Inner Silicon Tracking

ID
Task Name
DurationStartFinishResource Names 
1      
2
TPC checks
7 daysFri 2/9/07Mon 2/19/07  
3
Laser drift+T0
7 daysFri 2/9/07Mon 2/19/07Yuri[50%] 
4
SSD shift + East/West TPC tracks
3 daysFri 2/9/07Tue 2/13/07Spiros[25%] 
5
SVT aligment
7 days?Tue 2/20/07Wed 2/28/07  
6
SVT+SSD (cone) for each wafer
1 wkTue 2/20/07Mon 2/26/07Ivan,Richard 
7
Shell/Sector for each magnetic field settings
1 day?Tue 2/27/07Tue 2/27/07  
8
Ladder by Ladder
1 day?Wed 2/28/07Wed 2/28/07  
9
Using TPC+SSD, Determining the SVT Drift velocity
7 daysFri 2/9/07Mon 2/19/07Ivan 
10
Drift velocity
12 daysFri 2/9/07Mon 2/26/07  
11
High stat sample processing preview
7 daysFri 2/9/07Mon 2/19/07Vladimir 
12
Final evaluation
5 daysTue 2/20/07Mon 2/26/07Vladimir 
13      
14
Online QA (offline QA)
7 daysFri 2/9/07Mon 2/19/07Ivan,Helen 
15      
16
Hit error calculation final pass
1 wkFri 2/9/07Thu 2/15/07Victor 
17
Self-Alignement
3 wksFri 2/16/07Thu 3/8/07Victor 
18
Code in place for library - aligement related
1 wkFri 2/9/07Thu 2/15/07Yuri[10%],Victor[10%] 
19      
20
Tasks without immediate dependencies
60 daysFri 2/9/07Thu 5/3/07  
21
Cluster (SVT+SSD) and efficiency studies
1.5 monsFri 2/9/07Thu 3/22/07Artemios,Jonathan 
22
Slow/Fast simulators reshape
3 monsFri 2/9/07Thu 5/3/07Jonathan,Polish students x2,Stephen 
23      
24      
25
Cu+Cu re-production
87.5 daysFri 3/9/07Tue 7/10/07  
26
Cu+Cu 62 GeV production
3 wksFri 3/9/07Thu 3/29/07  
27
Cu+Cu 200 GeV production
72.5 daysFri 3/30/07Tue 7/10/07  
28
cuProdcutionMinBias (30 M)
8.5 wksFri 3/30/07Tue 5/29/07  
29
cuProductionHighTower (17 M)
6 wksTue 5/29/07Tue 7/10/07