computing
Updated on Fri, 2008-02-08 13:10 by testadmin. Originally created by jeromel on 2006-08-02 08:43.
Under: This page will list by year action items, run plans and opened questions. It will server as a repository for documents serving as basis for drawing the requirements.
Updated on Fri, 2007-02-16 23:24. Originally created by starembed on 2006-08-01 17:12.
Under: Overview
The document is intended as a forum for embedding group members to share information and notes.
Updated on Thu, 2007-02-22 15:22. Originally created by starembed on 2006-08-01 17:10.
Under:
dEdx Comparisons
These are dedx vs P graphs. All of them show reasonable agreement with data.(Done on May 2002)
![Dedx-dedxPiPlus.gif](/STAR/files/images/Dedx-dedxPiPlus.gif)
|
Updated on Fri, 2008-08-22 10:16. Originally created by starembed on 2006-08-01 17:07.
Under: Overview This page is intended to provide details of embedding jobs currently in production.
Updated on Sat, 2018-06-23 09:48 by zhux. Originally created by starembed on 2006-08-01 17:00.
Under: Overview
Updated on Sat, 2018-06-23 10:02 by zhux. Originally created by starembed on 2006-08-01 16:55.
Under: Overview
Updated on Thu, 2006-07-27 17:01. Originally created by jeromel on 2006-07-27 16:45.
Under: On this page, we will save snapshots of how SUMS "sees" the Grid utilization.
Updated on Fri, 2007-10-19 11:16. Originally created by kocolosk on 2006-07-15 15:14.
Under: This page describes the original cluster finder algorithm. In order to use this algorithm you should set with the algorithm kEmcClOld.
Updated on Thu, 2007-10-18 15:52. Originally created by kocolosk on 2006-07-15 15:13.
Under: This task has been picked up by Rory Clarke from TAMU. His page is here:
http://www4.rcf.bnl.gov/~rfc/
Updated on Fri, 2007-10-19 11:18. Originally created by kocolosk on 2006-07-15 15:10.
Under: After obtaining the clusters for 4 subdetectors, we need to obtain the information about the incident shower by making the proper matching between clusters from different subdetectors.
Updated on Mon, 2007-10-15 09:10. Originally created by kocolosk on 2006-07-15 15:05.
Under:
Updated on Wed, 2012-12-19 14:57. Originally created by genevb on 2006-07-07 17:00.
Under: The method of determining the amount of SpaceCharge present in the TPC from the signed distance of closest approach (sDCA) of global tracks to the primary vertex has worked well in the productions whe
Updated on Fri, 2006-06-23 13:33. Originally created by jeromel on 2006-06-23 13:05.
Under:
Thursday, 1 January 1970 , at 00:00 (GMT), duration : 00:00 Instead of an official agenda item list, here is a "lose" agenda
item for this 8th coordination meeting.
- General focus statement, next check point
- Comment on current review agenda available as
[node:2391]
- Christina's D0 observations, samples needed and conditions [last call]
last list [node:2361]
- Comments from Rene/Helen/anyone else on Anthony results
http://www.star.bnl.gov/protected/strange/atimmins/CuCuSVTQA/SVTQA.htm
- Progress and/or issues from Sarah + needs
- Progress and/or issues with B-studies + needs
- Opened discussion: strangeness Physics content and focus
Previous meetings are available at
- [node:1297]
- [node:1540]
- [node:1568]
- [node:2299]
- [node:2298]
- [node:2300]
- [node:2360]
Updated on Thu, 2013-06-27 12:17 by testadmin. Originally created by genevb on 2006-06-21 17:43.
Under: In order to better understand possible anisotropies in the azimuthal distribution of SpaceCharge (see, for example, zerobias data from day 47 of 2004), I have examined the signed DCA (sDCA) aziumthal distributions from several productions. I have separated these distributions into a static component and a dynamic component by determining <sDCA> in each phi bin for each dataset examined, and then looking at the differences from this mean. The mean does not truly equal the static component, but it is very helpful to subtract this component in order to see the the time-evolving component as both components are of similar magnitudes.
In the plots below, the first row shows the <sDCA> value for each phi bin (the bins are aligned along TPC sectors going from 2 o'clock, 1 o'clock, 12 o'clock, .... , 3o'clock with increasing phi). In the subsequent rows, I plot sDCA-<sDCA> versus day (with each phi bin offset) to see what's happening on sub-day time scales, versus day in a colored 2D graph to see what's happening on larger time scales, and versus SpaceCharge to see what's happening versus luminosity.
