FY04

Under:
Project Start Date: Fri 1/2/04
Project Finish Date: Mon 10/25/04

STAR FY04 v3 Shutdown


ID
Name
DurationStart_DateFinish_DateResource_NamesPredecessorsSuccessors
1
STAR Detector Operations
211.35 daysMon 1/5/04Mon 10/25/04   
2
Physics Run FY04
96 daysMon 1/5/04Sat 5/15/04  5FF
3
Start Shutdown Activities
116.35 daysSat 5/15/04Mon 10/25/04   
4
Move Detector into AB
14.6 daysSat 5/15/04Thu 6/3/04   
5
Purge TPC Gas
1 daySat 5/15/04Sat 5/15/04 2FF6SS
6
Subsystem Testing
6 daysSat 5/15/04Fri 5/21/04 5SS7
7
Retract PMD Detector
0.1 daysMon 5/24/04Mon 5/24/04Mech.Tech.68
8
Remove East BBC Detector
0.25 daysMon 5/24/04Mon 5/24/04Mech.Tech.79
9
Retract East Pole Tip
0.5 daysMon 5/24/04Mon 5/24/04Mech.Tech.[2]810FF
10
Install Scaffold
0.25 daysMon 5/24/04Mon 5/24/04Carpenter[2]9FF12,11
11
Remove Shield Wall
2.5 daysMon 5/24/04Thu 5/27/04Riggers[3]1026,23,16SS,18,135
12
Remove West Pole Tip Utilities
0.25 daysMon 5/24/04Tue 5/25/04Mech.Tech.1013
13
Remove West BBC Detector
0.25 daysTue 5/25/04Tue 5/25/04Mech.Tech.1214
14
Retract West Pole Tip
0.5 daysTue 5/25/04Tue 5/25/04Mech.Tech.[2]1315FF
15
Install Scaffold
0.13 daysTue 5/25/04Tue 5/25/04Carpenter[2]14FF 
16
Disconnect Electrical Power
0.5 daysMon 5/24/04Tue 5/25/04Electrician[2]11SS18,17
17
Disconnect Magnet Power
0.5 daysTue 5/25/04Tue 5/25/04Elect.Tech.[2]1618
18
Remove Buss Bridge
0.25 daysThu 5/27/04Thu 5/27/04Mech.Tech.[2]16,17,1119,21
19
Disconnect Platform MCWS
0.5 daysThu 5/27/04Fri 5/28/04Mech.Tech.1820
20
Disconnect Subsystems Utilities
1 dayFri 5/28/04Mon 5/31/04Mech.Tech.1926
21
Remove Platform Bridge
0.25 daysThu 5/27/04Thu 5/27/04Mech.Tech.[2]1826,22
22
Remove South Platform Stairs
0.25 daysThu 5/27/04Fri 5/28/04Mech.Tech.[2]2126,24
23
Disconnect RHIC Vacuum Pipe
0.5 daysThu 5/27/04Thu 5/27/04Mech.Tech.11 
24
Remove Seismic Anchors
0.25 daysFri 5/28/04Fri 5/28/04Mech.Tech.[2]2225
25
Disconnect Magnet LCW
0.25 daysFri 5/28/04Fri 5/28/04Mech.Tech.[2]2426
26
Roll Detector into AB
1 dayMon 5/31/04Tue 6/1/04Mech.Tech.[2]11,21,22,25,2027
27
Blow-out Magnet Coils
0.5 daysTue 6/1/04Tue 6/1/04Mech.Tech.[2]2628
28
Connect South Platform Stairs
0.5 daysTue 6/1/04Wed 6/2/04Mech.Tech.[2]2729
29
Connect Platform Bridge
0.5 daysWed 6/2/04Wed 6/2/04Mech.Tech.[2]2831,30
30
Connect Seismic Anchors
0.5 daysWed 6/2/04Thu 6/3/04Mech.Tech.29 
31
Install Buss Bridge
0.5 daysWed 6/2/04Thu 6/3/04Mech.Tech.[2]2932
32
Connect Electrical Power
0.5 daysThu 6/3/04Thu 6/3/04Electrician[2]3133SS
33
Connect Subsystems Utilities
