computing

Online computing run preparation plans

Under:

This page will list by year action items, run plans and opened questions. It will server as a repository for documents serving as basis for drawing the requirements.

Notes

Under:

Overview



The document is intended as a forum for embedding group members to share information and notes.

Quality Control

Under:

  • dEdx Comparisons

  • These are dedx vs P graphs. All of them show reasonable agreement with data.(Done on May 2002)

    Dedx-dedxPiPlus.gif
    Dedx-dedxKMinus.gif

    Old Requests

    Under:

    Overview



    This page is intended to provide details of embedding jobs currently in production.

    Embedding Procedures

    Under:

    Overview



    Embedding Documentation

    Under:

    Overview


    SUMS and Grid snapshots

    Under:
    On this page, we will save snapshots of how SUMS "sees" the Grid utilization.
    Average dispatch time,  all dispatchers, past 3 months (200607)

    Original cluster algorithm (kEmcClOld)

    Under:

    This page describes the original cluster finder algorithm. In order to use this algorithm you should set with the algorithm kEmcClOld.

    BPRS

    Under:

    This task has been picked up by Rory Clarke from TAMU. His page is here:

    http://www4.rcf.bnl.gov/~rfc/

    Point Maker

    Under:

    After obtaining the clusters for 4 subdetectors, we need to obtain the information about the incident shower by making the proper matching between clusters from different subdetectors.

    Service Tasks

    Under:


    Effect of SVT and SSD on SpaceCharge Calibration

    Under:
    The method of determining the amount of SpaceCharge present in the TPC from the signed distance of closest approach (sDCA) of global tracks to the primary vertex has worked well in the productions whe

    SVT/SSD Review Coordination meeting 8

    Under:
    -00-00
    Thursday, 1 January 1970
    , at 00:00 (GMT), duration : 00:00
    Instead of an official agenda item list, here is a "lose" agenda item for this 8th coordination meeting.
    1. General focus statement, next check point
    2. Comment on current review agenda available as
      [node:2391]
    3. Christina's D0 observations, samples needed and conditions [last call]
      last list [node:2361]
    4. Comments from Rene/Helen/anyone else on Anthony results http://www.star.bnl.gov/protected/strange/atimmins/CuCuSVTQA/SVTQA.htm
    5. Progress and/or issues from Sarah + needs
    6. Progress and/or issues with B-studies + needs

    7. Opened discussion: strangeness Physics content and focus

    Previous meetings are available at

    1. [node:1297]
    2. [node:1540]
    3. [node:1568]
    4. [node:2299]
    5. [node:2298]
    6. [node:2300]
    7. [node:2360]

    SpaceCharge azimuthal anisotropy

    Under:

    In order to better understand possible anisotropies in the azimuthal distribution of SpaceCharge (see, for example, zerobias data from day 47 of 2004), I have examined the signed DCA (sDCA) aziumthal distributions from several productions. I have separated these distributions into a static component and a dynamic component by determining <sDCA> in each phi bin for each dataset examined, and then looking at the differences from this mean. The mean does not truly equal the static component, but it is very helpful to subtract this component in order to see the the time-evolving component as both components are of similar magnitudes.

    In the plots below, the first row shows the <sDCA> value for each phi bin (the bins are aligned along TPC sectors going from 2 o'clock, 1 o'clock, 12 o'clock, .... , 3o'clock with increasing phi). In the subsequent rows, I plot sDCA-<sDCA> versus day (with each phi bin offset) to see what's happening on sub-day time scales, versus day in a colored 2D graph to see what's happening on larger time scales, and versus SpaceCharge to see what's happening versus luminosity.

    Additional comments below the plots.

    2004

    2004 AuAu200 early RFF data FF data late RFF data
    <sDCA>
    sDCA - <sDCA> vs. day
    sDCA - <sDCA> vs. day
    sDCA - <sDCA> vs. SpaceCharge

    The <sDCA> values appear to have fluctuation on the +/-200 micron scale in azimuth. The FF and late RFF data show a feature at phi~3 that is probably due to backgrounds from the collider entering the TPC and causing SpaceCharge distortions in only one region in phi. All of the fluctuations seem to subside to well below 100 microns at the lowest luminosities, implying that <sDCA> perhaps does represent well the static misalignments/distortions.

