Run 15 pAu200 preliminary 2
Updated on Mon, 2015-05-11 16:29. Originally created by genevb on 2015-05-08 14:31.
Under:
The first preliminary calibration, using HFT only, found (x0,y0) = (0.096 ± 0.009, -0.272 ± 0.009), using a production of data from run 16125048. The HFT cannot, however, determine a beam tilt. Using the same data, with TPC-found primary vertices, I find similar (x0,y0) = (0.105 ± 0.007, -0.278 ± 0.007), which essentially agrees within errors.
The agreement gave me some confidence in the cuts I was using to remove pile-up:
Given the higher confidence in HFT results due to the absence of systematics from the TPC (e.g. pile-up, distortions), I will enter in the database the (x0,y0) from the HFT-based calibration, but the slopes from the TPC-based calibration: dx/dz = -0.00414 ± 0.00003, dy/dz = 0.00041 ± 0.00003.
-Gene
The agreement gave me some confidence in the cuts I was using to remove pile-up:
- multiplicity > 20
- BEMC matches > 1
- TOF matches > 0
- rank > -5
Given the higher confidence in HFT results due to the absence of systematics from the TPC (e.g. pile-up, distortions), I will enter in the database the (x0,y0) from the HFT-based calibration, but the slopes from the TPC-based calibration: dx/dz = -0.00414 ± 0.00003, dy/dz = 0.00041 ± 0.00003.
-Gene
»
- Printer-friendly version
- Login or register to post comments