FY06

Under:

STAR FY06 Shutdown Schedule


Project Start Date: 6/26/06
Project Finish Date: 10/27/06

 

STAR FY06 v5 Shutdown

IDWBS
Name
DurationStart_DateFinish_DateResource_NamesPredecessorsSuccessors
11
STAR Detector FY06 Shutdown
87 days6/26/0610/27/06   
21.1
Disconnect Detector Utilities
10.75 days6/26/067/12/06   
31.1.1
Begin Shutdown Activities
0 days6/26/066/26/06  4SS,114SS
41.1.2
Purge TPC Gas
1 day6/26/066/26/06 3SS 
51.1.3
Remove West BBC Detector
0.25 days7/5/067/5/06Mech.Tech.1146,103
61.1.4
Disconnect West Pole Tip Utilities
0.5 days7/5/067/5/06Mech.Tech.[2]57
71.1.5
Retract West Pole Tip
0.5 days7/5/067/6/06Mech.Tech.[2]68FF
81.1.6
Install Scaffold
0.25 days7/6/067/6/06Carpenter[2]7FF9
91.1.7
Remove East BBC Detector
0.25 days7/6/067/6/06Mech.Tech.810,103
101.1.8
Disconnect East Pole Tip Utilities
0.25 days7/6/067/6/06Elect.Tech.[2]911
111.1.9
Retract East Pole Tip
0.5 days7/6/067/7/06Mech.Tech.[2]1012FF,15,13
121.1.10
Install Scaffold
0.25 days7/7/067/7/06Carpenter[2]11FF19
131.1.11
Disconnect Electrical Power
0.5 days7/7/067/7/06Electrician[2]1115,14,17
141.1.12
Disconnect Magnet Power
0.5 days7/7/067/10/06Elect.Tech.[2]1315
151.1.13
Remove Buss Bridge
0.25 days7/10/067/10/06Mech.Tech.[2]13,14,1116
161.1.14
Disconnect Platform MCWS
0.5 days7/10/067/10/06Mech.Tech.[2]1518
171.1.15
Disconnect Subsystems Utilities
2 days7/7/067/11/06Mech.Tech.13 
181.1.16
Remove South Platform Stairs
0.25 days7/11/067/11/06Mech.Tech.[2]1621
191.1.17
Remove pVPD Detectors
0.25 days7/7/067/7/06Mech.Tech.[2]1220
201.1.18
Disconnect RHIC Vacuum Pipe
3 days7/7/067/12/06Mech.Tech.[2]1924
211.1.19
Remove Seismic Anchors
0.25 days7/11/067/11/06Mech.Tech.[2]1822
221.1.20
Disconnect Magnet Water
0.25 days7/11/067/11/06Mech.Tech.[2]2123
231.1.21
Blow-out Magnet Coils
1 day7/11/067/12/06Mech.Tech.[2]2224
241.1.22
Detector Utilities Disconnected
0 days7/12/067/12/06 23,2026,57
251.2
Hydraulic System Testing
6.5 days7/12/067/21/06   
261.2.1
Run & Test Hydraulics
5 days7/12/067/19/06Mech.Tech.2427FF
271.2.2
Position Detector on Beamline
0.5 days7/19/067/19/06Mech.Tech.26FF28SS
281.2.3
Survey Detector on Beamline
2 days7/19/067/21/06Surveyors[2]27SS29
291.2.4
Hydraulics Tests Complete
0 days7/21/067/21/06 2831,67,132,85
301.3
Remove Hilman Rollers
5 days7/31/068/4/06   
311.3.1
Remove Roller Assemblies
5 days7/31/068/4/06Mech.Tech.[2]29,12332FF
321.3.2
Remove Roller Assemblies
2 days8/3/068/4/06Riggers[3]31FF33FF
331.3.3
Crate & Ship Roller Assemblies
1 day8/4/068/4/06Riggers[2],Carpenter[2]32FF34FF
341.3.4
Roller Assembly Removal Complete
0 days8/4/068/4/06 33FF 
351.4
Remove West FPD++ Detector
23.5 days7/5/068/7/06   
361.4.1
Disconnect Cabling
5 days7/5/067/11/06Mech.Tech.11437SS
371.4.2
Remove Existing Cells
13 days7/5/067/21/06Mech.Tech.36SS38
381.4.3
Remove Cabling
5 days7/31/068/4/06Mech.Tech.37,12339
391.4.4
Remove Enclosures & Shield Block
0.5 days8/7/068/7/06Riggers[3]38125,40
401.4.5
FPD++ Removal Complete
0 days8/7/068/7/06 3995
411.5
East FTPC Maintenance
15 days8/7/068/25/06   
421.5.1
Remove East IFC Air Manifolds
0.5 days8/7/068/7/06Mech.Tech.67,12343
431.5.2
Remove East Scaffold
0.5 days8/7/068/7/06Carpenter[2]4244
441.5.3
Rig East FTPC Platform
0.5 days8/8/068/8/06Riggers[3]4345SS
451.5.4
Install East FTPC Platform
0.5 days8/8/068/8/06Carpenter[2]44SS46
461.5.5
Install East FTPC Rails
0.5 days8/8/068/8/06Mech.Tech.[2]4547