    For the early RFF data, there are some unusual structures. The above SpaceCharge plot for this data was set so that the range of sDCA at higher luminosities could be viewed. Here is a plot of the same data with the range modified to see more clearly the low luminosity data, for which the fluctuations are again well below 100 microns.

     

    2005

    For the 2005 data, I wanted to compare the P06ic production (which includes SVT and SSD in tracking) with the P06ib production (TPC-only tracking). However, only a small number of tracks actually included SVT or SSD hits in the P06ic data sample.

     

    2005 CuCu P06ib 200GeV RFF data P06ic 200GeV RFF data P06ic 62GeV RFF data
    <sDCA>
    sDCA - <sDCA> vs. day
    sDCA - <sDCA> vs. day
    sDCA - <sDCA> vs. SpaceCharge

    Here, we again see <sDCA> distortions on the order of +/-200 microns, which are there independently of the SVT and SSD usage. This time, the feature at phi~3 is much more prominent, subsiding as the days progressed. It should be considered that the dip in this particular distortion is still atop the ~400 micron peak in the <sDCA> distribution at the same phi, so it is not reversing, but just decreasing relative to the average. A compensating feature appears at phi~4.5, which should exist if the E-by-E SpaceCharge code is working properly since it tries to pull the mean of all sDCAs to zero. It is difficult to say exactly what this means in terms of how the backgrounds causing this look.

    There appears to be an "event" of some sort for only the first few runs on day 40, as seen by the offset sDCA-<sDCA> plots.

    The 62 GeV CuCu data appears to have smaller static and dynamic distortions.

     


    Gene Van Buren

    Table Insertion Timeline

    Under:

    Effect of SVT and SSD on SpaceCharge Calibration (wrong SSD errors)

    Under:
    The method of determining the amount of SpaceCharge present in the TPC from the sDCA of global tracks has worked well in the productions where only TPC hits have been used on tracks.

