Scans of the logbook for supersector tests may be downloaded here:
Excel file with data: drupal.star.bnl.gov/STAR/system/files/EPDCosmicData.xlsx
Test configuration 1
SS05
SS06
SS07
SS08
SS09
SS10
While running at BNL, it was noticed that there was a diagonal line when looking at the correlation between two tiles. Essentially, they would both fire, and with ADCs that are strongly correlated.
Figure 1: Example correlation between two tiles on the left, example correlation between a tile and the empty tile at tile "zero".
In Figure 1, we can see an example of this. As expected, one can see that pedestal and mip peak for each tile, completely uncorrelated with the signal in the other, except for the points along the diagonal. In fact, this was even seen in the first channel when running on evens (which we have called tile 0). Since there is no tile, or fiber, there is no way for there to be a signal.
The entire set of correlations can be seen at: drupal.star.bnl.gov/STAR/system/files/Histos12142017_EPD_Diagonal.pdf
It should be noted here that the last 4 tiles of the bottom SS were removed from the ADC in slot 7 to the empty ADC (given the labels blank0, etc). In fact, if we select events in which tile 0 in the top supersector had a significantly higher than pedestal value (adc > 250), we see that we can pull this diagonal correlation from all channels, other than those from the "empty" ADC: drupal.star.bnl.gov/STAR/system/files/Histos12142017_EPD_Diagonal_SelectedonTile0.pdf
What was noticed is that the last ADC, which had been empty, did not show this characteristic diagonal correlation. This is true even with the data being added to it. (We noted that the empty channels in the previously full ADC do show it, but none of the channels on the empty one showed it either before or after putting the data into the system). One difference was the timing, the first 4 ADCs were 28 ns behind. Another was that the logic feeding these ADCs, it looked sort of like the 4-fold coincidence was a 3-fold (at least it was firing more often than the other, and we could not put the level any higher in coincidence), so we moved this cables into a more stable one and verified that both sets now fired precisely the same. We also removed the 28 ns of extra cable, so everything was a the same timing.
After doing this, the diagonal correlation seems to go away:
Figure 2: Two correlations after our fix which do not seem to show the diagonal line.
In Figure 2, we do not see any evidence of this correlation. On the left is the correlation between tile 14 on the top and in the middle, so the correlation in the middle is from true cosmic rays. On the right is the correlation between tile 14 on the top and tile 6 in the middle. One can see the pedestal and MIP peaks for both, which are mostly uncorrelated as expected. (The few points in the middle could be from diagonal cosmics.)
The full range of correlations from these channels can be seen at: drupal.star.bnl.gov/STAR/system/files/Histos12152017_EPD_NoDiagonalProblem.pdf
This will be a page that aggregates information for calibrating the EPD.
Welcome to the EPD calibration page. From here, you can:
Sections generally provide links to more detailed information.
---------------------------------------------------------------------------------------------
Calibration Status
Done:
production_3p85GeV_fixedTarget_2019 | 3 | 2019 | FXT | 5 | https://drupal.star.bnl.gov/STAR/blog/eloyd/EPD-Calibration-Run-19-385GeV-FXT-dataset |
1. Generate picos
|
|
production_4p59GeV_fixedTarget_2019 | 3.2 | 2019 | FXT | 5 | 2. Fit all days | ||
production_7.3GeV_fixedTarget_2019 | 3.9 | 2019 | FXT | 5 | https://drupal.star.bnl.gov/STAR/blog/cracz/run-19-epd-calibrations-73-gev-fxt |
3. Troubleshoot problem tiles
|
|
production_31GeV_fixedTarget_2019 | 7.7 | 2019 | FXT | 5 | https://drupal.star.bnl.gov/STAR/blog/eloyd/EPD-Calibration-Run-19-31GeV-FXT-dataset |
4. Enter values into database
|
|
production_7p7GeV_2019 | 7.7 | 2019 | COL | 5 | |||
production_14p5GeV_2019 | 14.5 | 2019 | COL | 5 | |||
production_19GeV_2019 | 19 | 2019 | COL | 5 | |||
production_AuAu200_2019 | 200 | 2019 | COL | 1 | |||
production_5p75GeV_fixedTarget_2020 | 3.5 | 2020 | FXT | 5 | |||
production_7p3GeV_fixedTarget_2020 | 3.9 | 2020 | FXT | 5 | |||
production_9p8GeV_fixedTarget_2020 | 4.5 | 2020 | FXT | 5 | |||
production_13p5GeV_fixedTarget_2020 | 5.2 | 2020 | FXT | 5 | https://drupal.star.bnl.gov/STAR/blog/eloyd/EPD-Calibration-Run-20-13p5GeV-FXT-dataset | ||
production_19p5GeV_fixedTarget_2020 | 6.2 | 2020 | FXT | 5 | https://drupal.star.bnl.gov/STAR/blog/eloyd/EPD-Calibration-Run-20-19p5GeV-FXT-dataset | ||
production_26p5GeV_fixedTarget_2020 | 7.2 | 2020 | FXT | 5 | https://drupal.star.bnl.gov/STAR/blog/eloyd/EPD-Calibration-Run-20-26p5GeV-FXT-dataset | ||
production_31p2GeV_fixedTarget_2020 | 7.7 | 2020 | FXT | 5 | |||
production_11p5GeV_2020 | 11.5 | 2020 | COL | 5 | https://drupal.star.bnl.gov/STAR/blog/dchen/EPD-Calibration-Run20-11p5-GeV-AuAu | ||
2021 "live calibration" | 2021 | 4 | |||||
2022 "calibration" | 2022 | 2 | |||||
production_26p5GeV_fixedTarget_2020 | 7.2 | 2020 | 1 |
This is the current and past calibration status for the various runs in STAR. All runs will also show whether they are complete, in progress, or not yet started.