Additional comments below the plots.
2004
2004 AuAu200 |
early RFF data |
FF data |
late RFF data |
<sDCA> |
![](/STAR/system/files/active/0/P05ic_RFFa_sdca_means.png) |
![](/STAR/system/files/active/0/P05ic_FF_sdca_means.png) |
![](/STAR/system/files/active/0/P05ic_RFFb_sdca_means.png) |
sDCA - <sDCA> vs. day |
![](/STAR/system/files/active/0/P05ic_RFFa_sdca_chart.png) |
![](/STAR/system/files/active/0/P05ic_FF_sdca_chart.png) |
![](/STAR/system/files/active/0/P05ic_RFFb_sdca_chart.png) |
sDCA - <sDCA> vs. day |
![](/STAR/system/files/active/0/P05ic_RFFa_sdca_variance.png) |
![](/STAR/system/files/active/0/P05ic_FF_sdca_variance.png) |
![](/STAR/system/files/active/0/P05ic_RFFb_sdca_variance.png) |
sDCA - <sDCA> vs. SpaceCharge |
![](/STAR/system/files/active/0/P05ic_RFFa_sdca_spacecharge_high.png) |
![](/STAR/system/files/active/0/P05ic_FF_sdca_spacecharge.png) |
![](/STAR/system/files/active/0/P05ic_RFFb_sdca_spacecharge.png) |
The <sDCA> values appear to have fluctuation on the +/-200 micron scale in azimuth. The FF and late RFF data show a feature at phi~3 that is probably due to backgrounds from the collider entering the TPC and causing SpaceCharge distortions in only one region in phi. All of the fluctuations seem to subside to well below 100 microns at the lowest luminosities, implying that <sDCA> perhaps does represent well the static misalignments/distortions.
For the early RFF data, there are some unusual structures. The above SpaceCharge plot for this data was set so that the range of sDCA at higher luminosities could be viewed. Here is a plot of the same data with the range modified to see more clearly the low luminosity data, for which the fluctuations are again well below 100 microns.
![](/STAR/system/files/active/0/P05ic_RFFa_sdca_spacecharge_low.png)
2005
For the 2005 data, I wanted to compare the P06ic production (which includes SVT and SSD in tracking) with the P06ib production (TPC-only tracking). However, only a small number of tracks actually included SVT or SSD hits in the P06ic data sample.
2005 CuCu |
P06ib 200GeV RFF data |
P06ic 200GeV RFF data |
P06ic 62GeV RFF data |
<sDCA> |
![](/STAR/system/files/active/0/P06ib_RFF_cu200_sdca_means.png) |
![](/STAR/system/files/active/0/P06ic_RFF_cu200_sdca_means.png) |
![](/STAR/system/files/active/0/P06ic_RFF_cu62_sdca_means.png) |
sDCA - <sDCA> vs. day |
![](/STAR/system/files/active/0/P06ib_RFF_cu200_sdca_chart.png) |
![](/STAR/system/files/active/0/P06ic_RFF_cu200_sdca_chart.png) |
![](/STAR/system/files/active/0/P06ic_RFF_cu62_sdca_chart.png) |
sDCA - <sDCA> vs. day |
![](/STAR/system/files/active/0/P06ib_RFF_cu200_sdca_variance.png) |
![](/STAR/system/files/active/0/P06ic_RFF_cu200_sdca_variance.png) |
![](/STAR/system/files/active/0/P06ic_RFF_cu62_sdca_variance.png) |
sDCA - <sDCA> vs. SpaceCharge |
![](/STAR/system/files/active/0/P06ib_RFF_cu200_sdca_spacecharge.png) |
![](/STAR/system/files/active/0/P06ic_RFF_cu200_sdca_spacecharge.png) |
![](/STAR/system/files/active/0/P06ic_RFF_cu62_sdca_spacecharge.png) |
Here, we again see <sDCA> distortions on the order of +/-200 microns, which are there independently of the SVT and SSD usage. This time, the feature at phi~3 is much more prominent, subsiding as the days progressed. It should be considered that the dip in this particular distortion is still atop the ~400 micron peak in the <sDCA> distribution at the same phi, so it is not reversing, but just decreasing relative to the average. A compensating feature appears at phi~4.5, which should exist if the E-by-E SpaceCharge code is working properly since it tries to pull the mean of all sDCAs to zero. It is difficult to say exactly what this means in terms of how the backgrounds causing this look.