    FY04

    Under:
    Project Start Date: Fri 1/2/04
    Project Finish Date: Mon 10/25/04

    STAR FY04 v3 Shutdown


    ID
    Name
    DurationStart_DateFinish_DateResource_NamesPredecessorsSuccessors
    1
    STAR Detector Operations
    211.35 daysMon 1/5/04Mon 10/25/04   
    2
    Physics Run FY04
    96 daysMon 1/5/04Sat 5/15/04  5FF
    3
    Start Shutdown Activities
    116.35 daysSat 5/15/04Mon 10/25/04   
    4
    Move Detector into AB
    14.6 daysSat 5/15/04Thu 6/3/04   
    5
    Purge TPC Gas
    1 daySat 5/15/04Sat 5/15/04 2FF6SS
    6
    Subsystem Testing
    6 daysSat 5/15/04Fri 5/21/04 5SS7
    7
    Retract PMD Detector
    0.1 daysMon 5/24/04Mon 5/24/04Mech.Tech.68
    8
    Remove East BBC Detector
    0.25 daysMon 5/24/04Mon 5/24/04Mech.Tech.79
    9
    Retract East Pole Tip
    0.5 daysMon 5/24/04Mon 5/24/04Mech.Tech.[2]810FF
    10
    Install Scaffold
    0.25 daysMon 5/24/04Mon 5/24/04Carpenter[2]9FF12,11
    11
    Remove Shield Wall
    2.5 daysMon 5/24/04Thu 5/27/04Riggers[3]1026,23,16SS,18,135
    12
    Remove West Pole Tip Utilities
    0.25 daysMon 5/24/04Tue 5/25/04Mech.Tech.1013
    13
    Remove West BBC Detector
    0.25 daysTue 5/25/04Tue 5/25/04Mech.Tech.1214
    14
    Retract West Pole Tip
    0.5 daysTue 5/25/04Tue 5/25/04Mech.Tech.[2]1315FF
    15
    Install Scaffold
    0.13 daysTue 5/25/04Tue 5/25/04Carpenter[2]14FF 
    16
    Disconnect Electrical Power
    0.5 daysMon 5/24/04Tue 5/25/04Electrician[2]11SS18,17
    17
    Disconnect Magnet Power
    0.5 daysTue 5/25/04Tue 5/25/04Elect.Tech.[2]1618
    18
    Remove Buss Bridge
    0.25 daysThu 5/27/04Thu 5/27/04Mech.Tech.[2]16,17,1119,21
    19
    Disconnect Platform MCWS
    0.5 daysThu 5/27/04Fri 5/28/04Mech.Tech.1820
    20
    Disconnect Subsystems Utilities
    1 dayFri 5/28/04Mon 5/31/04Mech.Tech.1926
    21
    Remove Platform Bridge
    0.25 daysThu 5/27/04Thu 5/27/04Mech.Tech.[2]1826,22
    22
    Remove South Platform Stairs
    0.25 daysThu 5/27/04Fri 5/28/04Mech.Tech.[2]2126,24
    23
    Disconnect RHIC Vacuum Pipe
    0.5 daysThu 5/27/04Thu 5/27/04Mech.Tech.11 
    24
    Remove Seismic Anchors
    0.25 daysFri 5/28/04Fri 5/28/04Mech.Tech.[2]2225
    25
    Disconnect Magnet LCW
    0.25 daysFri 5/28/04Fri 5/28/04Mech.Tech.[2]2426
    26
    Roll Detector into AB
    1 dayMon 5/31/04Tue 6/1/04Mech.Tech.[2]11,21,22,25,2027
    27
    Blow-out Magnet Coils
    0.5 daysTue 6/1/04Tue 6/1/04Mech.Tech.[2]2628
    28
    Connect South Platform Stairs
    0.5 daysTue 6/1/04Wed 6/2/04Mech.Tech.[2]2729
    29
    Connect Platform Bridge
    0.5 daysWed 6/2/04Wed 6/2/04Mech.Tech.[2]2831,30
    30
    Connect Seismic Anchors
    0.5 daysWed 6/2/04Thu 6/3/04Mech.Tech.29 
    31
    Install Buss Bridge
    0.5 daysWed 6/2/04Thu 6/3/04Mech.Tech.[2]2932
    32
    Connect Electrical Power
    0.5 daysThu 6/3/04Thu 6/3/04Electrician[2]3133SS
    33
    Connect Subsystems Utilities