Run 22 Calibration Status
Run 21 Calibration Status
Run 20 calibrations:
Run 19 calibrations:
Run 18 calibrations:
---------------------------------------------------------------------------------------------
Calibration Process
The basics of calibration can be found here:
https://drupal.star.bnl.gov/STAR/blog/skk317/epd-calibration-isobar-final
Erik's slides on the process of calibration:
https://drupal.star.bnl.gov/STAR/blog/eloyd/EPD-Calibration-Procedure
There will be some updates to this based on more recent code, but this will get you started. Up to date code can be found here:
https://github.com/cdxing/EpdCalibration
https://colab.research.google.com/drive/1a_GEeXxQRDjgFs1E1CUSNY-vjRJYTAKM?usp=sharing
Meeting 28 May 2020 (830 am EST)
One important point: best START for QT32Bs is -8 and best START for QT32Cs is -20
1st iteration by Sam:
2nd iteration by Prashanth:
Added tile structure:
Dropbox link for log book:
https://www.dropbox.com/s/73ddkbhnmvpnpc1/vsp_gstar_071717.pdf?dl=0
3rd Iteration by Prashanth
Changes:
1. Tile coordinates are from Solid Works.
2. Implemented thinner part of the tiles.
3. More realistic tile 1
Blue are regular 1.2 cm thick tiles.
Green are thinner part of tiles.
Red Tile 1 lower side (Trapezoidal)
Magenta Tile 1 triangular part.
Here is the detail calculations:
Justin Ewigleben's studies
Saehanseul Oh
The first vertical cosmics results:
- Landau fits: STAR/system/files/userfiles/3886/ADC_SS252723_odd.pdf
- presentation: drupal.star.bnl.gov/STAR/system/files/TeChuan_EPD_cosmic_20171204_0.pdf
SS14081516 configuration:
Strips:
https://drupal.star.bnl.gov/STAR/system/files/SS14081516odd_Configuration1_Strips_FEE.pdf
https://drupal.star.bnl.gov/STAR/system/files/SS14081516odd_Configuration2_Strips_FEE.pdf
https://drupal.star.bnl.gov/STAR/system/files/SS14081516odd_Configuration3_Strips_FEE.pdf
https://drupal.star.bnl.gov/STAR/system/files/SS14081516even_Configuration1_Strips_FEE.pdf
https://drupal.star.bnl.gov/STAR/system/files/SS14081516even_Configuration2_Strips_FEE.pdf
https://drupal.star.bnl.gov/STAR/system/files/SS14081516even_Configuration3_Strips_FEE.pdf
ADCs:
https://drupal.star.bnl.gov/STAR/system/files/ADC_SS14081516.pdf
====================================================================================================
SS17181920 configuration:
Strips:
https://drupal.star.bnl.gov/STAR/system/files/SS17181920even_Configuration1_Strips_FEE.pdf
https://drupal.star.bnl.gov/STAR/system/files/SS17181920even_Configuration2_Strips_FEE.pdf
https://drupal.star.bnl.gov/STAR/system/files/SS17181920even_Configuration3_Strips_FEE.pdf
https://drupal.star.bnl.gov/STAR/system/files/SS17181920odd_Configuration1_Strips_FEE.pdf
https://drupal.star.bnl.gov/STAR/system/files/SS17181920odd_Configuration2_Strips_FEE.pdf
ADCs:
https://drupal.star.bnl.gov/STAR/system/files/ADC_SS17181920.pdf
presentation:
https://drupal.star.bnl.gov/STAR/system/files/TeChuan_EPD_cosmic_20170925_0.pdf
Jinyue Ju from USTC
Description and link | Decision/Result | EPD Calendar reminder date if action required |
Dark current oscillating in multiple channels |
Revisit after run19 | 2019-07-13 |
"Y joints" on fiber bundles breaking | Reinforcement design needed | 2019-06-17 |
Scattered cold tiles in QA plots | Replace QT32B daughter board | |
4-tile hole in <ADC> and <TAC> QA plots | Daughter card (EQ3,0x1C, DC2) replaced | |
