CD2-3 review

The CD2-3 review is scheduled for July 13-14, 2011 at BNL.

DOE documents will be place here as they are approved.

Technical Documents

  • Technical Design Report , June30  (TDR

DOE HFT Review july 13-14, 2011

 

      8:45 am    STAR and HFT Physics...................................................................... N. Xu, STAR spokesperson

     9:00 am      Project Overview.................................................................................... F. Videbaek

   10:00 am      Break

   10:15 am      Engineering Overview............................................................................. E. Anderssen

   10:40 am      PXL subsystem ........................................................................................ L. Greiner

   11:05 am      IST subsystem............................................................................................ G. van Nieuwenhuizen

   11:25 am      SSD subsystem......................................................................................... ..J. Thomas

   11:45 am      Integration and Safety Management........................................................ D. Beavis

   12:05 am     Cost & Scehdule .......................................................................................... S.Morgan

 

July 14              Close out presentation

 

Short close out report

Full (draft) report