    0.5 daysThu 6/3/04Thu 6/3/04Mech.Tech.32SS34SS
    34
    Connect Platform MCWS
    0.5 daysThu 6/3/04Thu 6/3/04Mech.Tech.33SS35
    35
    Detector In AB
    0 daysThu 6/3/04Thu 6/3/04 3437,117,121
    36
    Remove East & West FTPC
    13.75 daysThu 6/3/04Wed 6/23/04   
    37
    Remove E/W IFC Air Manifolds
    0.25 daysThu 6/3/04Thu 6/3/04Mech.Tech.3538
    38
    Remove East & West Scaffold
    0.5 daysThu 6/3/04Fri 6/4/04Carpenter[2]3739
    39
    Install West Platform & Rails
    1 dayFri 6/4/04Mon 6/7/04Carpenter[2]3840,41
    40
    Remove West FTPC
    0.5 daysMon 6/7/04Mon 6/7/04Mech.Tech.3945
    41
    Rig Installation Frame into AB
    0.5 daysMon 6/7/04Mon 6/7/04Riggers[3]3942SS
    42
    Install East Installation Frame
    0.5 daysMon 6/7/04Mon 6/7/04Mech.Tech.[2]41SS43
    43
    Install East Rails
    1 dayMon 6/7/04Tue 6/8/04Mech.Tech.[2]4244
    44
    Remove East FTPC
    0.5 daysTue 6/8/04Wed 6/9/04Mech.Tech.[2]4345
    45
    East & West FTPC's Removed
    0 daysWed 6/9/04Wed 6/9/04 40,4446,48
    46
    Maintenance on FTPC's
    10 daysWed 6/9/04Wed 6/23/04Electronic Tech45 
    47
    Remove Cone
    11.5 daysWed 6/9/04Thu 6/24/04   
    48
    Disconnect Utilities
    4 daysWed 6/9/04Tue 6/15/04Mech.Tech.4549
    49
    Remove Cone from IFC
    0.5 daysTue 6/15/04Tue 6/15/04Mech.Tech.4876,126
    50
    Remove East Installation Frame
    1 dayTue 6/22/04Wed 6/23/04Mech.Tech.[2]76,12651FF
    51
    Remove Installation Frame from AB
    0.5 daysWed 6/23/04Wed 6/23/04Riggers[3]50FF52
    52
    Remove Installation Frame West
    1 dayWed 6/23/04Thu 6/24/04Carpenter[2]5153
    53
    Cone Removed
    0 daysThu 6/24/04Thu 6/24/04 5257
    54
    Install East BEMC Modules
    47.5 daysMon 6/14/04Wed 8/18/04   
    55
    (30) Modules Delivered
    4 daysMon 6/14/04Fri 6/18/04Riggers[3]57FF-5 days56FF
    56
    (30) Modules Staged in AB
    4 daysMon 6/14/04Fri 6/18/04Mech.Tech.[2]55FF 
    57
    Install East & West Scaffold
    0.5 daysThu 6/24/04Fri 6/25/04Carpenter[2]5358,55FF-5 days
    58
    Remove East Side Cables & Tray
    3 daysFri 6/25/04Wed 6/30/04Mech.Tech.[2]5759
    59
    Erect Installation Fixture S.E. Upper
    0.5 daysWed 6/30/04Wed 6/30/04Mech.Tech.[2]5860
    60
    Remove S.E. TPC Support Arm
    0.25 daysWed 6/30/04Thu 7/1/04Mech.Tech.[2]5961
    61
    Install Modules 106-103
    4 daysThu 7/1/04Wed 7/7/04Mech.Tech.[2]6062
    62
    Erect Installation Fixture S.E. Lower
    0.5 daysWed 7/7/04Wed 7/7/04Mech.Tech.[2]6163
    63
    Install Modules 102-89
    14 daysWed 7/7/04Tue 7/27/04Mech.Tech.[2]6264
    64
    Install S.E. TPC Support Arm
    0.5 daysTue 7/27/04Wed 7/28/04Mech.Tech.[2]6365
    65
    Erect Installation Fixture N.E. Lower
    0.5 daysWed 7/28/04Wed 7/28/04Mech.Tech.[2]6466
    66
    Install Modules 77-88
    12 daysWed 7/28/04Fri 8/13/04Mech.Tech.[2]6567
    67
    Remove Installation Fixture
    0.25 daysFri 8/13/04Fri 8/13/04Mech.Tech.[2]6668
    68