471.5.6
Remove East FTPC
1 day8/9/068/9/06Mech.Tech.[2]4648,74
481.5.7
Replace East FTPC FEE
5 days8/10/068/16/06Electronic Tech4749
491.5.8
Install FTPC on Rails & Test
5 days8/17/068/23/06 4850FF
501.5.9
Install East FTPC
0.5 days8/24/068/24/06Mech.Tech.[2]49FF,7551
511.5.10
Remove East FTPC Rails
0.5 days8/24/068/24/06Mech.Tech.[2]5052
521.5.11
Rig East FTPC Platform
0.5 days8/25/068/25/06Riggers[3]5153SS
531.5.12
Remove East FTPC Platform
0.5 days8/25/068/25/06Carpenter[2]52SS54
541.5.13
Install East Scaffold
0.5 days8/25/068/25/06Carpenter[2]5355
551.5.14
FTPC Maintenance Complete
0 days8/25/068/25/06 5486,70
561.6
SSD Maintenance
27.25 days7/12/068/18/06   
571.6.1
Compressor Maintenance
5 days7/12/067/19/06 24 
581.6.2
RDO maintenance
5 days7/31/068/4/06Carpenter[2]67SS59
591.6.3
Crate Maintenance
10 days8/7/068/18/06Riggers[3]58,12360
601.6.4
SSD Maintenance Complete
0 days8/18/068/18/06 59 
611.7
BEMC Maintenance
40 days7/31/069/25/06   
621.7.1
Remove & Repair Crates
20 days7/31/068/25/06Electronic Tech12363
631.7.2
Install PMT Box Remote Power
20 days8/28/069/25/06Electronic Tech[2]6264FF
641.7.3
PMT Box Maintenance
20 days8/28/069/25/06Elect.Tech.63FF65
651.7.4
BEMC Maintenance Complete
0 days9/25/069/25/06 64145
661.8
SVT RDO Box Relocation
39 days7/31/069/22/06   
671.8.1
Remove RDO Boxes
5 days7/31/068/4/06Electronic Tech29,12368,42,58SS
681.8.2
Repair RDO Boxes
20 days8/7/069/1/06Electronic Tech6769
691.8.3
Install West RDO Boxes
2 days9/12/069/13/06Electronic Tech68,8772,81,70
701.8.4
Install Remote East RDO Boxes
5 days9/14/069/20/06Mech.Tech.69,5571
711.8.5
Rout East RDO Cables
2 days9/21/069/22/06Electronic Tech[2]7072
721.8.6
SVT RDO Box Relocation Complete
0 days9/22/069/22/06 71,69139,145
731.9
HFT Prototype Installation
10 days8/10/068/23/06   
741.9.1
Install East HFT Prototype
10 days8/10/068/23/06Mech.Tech.[2]4775
751.9.2
HFT Prototype Installed
0 days8/23/068/23/06 7450
761.10
PMD Maintenance
40 days7/31/069/25/06   
771.10.1
Replace Supermodules
30 days7/31/069/11/06 12378
781.10.2
Detector Maintenance
10 days9/12/069/25/06 7779
791.10.3
PMD Maintenance Complete
0 days9/25/069/25/06 78145
801.11
EEMC Maintenance
15 days9/14/0610/4/06   
811.11.1
PMT/MAPMT Box Maintenance
12 days9/14/069/29/06Mech.Tech.[2]69,11282SS
821.11.2
Subsystem Testing
15 days9/14/0610/4/06 81SS83
831.11.3
EEMC Maintenance Complete
0 days10/4/0610/4/06 82145,115
841.12
TPC Maintenance
35.75 days7/21/069/11/06   
851.12.1
Remove East/West Bad FEE/RDO
5 days7/21/067/28/06Electronic Tech[2]2988
861.12.2
Install East FEE/RDO
5 days8/28/069/1/06Electronic Tech[2]5589,87
871.12.3
Install West FEE/RDO
5 days9/5/069/11/06Electronic Tech[2]8689,69
881.12.4
Maintenance on Gas Room UPS
1 day7/28/067/31/06 8589
891.12.5
TPC Maintenance Complete
0 days9/11/069/11/06 88,87,86139,145,107
901.13
TOF Maintenance
5 days10/5/0610/11/06   
911.13.1
Remove Old Tray
2 days10/5/0610/6/06Mech.Tech. 92
921.13.2
Install New Trays
3 days10/9/0610/11/06Mech.Tech.9193
931.13.3
TOF Installation Complete
0 days10/11/0610/11/06 92115
941.14
FMS Installation
43 days8/7/0610/6/06   
951.14.1
Install FMS Carriages
5 days8/7/068/14/06Mech.Tech.[2]4096
961.14.2
Install FMS Cells
30 days8/14/069/26/06Mech.Tech.[2]9598FF,97SS
971.14.3
Install AC Power
5 days8/14/068/21/06Electrician[2]96SS100
981.14.4
Install FMS Enclosures
5 days9/19/069/26/06Mech.Tech.[2]96FF99