Channel measuring cosmics out of Rx board, but blue in QA plots and not showing any MIP peaks | Bad QT32B connector (EQ1-0x10-C) replaced | |
EPD cable weight between Rx boards and QT boards | Regularly check cable tension between Rx and QT boards | 2019-06-17 |
Totally dead tile | Switched the connector from EQ1-0x1D-B channel 3 to EQ3-0x1D-D channel 1 | |
Totally dead tile | Fixed a bent ground pin | |
... | ... |
position on the East side (PP) | physical SS # | Fiber bundle # |
4 o'clock | 3 | 3 |
5 o'clock | 4 | 4 |
6 o'clock | 2 | 2 |
FEE # | tiles | one-wire ID |
---|---|---|
1 | PP 4 odd-numbered tiles | 0xFF00000007F6043A |
2 | PP 4 even-numbered tiles | 0xFE0000003263413A |
3 | PP 5 odd-numbered tiles | 0x0800000032C3333A |
4 | PP 5 even-numbered tiles | 0x1100000032C0493A |
5 | PP 6 odd-numbered tiles | 0x4800000032C04A3A |
6 | PP 6 even-numbered tiles | 0xA700000032C3423A |
Tile | FEE# = Rx# | FEE channel |
---|---|---|
1 | 1 | 0 |
3 | 1 | 1 |
5 | 1 | 2 |
7 | 1 | 3 |
9 | 1 | 4 |
11 | 1 | 5 |
13 | 1 | 6 |
15 | 1 | 7 |
17 | 1 | 8 |
19 | 1 | 9 |
21 | 1 | 10 |
23 | 1 | 11 |
25 | 1 | 12 |
27 | 1 | 13 |
29 | 1 | 14 |
31 | 1 | 15 |
2 | 2 | 1 |
4 | 2 | 2 |
6 | 2 | 3 |
8 | 2 | 4 |
10 | 2 | 5 |
12 | 2 | 6 |
14 | 2 | 7 |
16 | 2 | 8 |
18 | 2 | 9 |
20 | 2 | 10 |
22 | 2 | 11 |
24 | 2 | 12 |
26 | 2 | 13 |
28 | 2 | 14 |
30 | 2 | 15 |
Tile | FEE# = Rx# | FEE channel |
---|---|---|
1 | 3 | 0 |
3 | 3 | 1 |
5 | 3 | 2 |
7 | 3 | 3 |
9 | 3 | 4 |
11 | 3 | 5 |
13 | 3 | 6 |
15 | 3 | 7 |
17 | 3 | 8 |
19 | 3 | 9 |
21 | 3 | 10 |
23 | 3 | 11 |
25 | 3 | 12 |
27 | 3 | 13 |
29 | 3 | 14 |
31 | 3 | 15 |
2 | 4 | 1 |
4 | 4 | 2 |
6 | 4 | 3 |
8 | 4 | 4 |
10 | 4 | 5 |
12 | 4 | 6 |
14 | 4 | 7 |
16 | 4 | 8 |
18 | 4 | 9 |
20 | 4 | 10 |
22 | 4 | 11 |
24 | 4 | 12 |
26 | 4 | 13 |
28 | 4 | 14 |
30 | 4 | 15 |
Tile | FEE# = Rx# | FEE channel |
---|---|---|
1 | 5 | 0 |
3 | 5 | 1 |
5 | 5 | 2 |
7 | 5 | 3 |
9 | 5 | 4 |
11 | 5 | 5 |
13 | 5 | 6 |
15 | 5 | 7 |
17 | 5 | 8 |
19 | 5 | 9 |
21 | 5 | 10 |
23 | 5 | 11 |
25 | 5 | 12 |
27 | 5 | 13 |
29 | 5 | 14 |
31 | 5 | 15 |
2 | 6 | 1 |
4 | 6 | 2 |
6 | 6 | 3 |
8 | 6 | 4 |
10 | 6 | 5 |
12 | 6 | 6 |
14 | 6 | 7 |
16 | 6 | 8 |
18 | 6 | 9 |
20 | 6 | 10 |
22 | 6 | 11 |
24 | 6 | 12 |
26 | 6 | 13 |
28 | 6 | 14 |
30 | 6 | 15 |
There has been frequent mapping and swapping etc. Things can get confusing. This is the mapping as of 25 May 2017, and we (tentatively) plan to keep it this way at least through the Au+Au 53 GeV running. (Edit: nope, we remapped one more time. See drupal.star.bnl.gov/STAR/subsys/epd/mapping/mapping-53-gev-auau-run-30-may-2017)
And, just for kicks, an additional complication is the signal from PP4TT15 is being split between a QT32B[with TAC] (0x18 ADC/TAC=8/12) and a QT32 C (0x16 ADC/TAC=19/23).
Steve Valentino made a very nice "cheat sheet" showing QTs 0x18 and 0x16, shown here:
I have made two maps showing these maps from the "detector point of view." The first one shows simply the "Universal ID" which is 100*PP+TT (both numbering starting at 1), and the second one shows also the QT address and QT channels (starting from zero) of the ADC and TAC. A TAC address of -1000 means there is no TAC. They are below. If you need to use these maps, you may want to download the file (see bottom of page) in pdf or png, and blow them up.
