- 2006 R&D
- Proposals
- Forward Upgrade Project
- HFT project
- Monthly Reports
- OPA mini review September 24 2013
- HFT Review July 12 , 2013
- CD0
- HFT 2014 Commisioning and Physics Run
- HFT BNL review Feb 15 2013
- HFT Management , including f2f meeting schedules
- HFT Related Publications
- HFT Sub-system IST
- HFT Sub-system Integration
- HFT Sub-system PXL
- HFT Sub-system SSD
- HFT annual OPA Review 2012
- HFT software meetings (overview)
- OPA CD-4 Close-out review July 31, 2014
- OPA mini-review October 2012
- post CD-4 documents
- HFT Internal reviews
- CD2-3 review
- CD1 documents final
- CD0 - dummy
- HFT+
- Related Meetings and Events
- Working Group Meeting Notes and Review reports
- Simulations
- 2007 R&D
- 2008 (FY09) R&D
- 2016 R&D
- Capital Equipment Requests for FY09
- STAR RD and upgrades for 2014
- STAR RD and upgrades for 2014
- eSTAR LoI Draft
- eSTAR Task Force
post CD-4 documents
Updated on Thu, 2015-11-19 18:18. Originally created by videbaks on 2015-03-03 17:47.
Under:
Following CD$ there has been a few follow-up reports. These reside on this page
The PXL group has created a report on the damage and repair plan for the PXL#2 detector. See word document
The project was also asked to update the transsition to ops document describing how to get to the optimum value.
This is attached below.
Quarterly meetings with DOE in FY15 to discuss progress
- January 9, 2015 presentation
- April 9, 2015 presentation
- July 9, 2015 presentation
- November12 presentation
At the November 12 meeting DOE acccepted that the UPP has been met, congratulated the efforts, and declared no further meetings are
required.
»