ...
Run12 Calibration: New Fits
Updated on Thu, 2014-12-18 08:44. Originally created by jkadkins on 2014-12-15 21:22.
2011+2012 Collins Figure for Spin White Paper
Updated on Tue, 2014-12-16 16:03. Originally created by drach09 on 2014-12-15 17:54.Posted below in Fig. 1 and attached at the bottom of the blog is a proposed figure for the RHIC Spin White Paper.
PWGC Meeting
Updated on Tue, 2014-12-16 10:57. Originally created by geurts on 2014-12-15 15:46. 2014-12-16 11:00
2014-12-16 13:00
America/New York
--- Agenda ---
1) Run-14 production status
FMS Simulation Issues
Updated on Mon, 2014-12-15 03:03. Originally created by heppel on 2014-12-15 02:38.The problem that we notices in last weeks FMS meeting was that there appeared to be a strange cutoff in the per-tower simulation at 50 GeV.
2012 - Relative Luminosity Plots
Updated on Mon, 2014-12-15 01:18. Originally created by sra233 on 2014-12-15 01:18.IFF paper drafts
Updated on Tue, 2015-01-06 10:57. Originally created by avossen on 2014-12-13 20:24.
IST Sti Geometry
Updated on Mon, 2014-12-15 21:18. Originally created by smirnovd on 2014-12-12 16:31.Version 1: Simplified