There appears to be an "event" of some sort for only the first few runs on day 40, as seen by the offset sDCA-<sDCA> plots.
The 62 GeV CuCu data appears to have smaller static and dynamic distortions.
Gene Van Buren
Updated on Fri, 2007-10-19 15:52. Originally created by kocolosk on 2006-06-20 22:12.
Under:
Updated on Wed, 2012-12-19 14:56. Originally created by genevb on 2006-06-20 15:04.
Under: The method of determining the amount of SpaceCharge present in the TPC from the sDCA of global tracks has worked well in the productions where only TPC hits have been used on tracks.
Updated on Thu, 2006-06-15 15:13. Originally created by rlbrown on 2006-06-15 15:13.
Under: Project Start Date: Fri 1/2/04
Project Finish Date: Mon 10/25/04 STAR FY04 v3 ShutdownID | Name | Duration | Start_Date | Finish_Date | Resource_Names | Predecessors | Successors |
1 | STAR Detector Operations | 211.35 days | Mon 1/5/04 | Mon 10/25/04 | | | |
2 | Physics Run FY04 | 96 days | Mon 1/5/04 | Sat 5/15/04 | | | 5FF |
3 | Start Shutdown Activities | 116.35 days | Sat 5/15/04 | Mon 10/25/04 | | | |
4 | Move Detector into AB | 14.6 days | Sat 5/15/04 | Thu 6/3/04 | | | |
5 | Purge TPC Gas | 1 day | Sat 5/15/04 | Sat 5/15/04 | | 2FF | 6SS |
6 | Subsystem Testing | 6 days | Sat 5/15/04 | Fri 5/21/04 | | 5SS | 7 |
7 | Retract PMD Detector | 0.1 days | Mon 5/24/04 | Mon 5/24/04 | Mech.Tech. | 6 | 8 |
8 | Remove East BBC Detector | 0.25 days | Mon 5/24/04 | Mon 5/24/04 | Mech.Tech. | 7 | 9 |
9 | Retract East Pole Tip | 0.5 days | Mon 5/24/04 | Mon 5/24/04 | Mech.Tech.[2] | 8 | 10FF |
10 | Install Scaffold | 0.25 days | Mon 5/24/04 | Mon 5/24/04 | Carpenter[2] | 9FF | 12,11 |
11 | Remove Shield Wall | 2.5 days | Mon 5/24/04 | Thu 5/27/04 | Riggers[3] | 10 | 26,23,16SS,18,135 |
12 | Remove West Pole Tip Utilities | 0.25 days | Mon 5/24/04 | Tue 5/25/04 | Mech.Tech. | 10 | 13 |
13 | Remove West BBC Detector | 0.25 days | Tue 5/25/04 | Tue 5/25/04 | Mech.Tech. | 12 | 14 |
14 | Retract West Pole Tip | 0.5 days | Tue 5/25/04 | Tue 5/25/04 | Mech.Tech.[2] | 13 | 15FF |
15 | Install Scaffold | 0.13 days | Tue 5/25/04 | Tue 5/25/04 | Carpenter[2] | 14FF | |
16 | Disconnect Electrical Power | 0.5 days | Mon 5/24/04 | Tue 5/25/04 | Electrician[2] | 11SS | 18,17 |
17 | Disconnect Magnet Power | 0.5 days | Tue 5/25/04 | Tue 5/25/04 | Elect.Tech.[2] | 16 | 18 |
18 | Remove Buss Bridge | 0.25 days | Thu 5/27/04 | Thu 5/27/04 | Mech.Tech.[2] | 16,17,11 | 19,21 |
19 | Disconnect Platform MCWS | 0.5 days | Thu 5/27/04 | Fri 5/28/04 | Mech.Tech. | 18 | 20 |
20 | Disconnect Subsystems Utilities | 1 day | Fri 5/28/04 | Mon 5/31/04 | Mech.Tech. | 19 | 26 |
21 | Remove Platform Bridge | 0.25 days | Thu 5/27/04 | Thu 5/27/04 | Mech.Tech.[2] | 18 | 26,22 |
22 | Remove South Platform Stairs | 0.25 days | Thu 5/27/04 | Fri 5/28/04 | Mech.Tech.[2] | 21 | 26,24 |