    Install East Side Cables & Tray
    3 daysFri 8/13/04Wed 8/18/04Mech.Tech.[2]6769
    69
    East BEMC Installation Complete
    0 daysWed 8/18/04Wed 8/18/04 6882,72
    70
    Install BEMC PMT Boxes
    35 daysWed 7/14/04Wed 9/1/04   
    71
    Install 208 VAC Power
    15 daysWed 7/14/04Wed 8/4/04Electrician[2]72SF-10 days 
    72
    Install PMT Boxes
    10 daysWed 8/18/04Wed 9/1/04Mech.Tech.[2]6973FF,71SF-10 days
    73
    Install Electronics
    20 daysWed 8/4/04Wed 9/1/04Electronic Tech72FF74
    74
    PMT Box Installation Complete
    0 daysWed 9/1/04Wed 9/1/04 73144
    75
    Install SSD
    20.5 daysTue 6/15/04Wed 7/14/04   
    76
    Rig Cone to Cleanroom Roof
    0.5 daysTue 6/15/04Wed 6/16/04Mech.Tech.4977,50
    77
    Install SSD on Cone
    20 daysWed 6/16/04Wed 7/14/04Mech.Tech.7678SS,80
    78
    Install LV Crate & Cables
    5 daysWed 6/16/04Wed 6/23/04Electronic Tech77SS79
    79
    Install RDO Boxes
    5 daysWed 6/23/04Wed 6/30/04Electronic Tech78 
    80
    SSD Installed on Cone
    0 daysWed 7/14/04Wed 7/14/04 7785
    81
    Install Cone
    20.5 daysWed 8/18/04Thu 9/16/04   
    82
    Rig Installation Frame into AB
    0.5 daysWed 8/18/04Thu 8/19/04Riggers[3]6983SS
    83
    Install East Installation Frame
    0.5 daysWed 8/18/04Thu 8/19/04Mech.Tech.[2]82SS84
    84
    Install Tables & Rails
    0.5 daysThu 8/19/04Thu 8/19/04Mech.Tech.8385
    85
    Rig Cone to Rails
    0.5 daysThu 8/19/04Fri 8/20/04Mech.Tech.[2]84,8086
    86
    Survey SSD to SVT
    2 daysFri 8/20/04Tue 8/24/04Surveyors[2]8587
    87
    Complete SSD Installation
    2 daysTue 8/24/04Thu 8/26/04Mech.Tech.8688
    88
    Test Utility Connections
    1 dayThu 8/26/04Fri 8/27/04Electronic Tech8789FF
    89
    Clean TPC IFC
    1 dayThu 8/26/04Fri 8/27/04Mech.Tech.88FF90
    90
    Install Cone in Detector
    0.5 daysFri 8/27/04Fri 8/27/04Mech.Tech.8991
    91
    Test IFC High Voltage
    0.5 daysFri 8/27/04Mon 8/30/04Electronic Tech9092
    92
    Survey TPC to Magnet
    2 daysMon 8/30/04Wed 9/1/04Surveyors[2]9193
    93
    Survey SVT to TPC
    2 daysWed 9/1/04Fri 9/3/04Surveyors[2]9294
    94
    Install East Partitions
    0.5 daysFri 9/3/04Fri 9/3/04Mech.Tech.93110
    95
    Connect Water Lines
    0.5 daysMon 9/6/04Tue 9/7/04Mech.Tech.11096
    96
    Connect RDO Cables
    1 dayTue 9/7/04Wed 9/8/04Electronic Tech9597
    97
    Remove East Rails from IFC
    0.5 daysWed 9/8/04Wed 9/8/04Mech.Tech.[2]9698
    98
    Remove East Installation Frame
    0.5 daysWed 9/8/04Thu 9/9/04Mech.Tech.[2]9799FF
    99
    Remove Installation Frame from AB
    0.25 daysThu 9/9/04Thu 9/9/04Riggers[3]98FF100
    100
    East Side Complete
    0 daysThu 9/9/04Thu 9/9/04 99107,101
    101
    Install West Partitions
    0.5 daysThu 9/9/04Thu 9/9/04Mech.Tech.100112
    102
    Connect Water Lines
    0.5 daysMon 9/13/04Mon 9/13/04Mech.Tech.114103
    103
    Connect RDO Cables
    1 dayMon 9/13/04Tue 9/14/04Electronic Tech102104