0.5 daysThu 6/3/04Thu 6/3/04Mech.Tech.32SS34SS
34
Connect Platform MCWS
0.5 daysThu 6/3/04Thu 6/3/04Mech.Tech.33SS35
35
Detector In AB
0 daysThu 6/3/04Thu 6/3/04 3437,117,121
36
Remove East & West FTPC
13.75 daysThu 6/3/04Wed 6/23/04   
37
Remove E/W IFC Air Manifolds
0.25 daysThu 6/3/04Thu 6/3/04Mech.Tech.3538
38
Remove East & West Scaffold
0.5 daysThu 6/3/04Fri 6/4/04Carpenter[2]3739
39
Install West Platform & Rails
1 dayFri 6/4/04Mon 6/7/04Carpenter[2]3840,41
40
Remove West FTPC
0.5 daysMon 6/7/04Mon 6/7/04Mech.Tech.3945
41
Rig Installation Frame into AB
0.5 daysMon 6/7/04Mon 6/7/04Riggers[3]3942SS
42
Install East Installation Frame
0.5 daysMon 6/7/04Mon 6/7/04Mech.Tech.[2]41SS43
43
Install East Rails
1 dayMon 6/7/04Tue 6/8/04Mech.Tech.[2]4244
44
Remove East FTPC
0.5 daysTue 6/8/04Wed 6/9/04Mech.Tech.[2]4345
45
East & West FTPC's Removed
0 daysWed 6/9/04Wed 6/9/04 40,4446,48
46
Maintenance on FTPC's
10 daysWed 6/9/04Wed 6/23/04Electronic Tech45 
47
Remove Cone
11.5 daysWed 6/9/04Thu 6/24/04   
48
Disconnect Utilities
4 daysWed 6/9/04Tue 6/15/04Mech.Tech.4549
49
Remove Cone from IFC
0.5 daysTue 6/15/04Tue 6/15/04Mech.Tech.4876,126
50
Remove East Installation Frame
1 dayTue 6/22/04Wed 6/23/04Mech.Tech.[2]76,12651FF
51
Remove Installation Frame from AB
0.5 daysWed 6/23/04Wed 6/23/04Riggers[3]50FF52
52
Remove Installation Frame West
1 dayWed 6/23/04Thu 6/24/04Carpenter[2]5153
53
Cone Removed
0 daysThu 6/24/04Thu 6/24/04 5257
54
Install East BEMC Modules
47.5 daysMon 6/14/04Wed 8/18/04   
55
(30) Modules Delivered
4 daysMon 6/14/04Fri 6/18/04Riggers[3]57FF-5 days56FF
56
(30) Modules Staged in AB
4 daysMon 6/14/04Fri 6/18/04Mech.Tech.[2]55FF 
57
Install East & West Scaffold
0.5 daysThu 6/24/04Fri 6/25/04Carpenter[2]5358,55FF-5 days
58
Remove East Side Cables & Tray
3 daysFri 6/25/04Wed 6/30/04Mech.Tech.[2]5759
59
Erect Installation Fixture S.E. Upper
0.5 daysWed 6/30/04Wed 6/30/04Mech.Tech.[2]5860
60
Remove S.E. TPC Support Arm
0.25 daysWed 6/30/04Thu 7/1/04Mech.Tech.[2]5961
61
Install Modules 106-103
4 daysThu 7/1/04Wed 7/7/04Mech.Tech.[2]6062
62
Erect Installation Fixture S.E. Lower
0.5 daysWed 7/7/04Wed 7/7/04Mech.Tech.[2]6163
63
Install Modules 102-89
14 daysWed 7/7/04Tue 7/27/04Mech.Tech.[2]6264
64
Install S.E. TPC Support Arm
0.5 daysTue 7/27/04Wed 7/28/04Mech.Tech.[2]6365
65
Erect Installation Fixture N.E. Lower
0.5 daysWed 7/28/04Wed 7/28/04Mech.Tech.[2]6466
66
Install Modules 77-88
12 daysWed 7/28/04Fri 8/13/04Mech.Tech.[2]6567
67