23 | Disconnect RHIC Vacuum Pipe | 0.5 days | Thu 5/27/04 | Thu 5/27/04 | Mech.Tech. | 11 | |
24 | Remove Seismic Anchors | 0.25 days | Fri 5/28/04 | Fri 5/28/04 | Mech.Tech.[2] | 22 | 25 |
25 | Disconnect Magnet LCW | 0.25 days | Fri 5/28/04 | Fri 5/28/04 | Mech.Tech.[2] | 24 | 26 |
26 | Roll Detector into AB | 1 day | Mon 5/31/04 | Tue 6/1/04 | Mech.Tech.[2] | 11,21,22,25,20 | 27 |
27 | Blow-out Magnet Coils | 0.5 days | Tue 6/1/04 | Tue 6/1/04 | Mech.Tech.[2] | 26 | 28 |
28 | Connect South Platform Stairs | 0.5 days | Tue 6/1/04 | Wed 6/2/04 | Mech.Tech.[2] | 27 | 29 |
29 | Connect Platform Bridge | 0.5 days | Wed 6/2/04 | Wed 6/2/04 | Mech.Tech.[2] | 28 | 31,30 |
30 | Connect Seismic Anchors | 0.5 days | Wed 6/2/04 | Thu 6/3/04 | Mech.Tech. | 29 | |
31 | Install Buss Bridge | 0.5 days | Wed 6/2/04 | Thu 6/3/04 | Mech.Tech.[2] | 29 | 32 |
32 | Connect Electrical Power | 0.5 days | Thu 6/3/04 | Thu 6/3/04 | Electrician[2] | 31 | 33SS |
33 | Connect Subsystems Utilities | 0.5 days | Thu 6/3/04 | Thu 6/3/04 | Mech.Tech. | 32SS | 34SS |
34 | Connect Platform MCWS | 0.5 days | Thu 6/3/04 | Thu 6/3/04 | Mech.Tech. | 33SS | 35 |
35 | Detector In AB | 0 days | Thu 6/3/04 | Thu 6/3/04 | | 34 | 37,117,121 |
36 | Remove East & West FTPC | 13.75 days | Thu 6/3/04 | Wed 6/23/04 | | | |
37 | Remove E/W IFC Air Manifolds | 0.25 days | Thu 6/3/04 | Thu 6/3/04 | Mech.Tech. | 35 | 38 |
38 | Remove East & West Scaffold | 0.5 days | Thu 6/3/04 | Fri 6/4/04 | Carpenter[2] | 37 | 39 |
39 | Install West Platform & Rails | 1 day | Fri 6/4/04 | Mon 6/7/04 | Carpenter[2] | 38 | 40,41 |
40 | Remove West FTPC | 0.5 days | Mon 6/7/04 | Mon 6/7/04 | Mech.Tech. | 39 | 45 |
41 | Rig Installation Frame into AB | 0.5 days | Mon 6/7/04 | Mon 6/7/04 | Riggers[3] | 39 | 42SS |
42 | Install East Installation Frame | 0.5 days | Mon 6/7/04 | Mon 6/7/04 | Mech.Tech.[2] | 41SS | 43 |
43 | Install East Rails | 1 day | Mon 6/7/04 | Tue 6/8/04 | Mech.Tech.[2] | 42 | 44 |
44 | Remove East FTPC | 0.5 days | Tue 6/8/04 | Wed 6/9/04 | Mech.Tech.[2] | 43 | 45 |
45 | East & West FTPC's Removed | 0 days | Wed 6/9/04 | Wed 6/9/04 | | 40,44 | 46,48 |
46 | Maintenance on FTPC's | 10 days | Wed 6/9/04 | Wed 6/23/04 | Electronic Tech | 45 | |
47 | Remove Cone | 11.5 days | Wed 6/9/04 | Thu 6/24/04 | | | |
48 | Disconnect Utilities | 4 days | Wed 6/9/04 | Tue 6/15/04 | Mech.Tech. | 45 | 49 |
49 | Remove Cone from IFC | 0.5 days | Tue 6/15/04 | Tue 6/15/04 | Mech.Tech. | 48 | 76,126 |
50 | Remove East Installation Frame | 1 day | Tue 6/22/04 | Wed 6/23/04 | Mech.Tech.[2] | 76,126 | 51FF |
51 | Remove Installation Frame from AB | 0.5 days | Wed 6/23/04 | Wed 6/23/04 | Riggers[3] | 50FF | 52 |
52 | Remove Installation Frame West | 1 day | Wed 6/23/04 | Thu 6/24/04 | Carpenter[2] | 51 | 53 |