Per request from database admin Dmitry Arkhipkin <arkhipkin@bnl.gov>
https://drupal.star.bnl.gov/STAR/comp/db/how-to-user/new-table/
Here is the updated blog with the latest fields:
https://drupal.star.bnl.gov/STAR/blog/sprastar/epd-offline-db-table-updated
Following page is created:
https://drupal.star.bnl.gov/STAR/blog/sprastar/epd-offline-db-table
Dmitry has created the database for us, database explore is here:
https://online.star.bnl.gov/dbExplorer/
Entry History in tables:
Following entries erased after modigfication of tables{
* Geometry/epd/epdQTMap 2016-12-10 00:00:00 => sim initialization for year 2017
* Geometry/epd/epdQTMap 2016-12-20 00:00:00 => ofl initialization for year 2017
* Geometry/epd/epdQTMap 2017-02-13 12:00:00 => 1st cable mapping completed
* Geometry/epd/epdQTMap 2017-04-05 12:00:00 => QTB 0x18 and QTC 0x16 are swapped
* Geometry/epd/epdQTMap 2017-05-03 12:00:00 => QTC 0x16 are swapped PP5 Tile 10 and PP5 Tile 14 are swapped
* Geometry/epd/epdQTMap 2017-05-17 12:00:00 => Many changes drupal.star.bnl.gov/STAR/system/files/CableSwap_05172017.pdf
* Calibrations/epd/status 2017-05-30 12:00:00 => (inserted on 08/23/17)Updated the mapping, which is used for 54.4 GeV run
* Calibrations/epd/status 2016-12-10 00:00:00 => sim initialization for year 2017 (inserted on 08/23/17)
* Calibrations/epd/status 2016-12-20 00:00:00 => ofl initialization for year 2017 (inserted on 08/23/17)
* Geometry/epd/epdFEEMap 2016-12-20 00:00:00 => sim initialization for year 2017 (inserted on 08/23/17), 1-wire ID has the 54.4 GeV values
* Geometry/epd/epdFEEMap 2016-12-20 00:00:00 => ofl initialization for year 2017 (inserted on 08/23/17), 1-wire ID has the 54.4 GeV values
* Calibrations/epd/epdGain 2016-12-20 00:00:00 => sim initialization for year 2017 (inserted on 08/24/17)
* Calibrations/epd/epdGain 2016-12-20 00:00:00 => ofl initialization for year 2017 (inserted on 08/24/17)} Current entries:
* Geometry/epd/epdQTMap 2016-12-10 00:00:00 => sim initialization for year 2017
* Geometry/epd/epdQTMap 2016-12-20 00:00:00 => ofl initialization for year 2017
* Geometry/epd/epdFeeMap 2016-12-10 00:00:00 => ofl initialization for year 2017
* Geometry/epd/epdFeeMap 2016-12-10 00:00:00 => sim initialization for year 2017
* Geometry/epd/epdStatus 2016-12-10 00:00:00 => ofl initialization for year 2017
* Geometry/epd/epdStatus 2016-12-10 00:00:00 => sim initialization for year 2017
* Geometry/epd/epdGain 2016-12-10 00:00:00 => sim initialization for year 2017
* Geometry/epd/epdGain 2016-12-10 00:00:00 => ofl initialization for year 2017
* Geometry/epd/epdStatus 2017-02-08 00:00:00 => Completed 1st cabling
* Geometry/epd/epdFeeMap 2017-02-08 00:00:00 => Completed 1st cabling
* Geometry/epd/epdFeeMap 2017-02-08 00:00:00 => Completed 1st cabling
No | Run No | Voltages: Vset / Vbias (*) | Prashanth's initial results | Mike's Results |
1 | 18089047 | 56.5 / 58.3 | Bias Scan | drupal.star.bnl.gov/STAR/system/files/BiasScan.pdf See below for analysis |
2 | 18089055 | 55.5 / 57.3 | ||
3 | 18089063 | 57.5 / 59.3 | ||
4 | 18089065 | 54.5 / 56.3 | ||
5 | 18090003 | 58.5 / 60.3 |
Eleanor has given following information to start with:
%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%
%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%%
pedasphys configuration is copied to epdbitcheck_pedasphys
Tier1 file is changed to trg_170414_EPQ_AlgoX_OLX.bin
EPQ_Algorithm_Latch changed from 1 to 7 in 1 unit steps
for each of above steps following output latch is changed
EPD_QT_Output_Latch_Delay 0 to 120 in 20 steps
EPD_QTc_Output_Latch_Delay 0 to 120 in 20 steps
No | Run Number TAC min =50 |
Run Number TAC min =80 |
Run Number QTB TAC min =80 QTC TAC min =40
|
Run Number QTB TAC min =80 QTC TAC min =47 |
Run Number QTB TAC min =82 QTB ADC TH=80 QTC TAC min =40 |
EPQ_Algorithm_Latch (for QTB & QTC) |
