- BEMC
- BTOF
- DAQ
- Detector Upgrades
- EEMC
- EPD
- 2017 cosmic ray tests at OSU and BNL
- Calibrations
- EPD Meetings
- EPD Slow-Control Manual
- EPD-GSTAR
- IV Scan
- Individual's pages
- Known issues and problems
- Mapping
- Offline DataBase
- Operations 2017
- Operations 2018
- Operations 2019
- Operations 2024
- Software
- Start-of-run EPD tasks and instructions
- Useful EPD documents
- Useful Links
- ETOF
- FCS
- FGT
- FPD & FMS & FPS
- FTPC
- FTT
- HFT
- HLT
- L3
- MTD
- MTD NPS Maps
- PMD
- PP2PP
- RICH
- Roman Pot Phase II*
- Run-18 calibrations
- SSD
- SVT
- Slow Controls
- TPC
- TRG
- Trigger Detectors
- VPD
- test
Post-installation / pre-beam commissioning 2019
Updated on Fri, 2019-02-08 01:32. Originally created by rjreed on 2019-02-08 00:31.
Under:
1. Verify proper mapping from TUFF to StEvent (tests databases, cabling...) ("Seven Patterns" test) - DONE
We followed the instructions listed at: drupal.star.bnl.gov/STAR/subsys/epd/operations-2018/pre-and-post-beam-commissioning
2. Vped adjustment - DONE
The instructions written for this year can be found at: drupal.star.bnl.gov/STAR/blog/rjreed/epd-vped-scans-2019
3. Verifying fiber mapping/pre-post
In 2018 we verified the pre-post by running special runs. It was noted this year that if we are in the right bunch crossing, we should see the epd-bbc correlation. If not, then we will not.
In progress: *.daq files have been requested from HPSS and restored to NFS. Then the bfc.C has been run, creating pico/MuDsts. These need to be analyzed.
»