53 | Cone Removed | 0 days | Thu 6/24/04 | Thu 6/24/04 | | 52 | 57 |
54 | Install East BEMC Modules | 47.5 days | Mon 6/14/04 | Wed 8/18/04 | | | |
55 | (30) Modules Delivered | 4 days | Mon 6/14/04 | Fri 6/18/04 | Riggers[3] | 57FF-5 days | 56FF |
56 | (30) Modules Staged in AB | 4 days | Mon 6/14/04 | Fri 6/18/04 | Mech.Tech.[2] | 55FF | |
57 | Install East & West Scaffold | 0.5 days | Thu 6/24/04 | Fri 6/25/04 | Carpenter[2] | 53 | 58,55FF-5 days |
58 | Remove East Side Cables & Tray | 3 days | Fri 6/25/04 | Wed 6/30/04 | Mech.Tech.[2] | 57 | 59 |
59 | Erect Installation Fixture S.E. Upper | 0.5 days | Wed 6/30/04 | Wed 6/30/04 | Mech.Tech.[2] | 58 | 60 |
60 | Remove S.E. TPC Support Arm | 0.25 days | Wed 6/30/04 | Thu 7/1/04 | Mech.Tech.[2] | 59 | 61 |
61 | Install Modules 106-103 | 4 days | Thu 7/1/04 | Wed 7/7/04 | Mech.Tech.[2] | 60 | 62 |
62 | Erect Installation Fixture S.E. Lower | 0.5 days | Wed 7/7/04 | Wed 7/7/04 | Mech.Tech.[2] | 61 | 63 |
63 | Install Modules 102-89 | 14 days | Wed 7/7/04 | Tue 7/27/04 | Mech.Tech.[2] | 62 | 64 |
64 | Install S.E. TPC Support Arm | 0.5 days | Tue 7/27/04 | Wed 7/28/04 | Mech.Tech.[2] | 63 | 65 |
65 | Erect Installation Fixture N.E. Lower | 0.5 days | Wed 7/28/04 | Wed 7/28/04 | Mech.Tech.[2] | 64 | 66 |
66 | Install Modules 77-88 | 12 days | Wed 7/28/04 | Fri 8/13/04 | Mech.Tech.[2] | 65 | 67 |
67 | Remove Installation Fixture | 0.25 days | Fri 8/13/04 | Fri 8/13/04 | Mech.Tech.[2] | 66 | 68 |
68 | Install East Side Cables & Tray | 3 days | Fri 8/13/04 | Wed 8/18/04 | Mech.Tech.[2] | 67 | 69 |
69 | East BEMC Installation Complete | 0 days | Wed 8/18/04 | Wed 8/18/04 | | 68 | 82,72 |
70 | Install BEMC PMT Boxes | 35 days | Wed 7/14/04 | Wed 9/1/04 | | | |
71 | Install 208 VAC Power | 15 days | Wed 7/14/04 | Wed 8/4/04 | Electrician[2] | 72SF-10 days | |
72 | Install PMT Boxes | 10 days | Wed 8/18/04 | Wed 9/1/04 | Mech.Tech.[2] | 69 | 73FF,71SF-10 days |
73 | Install Electronics | 20 days | Wed 8/4/04 | Wed 9/1/04 | Electronic Tech | 72FF | 74 |
74 | PMT Box Installation Complete | 0 days | Wed 9/1/04 | Wed 9/1/04 | | 73 | 144 |
75 | Install SSD | 20.5 days | Tue 6/15/04 | Wed 7/14/04 | | | |
76 | Rig Cone to Cleanroom Roof | 0.5 days | Tue 6/15/04 | Wed 6/16/04 | Mech.Tech. | 49 | 77,50 |
77 | Install SSD on Cone | 20 days | Wed 6/16/04 | Wed 7/14/04 | Mech.Tech. | 76 | 78SS,80 |
78 | Install LV Crate & Cables | 5 days | Wed 6/16/04 | Wed 6/23/04 | Electronic Tech | 77SS | 79 |
79 | Install RDO Boxes | 5 days | Wed 6/23/04 | Wed 6/30/04 | Electronic Tech | 78 | |
80 | SSD Installed on Cone | 0 days | Wed 7/14/04 | Wed 7/14/04 | | 77 | 85 |
81 | Install Cone | 20.5 days | Wed 8/18/04 | Thu 9/16/04 | | | |
82 | Rig Installation Frame into AB | 0.5 days | Wed 8/18/04 | Thu 8/19/04 | Riggers[3] | 69 | 83SS |
