iTP insertion tooling review

2015-03-05 13:30
America/New York
Thursday, 5 March 2015
2-84 BNL, at 18:30 (GMT), duration : 00:00
 This is the second insertion tooling review for conceptual design.

The notes from the meeting are attached here


TimeTalkPresenter
13:30insertion tool and integration ( 00:20 ) 1 fileRahul Sharma

Estimation of 2S+3S RAA values and limits

Question whether we should go for 2S+3S RAA and/or limits.  The 1st estimation (approx 20% accuracy) is in UpsExcStates14.

HFT hit selection

The last puzzle in Sti was HFT hits selections. We requested at least 4 HFT hits on track
but sometimes tracks was accepted with even 1 Hft hit. I spend a lot of time to understand,

Iteration4

The result of analysis of iteration4 is below.The corrections from iteration4 to be used to set iteration5 voltages are Fms

Run14 Au+Au 200 GeV - T0 calibration using HFT


Regarding the T0 calibration. 

Re-Study the internal busy effect

newest one is in here :

Re-Study the internal busy effect

Speaker : Long Zhou


Talk time : 16:30, Duration : 00:20

CIPANP_Abstract

Run 15 goals in center production

Speaker : Igor Alekseev


Talk time : 12:50, Duration : 00:10

IST


Talk time : 11:20, Duration : 00:20

 

Summary from last week:

Speaker : Yaping


Talk time : 11:00, Duration : 00:20

1). code review was done for IST fast simulation maker, and moved to DEV library on Feb. 26.

VPDMB Rate

Speaker : Xin Dong


Talk time : 12:30, Duration : 00:20

 

iteration3

 This page represents the analysis of date taken after iteration3 voltages were set.

Trigger Board Meeting for Run15

2015-03-02 12:30
2015-03-02 14:00
America/New York
Monday, 2 March 2015
BNL Physics 1-224 and SeeVogh (ID 100 9853), at 17:30 (GMT), duration : 01:30
 
TimeTalkPresenter
12:30VPDMB Rate ( 00:20 ) 1 fileXin Dong
12:50Run 15 goals in center production ( 00:10 ) 1 fileIgor Alekseev
13:00FMS triggers fro pA ( 00:20 ) 1 fileakio Ogawa

EEMC Calibration Using Mip

 

HFT preview data

 

STAR Management Meeting

2015-03-20 12:00
2015-03-20 13:30
America/New York
Friday, 20 March 2015
Meeting ID: 260125137, BNL room 1-189, at 16:00 (GMT), duration : 01:30
 
1) run14 production status and next in priority discussions 

2) run15 status 

3) BUR

STAR Management Meeting

2015-03-06 11:00
2015-03-06 12:30
America/New York
Friday, 6 March 2015
Meeting ID: 260125137, BNL room 1-189, at 16:00 (GMT), duration : 01:30
 Agenda: 

1) run14 production status/plan 
2) run15 status/ strategy 
    trigger/physics priority
    long/trans decision

3) collaboration meeting 
https://drupal.star.bnl.gov/STAR/meetings/star-collaboration-meeting-june-1-6-2015 

4) BUR team 
5) proposals 

STAR Management Meeting

2015-03-13 12:00
2015-03-13 13:30
America/New York
Friday, 13 March 2015
Meeting ID: 260125137, BNL room 1-189, at 16:00 (GMT), duration : 01:30
1) run14 production readiness/preproduction status
     HFT preview production, D0!!! 
     Draft of message to collaboration with more statistics. 
     plans
2) run15 status and strategy 
   a) projections
   b) pp longitudinal extension 
      (it seems that PHENIX still wants p+Al as "distinct priority")
   c) shift policy, 
    enforce the overlap shift for 8 hours, should we
    inform collaboration (due to travel and policy enforce in the middle of run)
3) proposals (iTPC further developments)
4) collaboration meeting (June) 
5) pre-QM meeting in Sept. 
    new proposal: SINAP hosts in Shanghai
TimeTalkPresenter
12:00SINAP proposal to host pre-QM STAR Collaboration meeting in Shanghai ( 00:20 ) 1 fileYG Ma

STAR Management Meeting

2015-02-27 11:00
2015-02-27 12:30
America/New York
Friday, 27 February 2015
Meeting ID: 260125137, BNL room 1-189, at 16:00 (GMT), duration : 01:30
Agenda: 

1) run14 production
2) run15 status
3)BUR
4) collaboration meeting 

I have to leave at noon sharp.