Remove Installation Fixture
0.25 daysFri 8/13/04Fri 8/13/04Mech.Tech.[2]6668
68
Install East Side Cables & Tray
3 daysFri 8/13/04Wed 8/18/04Mech.Tech.[2]6769
69
East BEMC Installation Complete
0 daysWed 8/18/04Wed 8/18/04 6882,72
70
Install BEMC PMT Boxes
35 daysWed 7/14/04Wed 9/1/04   
71
Install 208 VAC Power
15 daysWed 7/14/04Wed 8/4/04Electrician[2]72SF-10 days 
72
Install PMT Boxes
10 daysWed 8/18/04Wed 9/1/04Mech.Tech.[2]6973FF,71SF-10 days
73
Install Electronics
20 daysWed 8/4/04Wed 9/1/04Electronic Tech72FF74
74
PMT Box Installation Complete
0 daysWed 9/1/04Wed 9/1/04 73144
75
Install SSD
20.5 daysTue 6/15/04Wed 7/14/04   
76
Rig Cone to Cleanroom Roof
0.5 daysTue 6/15/04Wed 6/16/04Mech.Tech.4977,50
77
Install SSD on Cone
20 daysWed 6/16/04Wed 7/14/04Mech.Tech.7678SS,80
78
Install LV Crate & Cables
5 daysWed 6/16/04Wed 6/23/04Electronic Tech77SS79
79
Install RDO Boxes
5 daysWed 6/23/04Wed 6/30/04Electronic Tech78 
80
SSD Installed on Cone
0 daysWed 7/14/04Wed 7/14/04 7785
81
Install Cone
20.5 daysWed 8/18/04Thu 9/16/04   
82
Rig Installation Frame into AB
0.5 daysWed 8/18/04Thu 8/19/04Riggers[3]6983SS
83
Install East Installation Frame
0.5 daysWed 8/18/04Thu 8/19/04Mech.Tech.[2]82SS84
84
Install Tables & Rails
0.5 daysThu 8/19/04Thu 8/19/04Mech.Tech.8385
85
Rig Cone to Rails
0.5 daysThu 8/19/04Fri 8/20/04Mech.Tech.[2]84,8086
86
Survey SSD to SVT
2 daysFri 8/20/04Tue 8/24/04Surveyors[2]8587
87
Complete SSD Installation
2 daysTue 8/24/04Thu 8/26/04Mech.Tech.8688
88
Test Utility Connections
1 dayThu 8/26/04Fri 8/27/04Electronic Tech8789FF
89
Clean TPC IFC
1 dayThu 8/26/04Fri 8/27/04Mech.Tech.88FF90
90
Install Cone in Detector
0.5 daysFri 8/27/04Fri 8/27/04Mech.Tech.8991
91
Test IFC High Voltage
0.5 daysFri 8/27/04Mon 8/30/04Electronic Tech9092
92
Survey TPC to Magnet
2 daysMon 8/30/04Wed 9/1/04Surveyors[2]9193
93
Survey SVT to TPC
2 daysWed 9/1/04Fri 9/3/04Surveyors[2]9294
94
Install East Partitions
0.5 daysFri 9/3/04Fri 9/3/04Mech.Tech.93110
95
Connect Water Lines
0.5 daysMon 9/6/04Tue 9/7/04Mech.Tech.11096
96
Connect RDO Cables
1 dayTue 9/7/04Wed 9/8/04Electronic Tech9597
97
Remove East Rails from IFC
0.5 daysWed 9/8/04Wed 9/8/04Mech.Tech.[2]9698
98
Remove East Installation Frame
0.5 daysWed 9/8/04Thu 9/9/04Mech.Tech.[2]9799FF
99
Remove Installation Frame from AB
0.25 daysThu 9/9/04Thu 9/9/04Riggers[3]98FF100
100
East Side Complete
0 daysThu 9/9/04Thu 9/9/04 99107,101
101
Install West Partitions
0.5 daysThu 9/9/04Thu 9/9/04Mech.Tech.100112
102
Connect Water Lines