83 | Install East Installation Frame | 0.5 days | Wed 8/18/04 | Thu 8/19/04 | Mech.Tech.[2] | 82SS | 84 |
84 | Install Tables & Rails | 0.5 days | Thu 8/19/04 | Thu 8/19/04 | Mech.Tech. | 83 | 85 |
85 | Rig Cone to Rails | 0.5 days | Thu 8/19/04 | Fri 8/20/04 | Mech.Tech.[2] | 84,80 | 86 |
86 | Survey SSD to SVT | 2 days | Fri 8/20/04 | Tue 8/24/04 | Surveyors[2] | 85 | 87 |
87 | Complete SSD Installation | 2 days | Tue 8/24/04 | Thu 8/26/04 | Mech.Tech. | 86 | 88 |
88 | Test Utility Connections | 1 day | Thu 8/26/04 | Fri 8/27/04 | Electronic Tech | 87 | 89FF |
89 | Clean TPC IFC | 1 day | Thu 8/26/04 | Fri 8/27/04 | Mech.Tech. | 88FF | 90 |
90 | Install Cone in Detector | 0.5 days | Fri 8/27/04 | Fri 8/27/04 | Mech.Tech. | 89 | 91 |
91 | Test IFC High Voltage | 0.5 days | Fri 8/27/04 | Mon 8/30/04 | Electronic Tech | 90 | 92 |
92 | Survey TPC to Magnet | 2 days | Mon 8/30/04 | Wed 9/1/04 | Surveyors[2] | 91 | 93 |
93 | Survey SVT to TPC | 2 days | Wed 9/1/04 | Fri 9/3/04 | Surveyors[2] | 92 | 94 |
94 | Install East Partitions | 0.5 days | Fri 9/3/04 | Fri 9/3/04 | Mech.Tech. | 93 | 110 |
95 | Connect Water Lines | 0.5 days | Mon 9/6/04 | Tue 9/7/04 | Mech.Tech. | 110 | 96 |
96 | Connect RDO Cables | 1 day | Tue 9/7/04 | Wed 9/8/04 | Electronic Tech | 95 | 97 |
97 | Remove East Rails from IFC | 0.5 days | Wed 9/8/04 | Wed 9/8/04 | Mech.Tech.[2] | 96 | 98 |
98 | Remove East Installation Frame | 0.5 days | Wed 9/8/04 | Thu 9/9/04 | Mech.Tech.[2] | 97 | 99FF |
99 | Remove Installation Frame from AB | 0.25 days | Thu 9/9/04 | Thu 9/9/04 | Riggers[3] | 98FF | 100 |
100 | East Side Complete | 0 days | Thu 9/9/04 | Thu 9/9/04 | | 99 | 107,101 |
101 | Install West Partitions | 0.5 days | Thu 9/9/04 | Thu 9/9/04 | Mech.Tech. | 100 | 112 |
102 | Connect Water Lines | 0.5 days | Mon 9/13/04 | Mon 9/13/04 | Mech.Tech. | 114 | 103 |
103 | Connect RDO Cables | 1 day | Mon 9/13/04 | Tue 9/14/04 | Electronic Tech | 102 | 104 |
104 | Remove West Rails from IFC | 0.5 days | Tue 9/14/04 | Wed 9/15/04 | Mech.Tech. | 103 | 105 |
105 | Remove Installation Frame West | 1 day | Wed 9/15/04 | Thu 9/16/04 | Carpenter[2] | 104 | 106 |
106 | West Side Complete | 0 days | Thu 9/16/04 | Thu 9/16/04 | | 105 | 107 |
107 | Cone Installation Complete | 0 days | Thu 9/16/04 | Thu 9/16/04 | | 100,106 | 144 |
108 | Install FTPC East & West in AB | 12.5 days | Wed 8/25/04 | Mon 9/13/04 | | | |
109 | Run & Test N. Platform | 5 days | Wed 8/25/04 | Wed 9/1/04 | Electronic Tech | 110SF-2 days | |
110 | Install East FTPC in Detector | 1 day | Fri 9/3/04 | Mon 9/6/04 | Mech.Tech.[2] | 94 | 115,109SF-2 days,95 |
111 | Run & Test N. Platform | 5 days | Wed 9/1/04 | Wed 9/8/04 | Electronic Tech | 114SF-2 days | |
112 | Remove West Scaffold | 0.25 days | Thu 9/9/04 | Fri 9/10/04 | Carpenter[2] | 101 | 113 |
113 | Install West Platform & Rails | 0.25 days | Fri 9/10/04 | Fri 9/10/04 | Carpenter[2] | 112 | 114 |