EPD_QT_Output_Latch_Delay (for QTB & QTC) |
% Miss match 0x18 Algo v5.2 |
% Miss match 0x16 Algo v6.d |
% Miss match 0x12 Algo v6.4 |
% Miss match 0x10 Algo v6.4 |
1 | 18129066 | 18130041 | 18131026 | 18150036 | 18158037 | 1 | 0 | ||||
2 | 18129067 | 18130042 | 18131027 | 18150037 | 18158038 | 1 | 20 | ||||
3 | 18129068 | 18130043 | 18131028 | 18150038 | 18158039 | 1 | 40 | ||||
4 | 18129069 | 18130044 | 18131029 | 18150039 | 18158040 | 1 | 60 | ||||
5 | 18129070 | 18130045 | 18131030 | 18150040 | 18158041 | 1 | 80 | ||||
6 | 18129071 | 18130046 | 18131031 | 18150041 | 18158042 | 1 | 100 | ||||
7 | 18129072 | 18130047 | 18131032 | 18150042 | 18158043 | 1 | 120 | ||||
8 | 18129073 | 18130048 | 18131059 | 18150043 | 18158044 | 2 | 0 | ||||
9 | 18129074 | 18130049 | 18131060 | 18150044 | 18158045 | 2 | 20 | ||||
10 | 18129075 | 18130050 | 18131061 | 18150045 | 18158046 | 2 | 40 | ||||
11 | 18129076 | 18130051 | 18131062 | 18150046 | 18158047 | 2 | 60 | ||||
12 | 18129077 | 18130052 | 18131063 | 18150047 | 18158048 | 2 | 80 | ||||
13 | 18129078 | 18130053 | 18131064 | 18150048 | 18158049 | 2 | 100 | ||||
14 | 18129079 | 18130054 | 18131065 | 18150049 | 18158050 | 2 | 120 | ||||
15 | 18129080 | 18130055 | 18131066 | 18150050 | 18158051 | 3 | 0 | ||||
16 | 18129081 | 18130056 | 18131067 | 18150051 | 18158052 | 3 | 20 | ||||
17 | 18129082 | 18130057 | 18131068 | 18150052 | 18158053 | 3 | 40 | ||||
18 | 18129083 | 18130058 | 18131069 | 18150053 | 18158054 | 3 | 60 | ||||
19 | 18129084 | 18130059 | 18131070 | 18150054 | 18158055 | 3 | 80 | ||||
20 | 18129085 | 18130060 | 18131071 | 18150055 | 18158056 | 3 | 100 | ||||
21 | 18129086 | 18130061 | 18131072 | 18150056 | 18158057 | 3 | 120 | ||||
22 | 18129061 | 18130062 | 18131033 | 18150057 | 18158058 | 4 | 0 | ||||
23 | 18129062 | 18130063 | 18131034 | 18150058 | 18158059 | 4 | 20 | ||||
24 | 18129063 | 18130064 | 18131035 | 18150059 | 18158060 | 4 | 40 | ||||
25 | 18129064 | 18130065 | 18131036 | 18150060 | 18158061 | 4 | 60 | ||||
26 | 18129065 | 18130066 | 18131037 | 18150061 | 18158062 | 4 | 80 | ||||
27 | 18129059 | 18130067 | 18131038 | 18150062 | 18158063 | 4 | 100 | ||||
28 | 18129060 | 18130068 | 18131039 | 18150063 | 18158064 | 4 | 120 | ||||
29 | 18129087 | 18130069 | 18131073 | 18150064 | 18158072 | 5 | 0 | ||||
30 | 18129088 | 18130070 | 18131074 | 18150065 | 18158073 | 5 | 20 | ||||
31 | 18129089 | 18130071 | 18131075 | 18150066 | 18158074 | 5 | 40 | ||||
32 | 18129090 | 18130072 | 18131076 | 18150067 | 18158075 | 5 | 60 | ||||
33 | 18129091 | 18130073 | 18131077 | 18150068 | 18158076 | 5 | 80 | ||||
34 | 18129092 | 18130074 | 18131078 | 18150069 | 18158077 | 5 | 100 | ||||
35 | 18129093 | 18130075 | 18131079 | 18150070 | 18158078 | 5 | 120 | ||||
36 | 18129094 | 18130076 | 18131040 | 18150071 | 18158079 | 6 | 0 | ||||
37 | 18129095 | 18130077 | 18131041 | 18150072 | 18158080 | 6 | 20 | ||||
38 | 18129096 | 18130078 | 18131042 | 18150073 | 18158081 | 6 | 40 | ||||
39 | 18129097 | 18130079 | 18131043 | 18150074 | 18158082 | 6 | 60 | ||||
40 | 18129098 | 18130080 | 18131044 | 18150075 | 18158083 | 6 | 80 | ||||
41 | 18129099 | 18130081 | 18131045 | 18150076 | 18158084 | 6 | 100 | ||||
42 | 18129100 | 18130082 | 18131046 | 18150077 | 18158085 | 6 | 120 | ||||
43 | 18130083 | 18131080 | 18150078 | 18158086 | 7 | 0 | |||||
44 | 18130084 | 18131081 | 18150079 | 18158087 | 7 | 20 | |||||
45 | 18130085 | 18131082 | 18150080 | 18158088 | 7 | 40 | |||||
46 | 18130086 | 18131083 | 18150081 | 18158089 | 7 | 60 | |||||
47 | 18130087 | 18131084 | 18150082 | 18158090 | 7 | 80 | |||||
48 | 18130088 | 18131085 | 18150083 | 18158091 | 7 | 100 | |||||
49 | 18130089 | 18131086 | 18150084 | 18158092 | 7 | 120 |
Following is worked out by Valentino, Stephen <svalentino@bnl.gov>
Following runs are taken
Gate values are set to best values in following runs.