0.5 daysMon 9/13/04Mon 9/13/04Mech.Tech.114103
103
Connect RDO Cables
1 dayMon 9/13/04Tue 9/14/04Electronic Tech102104
104
Remove West Rails from IFC
0.5 daysTue 9/14/04Wed 9/15/04Mech.Tech.103105
105
Remove Installation Frame West
1 dayWed 9/15/04Thu 9/16/04Carpenter[2]104106
106
West Side Complete
0 daysThu 9/16/04Thu 9/16/04 105107
107
Cone Installation Complete
0 daysThu 9/16/04Thu 9/16/04 100,106144
108
Install FTPC East & West in AB
12.5 daysWed 8/25/04Mon 9/13/04   
109
Run & Test N. Platform
5 daysWed 8/25/04Wed 9/1/04Electronic Tech110SF-2 days 
110
Install East FTPC in Detector
1 dayFri 9/3/04Mon 9/6/04Mech.Tech.[2]94115,109SF-2 days,95
111
Run & Test N. Platform
5 daysWed 9/1/04Wed 9/8/04Electronic Tech114SF-2 days 
112
Remove West Scaffold
0.25 daysThu 9/9/04Fri 9/10/04Carpenter[2]101113
113
Install West Platform & Rails
0.25 daysFri 9/10/04Fri 9/10/04Carpenter[2]112114
114
Install West FTPC in Detector
1 dayFri 9/10/04Mon 9/13/04Mech.Tech.[2]113115,111SF-2 days,102
115
FTPC Installed in AB
0 daysMon 9/13/04Mon 9/13/04 114,110 
116
PMD Maintenance
40 daysThu 6/3/04Thu 7/29/04   
117
Subsystem Maintenance
30 daysThu 6/3/04Thu 7/15/04 35118
118
Detector Commisioning
10 daysThu 7/15/04Thu 7/29/04 117119
119
PMD Maintenance Complete
0 daysThu 7/29/04Thu 7/29/04 118 
120
EEMC Maintenance
90 daysThu 6/3/04Thu 10/7/04   
121
Maintenance
50 daysThu 6/3/04Thu 8/12/04 35122SS
122
MAPMT Installation
80 daysThu 6/3/04Thu 9/23/04Mech.Tech.[2]121SS123
123
Subsystem Testing
10 daysThu 9/23/04Thu 10/7/04 122124
124
EEMC Maintenance Complete
0 daysThu 10/7/04Thu 10/7/04 123 
125
TPC Maintenance
50 daysTue 6/15/04Tue 8/24/04   
126
Repair IFC Strip Short
5 daysTue 6/15/04Tue 6/22/04Mech.Tech.49127,50,131SS
127
Modify Resistor Chain
5 daysTue 6/22/04Tue 6/29/04Mech.Tech.126128
128
FEE & RDO Maintenance
40 daysTue 6/29/04Tue 8/24/04Electronic Tech127129
129
TPC Maintenance Complete
0 daysTue 8/24/04Tue 8/24/04 128 
130
TOF Maintenance
15 daysTue 6/15/04Tue 7/6/04   
131
Tray Maintenance
10 daysTue 6/15/04Tue 6/29/04 126SS132
132
Detector Testing
5 daysTue 6/29/04Tue 7/6/04 131133
133
TOFp Maintenance Complete
0 daysTue 7/6/04Tue 7/6/04 132 
134
FPD Installation
20 daysThu 5/27/04Thu 6/24/04   
135
Install West Detectors
10 daysThu 5/27/04Thu 6/10/04Mech.Tech.11136
136
Install N. E. Stand for 20-cm Travel
5 daysThu 6/10/04Thu 6/17/04Mech.Tech.[2]135137
137
Detector Commisioning
5 daysThu 6/17/04Thu 6/24/04 136138
138
FPD Installation Complete