114 | Install West FTPC in Detector | 1 day | Fri 9/10/04 | Mon 9/13/04 | Mech.Tech.[2] | 113 | 115,111SF-2 days,102 |
115 | FTPC Installed in AB | 0 days | Mon 9/13/04 | Mon 9/13/04 | | 114,110 | |
116 | PMD Maintenance | 40 days | Thu 6/3/04 | Thu 7/29/04 | | | |
117 | Subsystem Maintenance | 30 days | Thu 6/3/04 | Thu 7/15/04 | | 35 | 118 |
118 | Detector Commisioning | 10 days | Thu 7/15/04 | Thu 7/29/04 | | 117 | 119 |
119 | PMD Maintenance Complete | 0 days | Thu 7/29/04 | Thu 7/29/04 | | 118 | |
120 | EEMC Maintenance | 90 days | Thu 6/3/04 | Thu 10/7/04 | | | |
121 | Maintenance | 50 days | Thu 6/3/04 | Thu 8/12/04 | | 35 | 122SS |
122 | MAPMT Installation | 80 days | Thu 6/3/04 | Thu 9/23/04 | Mech.Tech.[2] | 121SS | 123 |
123 | Subsystem Testing | 10 days | Thu 9/23/04 | Thu 10/7/04 | | 122 | 124 |
124 | EEMC Maintenance Complete | 0 days | Thu 10/7/04 | Thu 10/7/04 | | 123 | |
125 | TPC Maintenance | 50 days | Tue 6/15/04 | Tue 8/24/04 | | | |
126 | Repair IFC Strip Short | 5 days | Tue 6/15/04 | Tue 6/22/04 | Mech.Tech. | 49 | 127,50,131SS |
127 | Modify Resistor Chain | 5 days | Tue 6/22/04 | Tue 6/29/04 | Mech.Tech. | 126 | 128 |
128 | FEE & RDO Maintenance | 40 days | Tue 6/29/04 | Tue 8/24/04 | Electronic Tech | 127 | 129 |
129 | TPC Maintenance Complete | 0 days | Tue 8/24/04 | Tue 8/24/04 | | 128 | |
130 | TOF Maintenance | 15 days | Tue 6/15/04 | Tue 7/6/04 | | | |
131 | Tray Maintenance | 10 days | Tue 6/15/04 | Tue 6/29/04 | | 126SS | 132 |
132 | Detector Testing | 5 days | Tue 6/29/04 | Tue 7/6/04 | | 131 | 133 |
133 | TOFp Maintenance Complete | 0 days | Tue 7/6/04 | Tue 7/6/04 | | 132 | |
134 | FPD Installation | 20 days | Thu 5/27/04 | Thu 6/24/04 | | | |
135 | Install West Detectors | 10 days | Thu 5/27/04 | Thu 6/10/04 | Mech.Tech. | 11 | 136 |
136 | Install N. E. Stand for 20-cm Travel | 5 days | Thu 6/10/04 | Thu 6/17/04 | Mech.Tech.[2] | 135 | 137 |
137 | Detector Commisioning | 5 days | Thu 6/17/04 | Thu 6/24/04 | | 136 | 138 |
138 | FPD Installation Complete | 0 days | Thu 6/24/04 | Thu 6/24/04 | | 137 | 140 |
139 | BBC Maintenance | 15 days | Thu 6/24/04 | Thu 7/15/04 | | | |
140 | Subsystem Maintenance | 10 days | Thu 6/24/04 | Thu 7/8/04 | | 138 | 141 |
141 | Detector Commisioning | 5 days | Thu 7/8/04 | Thu 7/15/04 | | 140 | 142 |
142 | BBC Maintenance Complete | 0 days | Thu 7/15/04 | Thu 7/15/04 | | 141 | |
143 | Move Detector into WAH | 27 days | Thu 9/16/04 | Mon 10/25/04 | | | |
144 | Disconnect Electrical Power | 0.5 days | Thu 9/16/04 | Thu 9/16/04 | Electrician[2] | 107,74 | 147,145SS,146SS |
145 | Disconnect Platform MCWS | 0.5 days | Thu 9/16/04 | Thu 9/16/04 | Mech.Tech. | 144SS | |
146 | Disconnect TPC Utilities | 0.5 days | Thu 9/16/04 | Thu 9/16/04 | Mech.Tech. | 144SS | |