Run Number | QTB Discriminator Threshold | QTC_Discriminator_Threshold | |
1 | 18116044 | 16 (0x00F) = 8 mV | 64(0x03F) = 11 mV |
2 | 18116047 | 32 (0x01F) = 14 mV | 128(0x07F) = 28 mV |
3 | 18118021 | 24 (0x017) = 11 mV (linear interpolation) | 96(0x05F) = 19.5 mV (linear interpolation) |
Phase II | |||
4 | |||
Here is first analysis:
drupal.star.bnl.gov/STAR/system/files/EPD_ThresholdScan_Prashanth_05012017.pdf
#EPD Trigger is present in all following runs(i.e. +BBC_TAC +BBC_E + BBC_W) Timing Scan -----------
Pre-Post | Run# | QTb Start | QTb End | QTc Start | QTc End | TAC Stop |
Pre=2, Post=2 | 18066043 | 8 | 24 | not precent | not precent | 48 |
Pre=2, Post=0 | 18076064 | 0 | 16 | 0 | 16 | 56 |
Pre=0, Post=2 | 18076065 | 0 | 16 | 0 | 16 | 56 |
No | Run Number | Gate Start QT 32 b | Gate End QT 32 b | Gate Start QT 32 c | Gate End QT 32 c | TAC Stop | Data Start Address | Initial Study by Prashanth | Mike's PrePost study and Comments |
1 | 18078043 | 0 | 16 | 0 | 16 | 56 | c=8, b=8 | EPD_plots_18078043.pdf | PrePost=-1 1st run of the fill |
2 | 18078044 | 4 | 20 | 4 | 20 | 56 | c=8, b=8 | EPD_plots_18078044.pdf | PrePost=-1 |
3 | 18078045 | 8 | 24 | 8 | 24 | 56 | c=8, b=8 | EPD_plots_18078045.pdf | PrePost=0 |
4 | 18078046 | 12 | 28 | 12 | 28 | 56 | c=8, b=8 | EPD_plots_18078046.pdf | PrePost=0 |
5 | 18078047 | 16 | 32 | 16 | 32 | 56 | c=8, b=8 | EPD_plots_18078047.pdf | This run was stopped for beam squeeze |
6 | 18078048 | 16 | 32 | 16 | 32 | 56 | c=8, b=8 | EPD_plots_18078048.pdf | PrePost=0 |
7 | 18078049 | 20 | 36 | 20 | 36 | 56 | c=8, b=8 | EPD_plots_18078049.pdf | stopped for polarization measurements |
8 | 18078050 | 20 | 36 | 20 | 36 | 56 | c=8, b=8 | EPD_plots_18078050.pdf | PrePost=0 |
9 | 18078051 | 24 | 40 | 24 | 40 | 56 | c=8, b=8 | EPD_plots_18078051.pdf | PrePost=0 |
10 | 18078052 | 28 | 44 | 28 | 44 | 56 | c=8, b=8 | EPD_plots_18078052.pdf | PrePost=0 Taken By Yang Wu |
11 | 18078053 | 32 | 48 | 32 | 48 | 56 | c=8, b=8 | EPD_plots_18078053.pdf | PrePost=0 |
12 | 18078054 | 36 | 52 | 36 | 52 | 56 | c=8, b=8 | EPD_plots_18078054.pdf | PrePost=0 |
13 | 18078056 | 40 | 56 | 40 | 56 | 56 | c=8, b=8 | EPD_plots_18078056.pdf | PrePost probably 0 (bad stats) |
14 | 18078057 |
44 | 60 | 44 | 60 | 56 | c=8, b=8 | EPD_plots_18078057.pdf | PrePost probably 0 (out of gate) |
15 | 18078058 | 48 | 64 | 48 | 64 | 56 | c=8, b=8 | EPD_plots_18078058.pdf | PrePost=0? or 1? |
c=8, b=8 | |||||||||
Negative Scan | |||||||||
16 | 18082042 | 0 | 16 | 0 | 16 | 56 | c=8, b=8 | EPD_plots_18082042.pdf | QT32b in PrePost=-1 QT32c in PrePost=0 |
17 | 18082043 |
107(0) | 123(16) | 107(0) | 123(16) | 56 | c=8, b=8 | EPD_plots_18082043.pdf | QT32b in PrePost=-1 QT32c in PrePost=0 |
18 | 18082044 | 103(-4) | 119(12) | 103(-4) | 119(12) | 56 | c=8, b=8 | EPD_plots_18082044.pdf | QT32b in PrePost=-1 QT32c in PrePost=0 |
19 | 18082045 | 99(-8) | 115(8) | 99(-8) | 115(8) | 56 | c=8, b=8 | EPD_plots_18082045.pdf | QT32b in PrePost=-1 QT32c in PrePost=0 |
20 | 18082046 | 95(-12) | 111(4) | 95(-12) | 111(4) | 56 | c=8, b=8 | EPD_plots_18082046.pdf | QT32b in PrePost=-1 QT32c in PrePost=0 |
21 | 18082047 | 91(-16) | 107(0) | 91(-16) | 107(0) | 56 | c=8, b=8 | EPD_plots_18082047.pdf | QT32b in PrePost=-1 QT32c in PrePost=0 |
22 | 18089004 | 87(-20) | 103(-4) | 87(-20) | 103(-4) | 56 | c=8, b=8 |
EPD_plots_18089004.pdf | |
23 | 18089007 | 83(-24) | 99(-8) | 83(-24) | 99(-8) | 56 | c=8, b=8 |
EPD_plots_18089007.pdf | |
24 | 18089008 | 79(-28) | 95(-12) | 79(-28) | 95(-12) | 56 | c=8, b=8 |
EPD_plots_18089008.pdf | |
25 | 18089009 | 75(-32) | 91(-16) | 75(-32) | 91(-16) | 56 | c=8, b=8 |
EPD_plots_18089009.pdf | |
26 | 18089010 | 99(-8) | 115(8) | 99(-8) | 115(8) | 56 | c=8, b=7 |
EPD_plots_18089010.pdf | |
27 | 18089013 | 99(-8) | 115(8) | 99(-8) | 115(8) | 56 | c=8, b=9 |
EPD_plots_18089013.pdf |
QT32c
Gate (STAR,STOP) = (0,16)prepost =0 Gate (STAR,STOP) = (4,20) |
vs. |
QT32b
Gate (STAR,STOP) = (0,16)Prepost=-1 Gate (STAR,STOP) = (4,20) Gate (STAR,STOP) = (8,24) Gate (STAR,STOP) = (12,28) |
E-Scope connections
03/24/2017
CH#1 => PP4_tile_1 (no-split, 50 ohm)
CH#3 => QT32b board 0x18 gate
Please see attaced image:PP_6_tile_1_nosplit.pdf, which shows a cosmic ray pules and QT gate.
04/03/2017
Following scope traces are acquired during beamin in RHIC.
THreshold = 8mV
CH#1 of scop to PP6 Tile 1 no split, 50 ohm termination)
CH#3 => QT32b board 0x10 gate
Please see
04/04/2017
Following scope traces are acquired during beamin in RHIC.