0 daysThu 6/24/04Thu 6/24/04 137140
139
BBC Maintenance
15 daysThu 6/24/04Thu 7/15/04   
140
Subsystem Maintenance
10 daysThu 6/24/04Thu 7/8/04 138141
141
Detector Commisioning
5 daysThu 7/8/04Thu 7/15/04 140142
142
BBC Maintenance Complete
0 daysThu 7/15/04Thu 7/15/04 141 
143
Move Detector into WAH
27 daysThu 9/16/04Mon 10/25/04   
144
Disconnect Electrical Power
0.5 daysThu 9/16/04Thu 9/16/04Electrician[2]107,74147,145SS,146SS
145
Disconnect Platform MCWS
0.5 daysThu 9/16/04Thu 9/16/04Mech.Tech.144SS 
146
Disconnect TPC Utilities
0.5 daysThu 9/16/04Thu 9/16/04Mech.Tech.144SS 
147
Remove Buss Bridge
0.5 daysThu 9/16/04Fri 9/17/04Mech.Tech.[2]144148
148
Remove Platform Bridge
0.5 daysFri 9/17/04Fri 9/17/04Mech.Tech.[2]147149
149
Remove South Platform Stairs
1 dayFri 9/17/04Mon 9/20/04Mech.Tech.[2]148150
150
Disconnect Seismic Anchors
0.5 daysMon 9/20/04Tue 9/21/04Mech.Tech.[2]149151SS
151
Lower Detector to Rails
0.5 daysMon 9/20/04Tue 9/21/04Mech.Tech.[2]150SS152
152
Roll Detector into WAH
1.5 daysTue 9/21/04Wed 9/22/04Mech.Tech.[2]151153,154
153
Connect Magnet LCW
1 dayWed 9/22/04Thu 9/23/04Mech.Tech.[2]152 
154
Raise/Level Detector @ IR
0.5 daysWed 9/22/04Thu 9/23/04Mech.Tech.[2]152155FF,163
155
Connect Seismic Anchors
0.5 daysWed 9/22/04Thu 9/23/04Mech.Tech.[2]154FF159,156
156
Install Buss Bridge
0.5 daysThu 9/23/04Thu 9/23/04Mech.Tech.[2]155157,160
157
Connect Electrical Power
1 dayThu 9/23/04Fri 9/24/04Electrician[2]156158
158
Connect Magnet Power
1 dayFri 9/24/04Mon 9/27/04Elect.Tech.[2]157 
159
Connect All Subsystem Utilities
2 daysThu 9/23/04Mon 9/27/04Mech.Tech.[2]155168,166
160
Connect Platform MCWS
0.5 daysThu 9/23/04Fri 9/24/04Mech.Tech.156168,161
161
Connect South Platform Stairs
1 dayFri 9/24/04Mon 9/27/04Mech.Tech.[2]160162
162
Connect Platform Bridge
0.5 daysMon 9/27/04Mon 9/27/04Mech.Tech.[2]161167
163
Connect Vacuum Pipe & Supports
0.5 daysThu 9/23/04Thu 9/23/04Mech.Tech.[2]154164
164
Vacuum Pipe Bake-out
5 daysThu 9/23/04Thu 9/30/04Mech.Tech.[2]163165
165
Survey Beam Pipe & Magnet
4 daysThu 9/30/04Wed 10/6/04Surveyors[2]164 
166
Detector Safety Certification
2 daysMon 9/27/04Wed 9/29/04 159 
167
Install Shield Wall
3 daysMon 9/27/04Thu 9/30/04Riggers[3]162171
168
Subsystems testing in WAH
20 daysMon 9/27/04Mon 10/25/04 160,159169SS+5 days
169
Install Pole Tips
2 daysMon 10/4/04Wed 10/6/04Mech.Tech.[2]168SS+5 days170
170
Install BBC Detectors
1 dayWed 10/6/04Thu 10/7/04Mech.Tech.[2]169171
171
Shutdown Activities Complete
0 daysThu 10/7/04Thu 10/7/04 167,170