147 | Remove Buss Bridge | 0.5 days | Thu 9/16/04 | Fri 9/17/04 | Mech.Tech.[2] | 144 | 148 |
148 | Remove Platform Bridge | 0.5 days | Fri 9/17/04 | Fri 9/17/04 | Mech.Tech.[2] | 147 | 149 |
149 | Remove South Platform Stairs | 1 day | Fri 9/17/04 | Mon 9/20/04 | Mech.Tech.[2] | 148 | 150 |
150 | Disconnect Seismic Anchors | 0.5 days | Mon 9/20/04 | Tue 9/21/04 | Mech.Tech.[2] | 149 | 151SS |
151 | Lower Detector to Rails | 0.5 days | Mon 9/20/04 | Tue 9/21/04 | Mech.Tech.[2] | 150SS | 152 |
152 | Roll Detector into WAH | 1.5 days | Tue 9/21/04 | Wed 9/22/04 | Mech.Tech.[2] | 151 | 153,154 |
153 | Connect Magnet LCW | 1 day | Wed 9/22/04 | Thu 9/23/04 | Mech.Tech.[2] | 152 | |
154 | Raise/Level Detector @ IR | 0.5 days | Wed 9/22/04 | Thu 9/23/04 | Mech.Tech.[2] | 152 | 155FF,163 |
155 | Connect Seismic Anchors | 0.5 days | Wed 9/22/04 | Thu 9/23/04 | Mech.Tech.[2] | 154FF | 159,156 |
156 | Install Buss Bridge | 0.5 days | Thu 9/23/04 | Thu 9/23/04 | Mech.Tech.[2] | 155 | 157,160 |
157 | Connect Electrical Power | 1 day | Thu 9/23/04 | Fri 9/24/04 | Electrician[2] | 156 | 158 |
158 | Connect Magnet Power | 1 day | Fri 9/24/04 | Mon 9/27/04 | Elect.Tech.[2] | 157 | |
159 | Connect All Subsystem Utilities | 2 days | Thu 9/23/04 | Mon 9/27/04 | Mech.Tech.[2] | 155 | 168,166 |
160 | Connect Platform MCWS | 0.5 days | Thu 9/23/04 | Fri 9/24/04 | Mech.Tech. | 156 | 168,161 |
161 | Connect South Platform Stairs | 1 day | Fri 9/24/04 | Mon 9/27/04 | Mech.Tech.[2] | 160 | 162 |
162 | Connect Platform Bridge | 0.5 days | Mon 9/27/04 | Mon 9/27/04 | Mech.Tech.[2] | 161 | 167 |
163 | Connect Vacuum Pipe & Supports | 0.5 days | Thu 9/23/04 | Thu 9/23/04 | Mech.Tech.[2] | 154 | 164 |
164 | Vacuum Pipe Bake-out | 5 days | Thu 9/23/04 | Thu 9/30/04 | Mech.Tech.[2] | 163 | 165 |
165 | Survey Beam Pipe & Magnet | 4 days | Thu 9/30/04 | Wed 10/6/04 | Surveyors[2] | 164 | |
166 | Detector Safety Certification | 2 days | Mon 9/27/04 | Wed 9/29/04 | | 159 | |
167 | Install Shield Wall | 3 days | Mon 9/27/04 | Thu 9/30/04 | Riggers[3] | 162 | 171 |
168 | Subsystems testing in WAH | 20 days | Mon 9/27/04 | Mon 10/25/04 | | 160,159 | 169SS+5 days |
169 | Install Pole Tips | 2 days | Mon 10/4/04 | Wed 10/6/04 | Mech.Tech.[2] | 168SS+5 days | 170 |
170 | Install BBC Detectors | 1 day | Wed 10/6/04 | Thu 10/7/04 | Mech.Tech.[2] | 169 | 171 |
171 | Shutdown Activities Complete | 0 days | Thu 10/7/04 | Thu 10/7/04 | | 167,170 | |
Updated on Fri, 2007-10-19 12:29. Originally created by kocolosk on 2006-06-13 15:34.
Under: Documentation provided by Renee Fatemi
MOTIVATION:
Updated on Thu, 2007-10-18 13:59. Originally created by kocolosk on 2006-06-12 22:04.
Under: March 27, 2007
Updated on Fri, 2007-10-19 11:47. Originally created by kocolosk on 2006-06-12 21:36.
Under:
The main EMC offline reconstruction chain consists of:
|
|