Pre- and post-beam commissioning
Updated on Fri, 2019-02-15 13:26. Originally created by lisa on 2018-03-10 16:07.
Under:
Post-installation / pre-beam commissioning
Post-beam commissioning to be ready for PHYSICS
- Pre-post checking, to make sure we are in same bin as BBC. DONE
- Instructions - Rosi has agreed to elaborate a bit more (mal 15feb2019)
- check by Rosi
- Verify proper mapping from TUFF to StEvent (tests databases, cabling...) ("Seven Patterns" test) DONE
- Vped adjustment DONE
- I-V scan has been done about once/day DONE
- Confirm data goes from QT32C to TCU
- this is important for TRIGGER readiness, but not for PHYSICS readiness
- Prashanth or Rosi need to write up the purpose and instructions here.
Post-beam commissioning to be ready for PHYSICS
- (Re-)confirm pre-post timing (it's easy and it's important)
- Same instructions as item #1 above.
- Same instructions as item #1 above.
- Timing scan DONE
- Bias scan DONE
»