Work Planned (OBSOLETE)

Under:
Based on:
  • An initial meeting held during QM06 (Chair: J.Lauret, L. Barnby, O, Baranikova, A. Rose)
  • Email exchange and notes from the meeting (From: J. Lauret, Date: 11/20/2006 22:36, Subject: Summary of our embedding meeting)
  • Further EMails from L. Barnby in embedding-hn (Date: 1/18/2007 15:12, Thread ID 84)
the following task list has been defined.

ID
Task
% Complete Duration Start Finish Assigned people
1
General QA consolidation
28% 109 days? Thu 11/16/06 Tue 4/17/07  
2            
3
Documentation
25% 37 days Mon 12/18/06 Tue 2/6/07  
4
Port old QA documentation to Drupal, define hierarchy
50% 4 wks Mon 12/18/06 Fri 1/12/07 Cristina Suarez[10%]
5
Add general documentation descriptive of the embedding purpose
0% 2 days Mon 1/15/07 Tue 1/16/07 Lee Barnby[10%],Andrew Rose[10%]
6
Add documentation as per the embedding procedure, diverse embedding
0% 2 days Mon 1/15/07 Tue 1/16/07 Lee Barnby[10%],Andrew Rose[10%]
7
Import PDSF documentation into Drupal
0% 1 wk Wed 1/17/07 Tue 1/23/07 Andrew Rose[10%]
8
Review and adjust documentation
0% 1 wk Wed 1/24/07 Tue 1/30/07 Olga Barranikova[10%],Andrew Rose[5%],Lee Barnby[5%]
9
Deliver documentation to collaboration for comments
0% 1 wk Wed 1/31/07 Tue 2/6/07 STAR Collaboration[10%]
10
Drop all old documentation, adjust link (redirect)
0% 1 day Wed 1/31/07 Wed 1/31/07 Andrew Rose[15%],Jerome Lauret[15%]
11            
12
Line of authority, base conventions
84% 52 days Thu 11/16/06 Fri 1/26/07  
13
Meeting with key personnel
100% 1 day Thu 11/16/06 Thu 11/16/06 Jerome Lauret[10%],Olga Barranikova[10%],Andrew Rose[10%],Lee Barnby[10%]
14
Define responsibilities and scope of diverse individual in the embedding team
100% 1 mon Mon 12/4/06 Fri 12/29/06 Jerome Lauret[15%],Olga Barranikova[6%]
15
Define file name convention, document final proposal
50% 2 wks Mon 1/15/07 Fri 1/26/07 Jerome Lauret[6%],Lee Barnby[6%],Lidia Didenko[6%],Andrew Rose[6%]
16            
17
Collaborative work
45% 60 days Mon 1/22/07 Fri 4/13/07  
18
General Cataloguing issues
0% 9 days Mon 1/29/07 Thu 2/8/07  
19
Test Catalog registration, adjust as necessary
0% 4 days Mon 1/29/07 Thu 2/1/07 Lidia Didenko[20%],Jerome Lauret[20%]
20
Extend Spider/Indexer to include embedding registration
0% 1 wk Fri 2/2/07 Thu 2/8/07 Jerome Lauret[10%]
21
Bug tracking, mailing lists and other tools
69% 60 days Mon 1/22/07 Fri 4/13/07  
22
Re-enable embedding list, establish focus comunication at PWG level and user level
75% 3 mons Mon 1/22/07 Fri 4/13/07 Jerome Lauret[10%]
23
Establish embedding RT system queue
0% 1 day Tue 1/23/07 Tue 1/23/07 Jerome Lauret[5%]
24
Exercise embedding RT queue, adjust requirement
0% 4 days Wed 1/24/07 Mon 1/29/07 Andrew Rose[10%]
25
Establish data transfer scheme to a BNL disk pool
0% 22 days Mon 1/22/07 Tue 2/20/07  
26
Define requirements, general problems and issues
0% 1 wk Mon 1/22/07 Fri 1/26/07  
27
Add data pool mechanism at BNL, transfer with any method
0% 1 wk Mon 1/29/07 Fri 2/2/07  
28
Establish security schem, HPSS auto-synching