991.14.5
Install FMS Cabling
8 days9/26/0610/6/06Mech.Tech.[2]98101
1001.14.6
Install Electronics Racks
10 days8/21/069/5/06Electronic Tech[2]97101
1011.14.7
FMS Installation Complete
0 days10/6/0610/6/06 99,100145
1021.15
BBC Maintenance
25 days7/6/068/10/06   
1031.15.1
Subsystem Maintenance
20 days7/6/068/3/06 5,9104
1041.15.2
Detector Commisioning
5 days8/3/068/10/06 103105
1051.15.3
BBC Maintenance Complete
0 days8/10/068/10/06 104 
1061.16
Trigger Maintenance
10 days9/12/069/25/06   
1071.16.1
Trigger Maintenance
10 days9/12/069/25/06 89108
1081.16.2
Trigger Maintenance Complete
0 days9/25/069/25/06 107145
1091.17
Pole Tip Hose Replacement
5 days7/31/068/4/06   
1101.17.1
Remove Old Hose
2 days7/31/068/1/06Mech.Tech.[2]123111
1111.17.2
Install New Braided Hose
3 days8/2/068/4/06Mech.Tech.[2]110112
1121.17.3
Hose Replacement Complete
0 days8/4/068/4/06 11181
1131.18
Magnet Power Supply Maintenance & Test
87 days6/26/0610/27/06   
1141.18.1
Power Supply Maintenance & Test
5 days6/26/066/30/06Electronic Tech[2]3SS5,36
1151.18.2
Remove East/West Scaffold
0.5 days10/12/0610/12/06Carpenter[2]83,93116SS
1161.18.3
Install East Pole Tip
1 day10/12/0610/12/06Mech.Tech.[2]115SS117
1171.18.4
Install West Pole Tip
1 day10/13/0610/13/06Mech.Tech.[2]116118,143FF
1181.18.5
Power Supply Maintenance & Test
10 days10/16/0610/27/06Electronic Tech[2]117119
1191.18.6
Power Supply Maintenance Complete
0 days10/27/0610/27/06 118146
1201.19
C-AD Maintenance
49 days7/24/069/29/06   
1211.19.1
SGIS Modifications
10 days9/18/069/29/06Elect.Tech.[2] 130,144
1221.19.2
PS Sound Barrier Wall
10 days7/31/068/11/06 123 
1231.19.3
AC Substation Maintenance
5 days7/24/067/28/06  62,110,124,128,77,42,59,31,67,38,132,122
1241.19.4
Control Room Modification
10 days7/31/068/11/06 123126
1251.19.5
Install West Tunnel Shielding
5 days8/7/068/14/06Riggers[3]39 
1261.19.6
DAQ Room A/C Upgrade
10 days8/14/068/25/06 124127
1271.19.7
Fire Sprinkler Preaction Upgrade
10 days8/28/069/11/06 126130
1281.19.8
MCW Flow Balance
10 days7/31/068/11/06Mech.Tech.[2]123129
1291.19.9
Seal Tower Basin
5 days8/14/068/18/06Mech.Tech.[2]128 
1301.19.10
C-A Maintenance Complete
0 days9/29/069/29/06 127,121 
1311.20
Connect Detector Utilities
64 days7/31/0610/27/06   
1321.20.1
Connect Magnet LCW
1 day7/31/067/31/06Mech.Tech.[2]29,123133
1331.20.2
Install Buss Bridge
0.5 days8/1/068/1/06Mech.Tech.[2]132134,137
1341.20.3
Connect Electrical Power
1 day8/1/068/2/06Electrician[2]133135,136
1351.20.4
Connect Magnet Power
1 day8/2/068/3/06Elect.Tech.[2]134 
1361.20.5
Connect All Subsystem Utilities
1 day8/2/068/3/06Mech.Tech.[2]134 
1371.20.6
Connect Platform MCWS
0.5 days8/1/068/1/06Mech.Tech.133138
1381.20.7
Connect South Platform Stairs
1 day8/2/068/2/06Mech.Tech.[2]137 
1391.20.8
Connect Vacuum Pipe & Supports
3 days9/25/069/27/06Mech.Tech.[2]72,89140SS
1401.20.9
Vacuum Pipe Bake-out
10 days9/25/0610/6/06Mech.Tech.[2]139SS141
1411.20.10
Install START Detectors
0.5 days10/9/0610/9/06Mech.Tech.140142
1421.20.11
Survey Beam Pipe
2 days10/9/0610/11/06Surveyors[2]141143
1431.20.12
Install BBC Detectors
1 day10/13/0610/13/06Mech.Tech.[2]142,117FF 
1441.20.13
Detector Safety Certification
5 days10/2/0610/6/06 121145
1451.20.14
Subsystems testing in WAH
5 days10/9/0610/13/06 144,65,108,101,72,79,83,89146
1461.20.15
Shutdown Activities Complete
0 days10/27/0610/27/06 145,119