    104
    Remove West Rails from IFC
    0.5 daysTue 9/14/04Wed 9/15/04Mech.Tech.103105
    105
    Remove Installation Frame West
    1 dayWed 9/15/04Thu 9/16/04Carpenter[2]104106
    106
    West Side Complete
    0 daysThu 9/16/04Thu 9/16/04 105107
    107
    Cone Installation Complete
    0 daysThu 9/16/04Thu 9/16/04 100,106144
    108
    Install FTPC East & West in AB
    12.5 daysWed 8/25/04Mon 9/13/04   
    109
    Run & Test N. Platform
    5 daysWed 8/25/04Wed 9/1/04Electronic Tech110SF-2 days 
    110
    Install East FTPC in Detector
    1 dayFri 9/3/04Mon 9/6/04Mech.Tech.[2]94115,109SF-2 days,95
    111
    Run & Test N. Platform
    5 daysWed 9/1/04Wed 9/8/04Electronic Tech114SF-2 days 
    112
    Remove West Scaffold
    0.25 daysThu 9/9/04Fri 9/10/04Carpenter[2]101113
    113
    Install West Platform & Rails
    0.25 daysFri 9/10/04Fri 9/10/04Carpenter[2]112114
    114
    Install West FTPC in Detector
    1 dayFri 9/10/04Mon 9/13/04Mech.Tech.[2]113115,111SF-2 days,102
    115
    FTPC Installed in AB
    0 daysMon 9/13/04Mon 9/13/04 114,110 
    116
    PMD Maintenance
    40 daysThu 6/3/04Thu 7/29/04   
    117
    Subsystem Maintenance
    30 daysThu 6/3/04Thu 7/15/04 35118
    118
    Detector Commisioning
    10 daysThu 7/15/04Thu 7/29/04 117119
    119
    PMD Maintenance Complete
    0 daysThu 7/29/04Thu 7/29/04 118 
    120
    EEMC Maintenance
    90 daysThu 6/3/04Thu 10/7/04   
    121
    Maintenance
    50 daysThu 6/3/04Thu 8/12/04 35122SS
    122
    MAPMT Installation
    80 daysThu 6/3/04Thu 9/23/04Mech.Tech.[2]121SS123
    123
    Subsystem Testing
    10 daysThu 9/23/04Thu 10/7/04 122124
    124
    EEMC Maintenance Complete
    0 daysThu 10/7/04Thu 10/7/04 123 
    125
    TPC Maintenance
    50 daysTue 6/15/04Tue 8/24/04   
    126
    Repair IFC Strip Short
    5 daysTue 6/15/04Tue 6/22/04Mech.Tech.49127,50,131SS
    127
    Modify Resistor Chain
    5 daysTue 6/22/04Tue 6/29/04Mech.Tech.126128
    128
    FEE & RDO Maintenance
    40 daysTue 6/29/04Tue 8/24/04Electronic Tech127129
    129
    TPC Maintenance Complete
    0 daysTue 8/24/04Tue 8/24/04 128 
    130
    TOF Maintenance
    15 daysTue 6/15/04Tue 7/6/04   
    131
    Tray Maintenance
    10 daysTue 6/15/04Tue 6/29/04 126SS132
    132
    Detector Testing
    5 daysTue 6/29/04Tue 7/6/04 131133
    133
    TOFp Maintenance Complete
    0 daysTue 7/6/04Tue 7/6/04 132 
    134
    FPD Installation
    20 daysThu 5/27/04Thu 6/24/04   
    135
    Install West Detectors
    10 daysThu 5/27/04Thu 6/10/04Mech.Tech.11136
    136
    Install N. E. Stand for 20-cm Travel
    5 daysThu 6/10/04Thu 6/17/04Mech.Tech.[2]135137
    137
    Detector Commisioning
    5 daysThu 6/17/04Thu 6/24/04 136138
    138
    FPD Installation Complete
    0 daysThu 6/24/04Thu 6/24/04 137140
    139
    BBC Maintenance
    15 daysThu 6/24/04Thu 7/15/04   
    140
    Subsystem Maintenance
    10 daysThu 6/24/04Thu 7/8/04 138141
    141