0% 1 wk Mon 2/5/07 Fri 2/9/07  
29
Test on one or more sites (non-PDSF)
0% 1 wk Mon 2/12/07 Fri 2/16/07  
30
Integrate to all participating sites
0% 1 wk Mon 2/12/07 Fri 2/16/07  
31
Document data transfer schemeand procedure
0% 2 days Mon 2/19/07 Tue 2/20/07  
32            
33
CVS check-in and cleanup
4% 17 days? Mon 1/22/07 Tue 2/13/07  
34
Initial setup, existing framework
0% 17 days Mon 1/22/07 Tue 2/13/07  
35
Define proper CVS location for perl, libs, macros
0% 1 day Mon 1/22/07 Mon 1/22/07 Jerome Lauret[10%],Andrew Rose[10%],Lee Barnby[10%]
36
Add existing QA macros to CVS
0% 1 day Tue 1/23/07 Tue 1/23/07 Andrew Rose[20%]
37
Checkout and test on +1 site (non-PDSF), adjust as necessary
0% 1 wk Wed 1/24/07 Tue 1/30/07 Lee Barnby[10%]
38
Bootstrap on +1 site / remove ALL site specifics references
0% 1 wk Wed 1/31/07 Tue 2/6/07 Cristina Suarez[10%]
39
Commit to CVS, verify new scripts on all sites, final adjustments
0% 1 wk Wed 2/7/07 Tue 2/13/07 Cristina Suarez[10%],Andrew Rose[10%],Lee Barnby[10%]
40
QA and nightly tests
17% 7 days? Mon 1/22/07 Tue 1/30/07  
41
Establish a QA area in CVS
100% 1 day? Mon 1/22/07 Mon 1/22/07  
42
Check existing QA suite
0% 1 wk Wed 1/24/07 Tue 1/30/07  
43            
44
Development
0% 62 days Mon 1/22/07 Tue 4/17/07  
45
General QA consolidation
0% 10 days Wed 1/31/07 Tue 2/13/07  
46
Gather feedback from PWG, add QA tests relevant to Physics topics
0% 2 wks Wed 1/31/07 Tue 2/13/07  
47
Establish nightly test framework at BNL for embedding
0% 1 wk Wed 1/31/07 Tue 2/6/07  
48
General improvements
0% 35 days Mon 1/22/07 Fri 3/9/07  
49
Requirements study for an embedding request interface
0% 2 wks Mon 1/29/07 Fri 2/9/07 Andrew Rose[10%],Jerome Lauret[10%]
50
Develop new embedding request form compatible with Drupal module
0% 4 wks Mon 2/12/07 Fri 3/9/07 Andrew Rose[10%]
51
Test new interface, import old tasks (historical purposes)
0% 5 days Mon 1/22/07 Fri 1/26/07 Andrew Rose[10%],Cristina Suarez[10%]
52
Distributed Computing
0% 20 days Wed 2/14/07 Tue 3/13/07  
53
Use SUMS framework to submit embedding, establish first XML
0% 1 wk Wed 2/14/07 Tue 2/20/07 Lee Barnby[10%]
54
Test on one site
0% 1 wk Wed 2/21/07 Tue 2/27/07 Lee Barnby[10%]
55
Test on all sites, adjust as necessary
0% 2 wks Wed 2/28/07 Tue 3/13/07 Cristina Suarez[10%],Andrew Rose[10%],Lee Barnby[10%]
56
Gridfication
0% 25 days Wed 3/14/07 Tue 4/17/07  
57
Test XML using Grid policy (one site)
0% 1 wk Wed 3/14/07 Tue 3/20/07  
58
Establish test of data transfer method, GSI enabled HPSS access possible
0% 1 wk Wed 3/21/07 Tue 3/27/07  
59
Regression and stress test on one site
0% 1 wk Wed 3/28/07 Tue 4/3/07  
60
Test on +1 site, infrastructure consolidation
0% 2 wks Wed 4/4/07 Tue 4/17/07  
61            
62
Embedding operation
25% 261 days? Mon 1/1/07 Mon 12/31/07  
63
PDSF support
50% 261 days? Mon 1/1/07 Mon 12/31/07 Andrew Rose[10%]
64
BHAM support
10% 261 days? Mon 1/1/07 Mon 12/31/07 Lee Barnby[10%]
65
UIC Support including QA
15% 261 days? Mon 1/1/07 Mon 12/31/07 Olga Barranikova[5%],Cristina Suarez[10%]