THreshold = 4mV
CH#1 of scop to PP6 Tile 1 no split, 50 ohm termination)
CH#3 => QT32b board 0x10 gate
Please see https://drupal.star.bnl.gov/STAR/system/files/scopetracesPP6T1_nosplit_4mV.pdf
04/04/2017
Following scope traces are acquired during beamin in RHIC.
THreshold = 4mV && persistent
CH#1 of scop to PP6 Tile 1 no split, 50 ohm termination)
CH#3 => QT32b board 0x10 gate
Please see : https://drupal.star.bnl.gov/STAR/system/files/scopetracesPP6T1_nosplit_4mV_persistent.pdf
Isobar run by run QA: drupal.star.bnl.gov/STAR/blog/jewigleb/epd-isobar-2018-run-list
EPD uses 1C2 and 1C3 racks in the south platform:
Here is the drawing of the racks:
EPD Trigger is very similar to BBC, except EPD uses hit count instead of ADC sum for trigger.
Trigger layers:
Useful links:
EPD trigger shows some mismatch (few percent to 20%) from QTC to L0 DSM.
Issue is more likely the Algorithm and/or output latch issues and can not be hardware issue (Many thanks to Steve and Jack fixing hardware issues).
Current Tier1 file is set to provide EPD-E, EPD-W and EPD-TAC
To test the trigger capabilities of EPD following runs are taken only with triggers: EPD-E + EPD-W + EPD-TAC
19075034 (short run)
19075035 (long run)
19075053 (during the vernier scan, very long run)
Following thresholds are used in above runs:
Following are some QA plots from run 19075035
EPD TAC difference East vs. West | (a)Earliest TAC East, (b) Earliest TAC west, (c) TAC diff. Blue histo is calculated from QTs and Red is from EP101 So the difference between red and blue tells the bits mis-match! |
Hit count from Ep101, Note that we have 108 TAC channles | Top left panel is for BBC only, rest compare BBC with EPD |
Applied cut is doing its job on selecting events from ~30 cm cut.
Now the issues:
EP001 and EP002 shows earliest TAC of 0x20, 0x800 and 0x820 for east and west for about 5-20% of the time for all the QTC boards.
Please following bit map check plot, plot compares mis-match from QTC algorithm against bits received by EP001/2. Bits mismatch at 0x20, 0x800 and 0x820 clearly visible.
For 19075034
This gives peak TAC difference centered around 4096 (0x800-0x800 or 0x820=0x820 or 0x20-0x20, plus 4096)
and 0x20 above and below 4096 for 0x800 and 0x820 combos.
Following plot from low statistic run 19075034
We confirmed that when there is no good hit in QT, no output is generated from QT algorithm or in EP001/2.
Current proposal is to include EPD trigger in production running with limited band with and play with QT algo latches and output latches.
Any thoughts, comments or suggestions?
Position | OSU SS # | Lehigh FB# | FEE# (odd) | FEE# (even) | SiPM# (odd) | SiPM# (even) | Comments/issues | |
---|---|---|---|---|---|---|---|---|
East PP01 | 21 | 13 | 04 | 47 | 13 | 59 | ||
East PP02 | 23 | 23 | 05 | 52 | 43 | 53 | ||
East PP03 | 20 | 20 | 11 | 46 | 47 | 57 | ||
East PP04 | 22 | 15 | 10 | 41 | 51 | 52 | ||
East PP05 | 14 | 05 | 14 | 21 | 19 | 06 | ||
East PP06 | 29 | 18 | 12 | 20 | 50 | 49 | ||
East PP07 | 25 | 08 | 44 | 42 | 02 | 11 | |
|
East PP08 | 24 | 24 | 49 | 60 | 56 | 12 | ||
East PP09 | 01 | 27 | 58 | 48 | 46 | 55 | ||
East PP10 | 05 | 14 | 51 | 55 | 26 | |
SiPM#28 was bad; replaced | |
East PP11 | 06 | 21 | 01 | 53 | ??????? | 58 | odd SiPM# not recorded | |
East PP12 | 31 | 01 | 50 | 59 | 27 | 29 | ||
West PP01 | 15 | 04 | 22 | 15 | 15 | 14 | ||
West PP02 | 19 | 03 | 17 | 19 | 35 | 25 | ||
West PP03 | 12 | 11 | 28 | 24 | 24 | 34 | ||
West PP04 | 11 | 02 | 07 | 29 | 37 | 36 | ||
West PP05 | 30 | 16 | 25 | 16 | 18 | 21 | ||
West PP06 | 27 | 26 | 38 | 02 | 10 | 60 | ||
West PP07 | 07 | 10 | 23 | 57 | 22 | 08 | ||
West PP08 | 09 | 07 | 26 | 43 | 16 | 09 | ||
West PP09 | 02 | 17 | 32 | 56 | 20 | 38 | |
|
West PP10 | 04 | 09 | 27 | 30 | 33 | 05 | ||
West PP11 | 10 | 06 | 31 | 40 | 04 | 07 | ||
West PP12 | 03 | 19 | 45 | 37 | 23 | 03 |
Not listed in the table above (i.e. not used in run 2018):
Here is a handy map to help reproduce the fiber placement in run 2019. A high-resolution PDF file is here: drupal.star.bnl.gov/STAR/system/files/Setup2018.pdf
Here are some scope traces took on Feb 26, 2019, with beam:
1. Verify proper mapping from TUFF to StEvent (tests databases, cabling...) ("Seven Patterns" test) - DONE
We followed the instructions listed at: drupal.star.bnl.gov/STAR/subsys/epd/operations-2018/pre-and-post-beam-commissioning
2. Vped adjustment - DONE
The instructions written for this year can be found at: drupal.star.bnl.gov/STAR/blog/rjreed/epd-vped-scans-2019
3. Verifying fiber mapping/pre-post
In 2018 we verified the pre-post by running special runs. It was noted this year that if we are in the right bunch crossing, we should see the epd-bbc correlation. If not, then we will not.