    Detector Commisioning
    5 daysThu 7/8/04Thu 7/15/04 140142
    142
    BBC Maintenance Complete
    0 daysThu 7/15/04Thu 7/15/04 141 
    143
    Move Detector into WAH
    27 daysThu 9/16/04Mon 10/25/04   
    144
    Disconnect Electrical Power
    0.5 daysThu 9/16/04Thu 9/16/04Electrician[2]107,74147,145SS,146SS
    145
    Disconnect Platform MCWS
    0.5 daysThu 9/16/04Thu 9/16/04Mech.Tech.144SS 
    146
    Disconnect TPC Utilities
    0.5 daysThu 9/16/04Thu 9/16/04Mech.Tech.144SS 
    147
    Remove Buss Bridge
    0.5 daysThu 9/16/04Fri 9/17/04Mech.Tech.[2]144148
    148
    Remove Platform Bridge
    0.5 daysFri 9/17/04Fri 9/17/04Mech.Tech.[2]147149
    149
    Remove South Platform Stairs
    1 dayFri 9/17/04Mon 9/20/04Mech.Tech.[2]148150
    150
    Disconnect Seismic Anchors
    0.5 daysMon 9/20/04Tue 9/21/04Mech.Tech.[2]149151SS
    151
    Lower Detector to Rails
    0.5 daysMon 9/20/04Tue 9/21/04Mech.Tech.[2]150SS152
    152
    Roll Detector into WAH
    1.5 daysTue 9/21/04Wed 9/22/04Mech.Tech.[2]151153,154
    153
    Connect Magnet LCW
    1 dayWed 9/22/04Thu 9/23/04Mech.Tech.[2]152 
    154
    Raise/Level Detector @ IR
    0.5 daysWed 9/22/04Thu 9/23/04Mech.Tech.[2]152155FF,163
    155
    Connect Seismic Anchors
    0.5 daysWed 9/22/04Thu 9/23/04Mech.Tech.[2]154FF159,156
    156
    Install Buss Bridge
    0.5 daysThu 9/23/04Thu 9/23/04Mech.Tech.[2]155157,160
    157
    Connect Electrical Power
    1 dayThu 9/23/04Fri 9/24/04Electrician[2]156158
    158
    Connect Magnet Power
    1 dayFri 9/24/04Mon 9/27/04Elect.Tech.[2]157 
    159
    Connect All Subsystem Utilities
    2 daysThu 9/23/04Mon 9/27/04Mech.Tech.[2]155168,166
    160
    Connect Platform MCWS
    0.5 daysThu 9/23/04Fri 9/24/04Mech.Tech.156168,161
    161
    Connect South Platform Stairs
    1 dayFri 9/24/04Mon 9/27/04Mech.Tech.[2]160162
    162
    Connect Platform Bridge
    0.5 daysMon 9/27/04Mon 9/27/04Mech.Tech.[2]161167
    163
    Connect Vacuum Pipe & Supports
    0.5 daysThu 9/23/04Thu 9/23/04Mech.Tech.[2]154164
    164
    Vacuum Pipe Bake-out
    5 daysThu 9/23/04Thu 9/30/04Mech.Tech.[2]163165
    165
    Survey Beam Pipe & Magnet
    4 daysThu 9/30/04Wed 10/6/04Surveyors[2]164 
    166
    Detector Safety Certification
    2 daysMon 9/27/04Wed 9/29/04 159 
    167
    Install Shield Wall
    3 daysMon 9/27/04Thu 9/30/04Riggers[3]162171
    168
    Subsystems testing in WAH
    20 daysMon 9/27/04Mon 10/25/04 160,159169SS+5 days
    169
    Install Pole Tips
    2 daysMon 10/4/04Wed 10/6/04Mech.Tech.[2]168SS+5 days170
    170
    Install BBC Detectors
    1 dayWed 10/6/04Thu 10/7/04Mech.Tech.[2]169171
    171
    Shutdown Activities Complete
    0 daysThu 10/7/04Thu 10/7/04 167,170 

    StEmcTriggerMaker

    Under:
    Documentation provided by Renee Fatemi

    MOTIVATION:

    First Iteration

    Under:
    March 27, 2007

    Software

    Under:
    The main EMC offline reconstruction chain consists of: