iTPC


proposal draft (with link to bookpage)

SDU iTPC blog (Qinghu Xu)

Chinese iTPC project (part of Project 973 for RHIC physics)

STAR TPC

STAR TPC 2003 NIMA paper

mailing list: (itpc-l@lists.bnl.gov)

September 2016 NP iTPC review

September 2017 DOE Progress Review

  A talk on the iTPC was given to the instrumentation group on December 03 by FV. The talks is attached to this page.

 

 

 

TPC group meetings 2020-

Provide minutes or link to minutes of meetings held.

TPC activities for run 21

 At TPC meeting  (9/16) the misc activities needed for run21 was discussed
Page will be updated with progress.

iTPC QA run20

 This blog is intended to maintain a log of issues that will be identified as the
run progresses. For initial start the process will be as for run19. See earlier QA blog page

TPC summary for run19

 Following the run-19 there are are a number of actions that has to be done ahead of RUN-20

TPC summary for run19

 Following the run-19 there are are a number of actions that has to be done ahead of RUN-20

iTPC closeout review May 2, 2019

Final report and experts from the review were received on August 1, 2019
The three documents have been attached 

iTPC QA run 19

 
History of bad/DEAD FEEs and channels. Will be updated as run goes along (last July 15, 2019). Updated plot with corrected sinngle FEEs Jan 2022

iTPC sector 3 issue

 
The issue has been resolved. There was a cabling issue that resulted in outer sector voltage 1390V was applied to inner sector 1.

October 2018 DOE NP review

 Review was held at BNL

Here are the final reports

itpc talk for analysis meeting

 posted draft for Wed talk at analysis meeting


iTPC software

2018-11-15 11:00
2018-11-15 12:30
America/New York
Thursday, 15 November 2018
BNL 1-189, at 16:00 (GMT), duration : 01:30

Blue jeans info

 Phone Dial-in
+1.408.740.7256 (US (San Jose))
+1.888.240.2560 (US Toll Free)
+1.408.317.9253 (US (Primary, San Jose))
(Global Numbers)

Meeting ID: 533 957 3986
Moderator Passcode: 6253 

iTPC installation pictures

 Some pictures from installation

First two iTPC sector with mounted RDO and FEEs
courtesy  Bob Scheetz

star regional meeting

 Talks for regional meeting USTC October 31-Nov 2, 2018

a) iTPC installation and commisioning
b) TPC readiness discussion 

iTPC software

2018-10-23 11:00
2018-10-23 12:00
America/New York
Tuesday, 23 October 2018
1-189 Physics, at 15:00 (GMT), duration : 01:00
 Weekly software meeting.
Please add items to page before meeting

Bluejeans ID 481429146



SN0031 article 31

 SN0031

iTPC software

2018-08-07 11:00
2018-08-07 12:00
America/New York
Tuesday, 7 August 2018
BNL 1-189, at 15:00 (GMT), duration : 01:00
 Blue jeans information

I reserved bluejeans
Phone Dial-in
+1.408.740.7256 (US (San Jose))
+1.888.240.2560 (US Toll Free)
+1.408.317.9253 (US (Primary, San Jose))
(Global Numbers)

Meeting ID: 481 429 146


Room System
199.48.152.152 or bjn.vc

Meeting ID: 481 429 146
participiant can join w/o moderator.

TPC cosmic request

 Draft doc for request

SN0018 (Article 24)

 

Electronics Production Readiness Review

 An iTPC production readiness review was held on January 22, 2018

The agenda was:

Article 22 SN0017