In progress: *.daq files have been requested from HPSS and restored to NFS. Then the bfc.C has been run, creating pico/MuDsts. These need to be analyzed.
Nominal Values for 2018 were
B Gate End = 48
B Gate Start = 32
C Gate End = 39
C Gate Start = 23
TAC Stop = 64
This page collects the most important "free-standing" documents for the Event Plane Detector.
Logbook | links |
---|---|
OSU Supersector Construction Logbook (2017) | online google doc (do not edit!) / pdf file (printout of google doc) / .docx file |
EPD BNL Logbook (2016-2018) | 01-40, 42-49, 51-96, 97-123 |
OSU Supersector Testing Logbook (2017) | 01-49, 50-99, 100-149, 150-159, 160, 161-174 |
FB# | Status | Comments | Average | Max | Full Sheet |
1 | Healthy | First bundle; repolished twice | -63% | -68% | FB01 |
2 | Healthy | Results from 2nd test; avg unchanged from first test | -55% | -62% | FB02 |
3 | Healthy | -54% | -67% | FB03 | |
4 | Healthy | -63% | -73% | FB04 | |
5 | Healthy | -62% | -71% | FB05 | |
6 | Healthy | Repolished once | -62% | -68% | FB06 |
7 | Healthy | -61% | -73% | FB07 | |
8 | Healthy | Repolished 3 times | -63% | -72% | FB08 |
9 | Healthy | -64% | -71% | FB09 | |
10 | Healthy | -62% | -68% | FB10 | |
11 | Healthy | -62% | -73% | FB11 | |
13 | Healthy | Repolished 3 times | -64.8% | -73% | FB13 |
14 | Healthy | -62% | -73% | FB14 | |
15 | Healthy | -62% | -73% | FB15 | |
16 | Healthy | -62% | -73% | FB16 | |
17 | Healthy | -63% | -70% | FB17 | |
18 | Healthy | -61% | -69% | FB18 | |
19 | Healthy | -63% | -68% | FB19 | |
20 | Healthy | Repolished twice | -64% | -69% | FB20 |
21 | Healthy | -64% | -72% | FB21 | |
23 | Healthy | Repolished once | -63% | -72% | FB23 |
24 | Healthy | -63% | -74.6% | FB24 | |
26 | Healthy | -62% | -66% | FB26 | |
27 | Healthy | -57% | -68% | FB27 |
FB# | Status | Comments | Average | Max | Full Sheet |
22 | Injured | Failing upon retest. Not sure what's going on | -61% | -77% | FB22 |
12 | Injured | Single fiber glows on both ends, possibly cracked | N/A | N/A | N/A |
28 | Injured | Failing final test. Also even/odd difference of 6% | -61% | -78% | FB28 |
USTC has done a fantastic job of collecting and systematically posting their QA and characterization tests here. They cover
SS | status | comments | ADC spectra |
1 | healthy | hey, our much-maligned "first pancake" actually looks great! | 160131 |
2 | healthy | 020304 | |
3 | healthy | 020304 | |
4 | healthy | a bit less light than some others, but it worked well in run 2017 | 020304 |
5 | healthy | (taking another look at TT26 jan2018, to be sure, but it's fine) | 08050607 |
6 | healthy | (taking another look at TT26 jan2018, to be sure, but it's fine) | 08050607 |
7 | healthy | 08181007 | |
8 | injured | TT05 very low gain, probably unusable | 14081516 |
9 | healthy | TT03 has low gain | 06091417 |
10 | healthy | 08181007 | |
11 | healthy | 09111213 | |
12 | healthy | ADC spectra in test looked a little strange | 09111213 |
13 | injured | MAY be usable. X-talk b/t TT01,03; glued WLS fibers | 09111213 |
14 | healthy | 06091417 | |
15 | healthy | ADC spectrum for TT20 a little strange; see notes | 14081516 |
16 | injured | TT02 has very low gain. Had suspected paint on fiber end, but problem persists after cleaning | 161731 |
17 | prob. healthy | Joey should comment on X-talk issue; see health sheet | 161731 |
18 | injured | TT03 broke during construction. low gain. PERHAPS viable | 08181007 |
19 | healthy | 17181920 | |
20 | healthy | 17181920 | |
21 | healthy | TT21 ADC distribution a bit abnormal | 212930 |
22 | healthy | 21222426 | |
23 | healthy | 252723 | |
24 | healthy | 21222426 | |
25 | healthy | 252723 | |
26 | healthy enough |
TT03 has rather low gain, but probably usable. I'm comfortable with this in the experiment. | 21222426 |
27 | healthy | see notes for comments on TT24,25,27-31 | 252723 |
28 | dead | dropped and broken in pieces :-( | |
29 | healthy | TT27 has low gain | 212930 |
30 | healthy | 212930 | |
31 | healthy | 161731 |
Attaced (ScopeTraces_beforeTimeIn.pdf) is scope traces before timing in, taken during beam in RHIC